3_Rates & Regulatory_LABRAYCANNON Updated:2015-08-06 15:26 CS

Download Report

Transcript 3_Rates & Regulatory_LABRAYCANNON Updated:2015-08-06 15:26 CS

Rates & Regulatory
Updates
Topics Covered
Rate Updates
– Transmission Rates:
• 2015 Annual Update
Regulatory Updates
2
2015 Annual Update
Annual Update - May 15, 2015
• Schedule 1 rate (0.77 $/kW-year) effective June 1, 2015 –
May 31, 2016
• 2015 Projected rate (28.51 $/kW-year) effective June 1,
2015 – May 31, 2016 for Schedules 7, 8, and NITS rates
• 2014 True-up rate (25.52 $/kW-year) for Schedules 7, 8,
and NITS rates charged in CY 2014
– January – May (2013 Projection): 25.86 $/kW-year
– June – December (2014 Projection): 27.54 $/kW-year
3
OASIS Postings:
Currently Effective Rates
Annual Update Information
• Informational Filing at
FERC [Docket No. ER113643]
• Open Access Same-Time
Information System
www.oasis.oati.com/ppw/
[Documents > PacifiCorp
OASIS Tariff/Company
Information > OATT Pricing >
2015 Transmission Formula
Annual Update]
• July 10, 2015 – Annual
Update Customer Meeting
5
Regulatory Updates
• Peak Reliability alternative funding agreement approved June
10, 2015.
• FERC Notice of Proposed Rulemaking to approve 7 CIP
Standards on cybersecurity.
• NERC submitted compliance filing on Risk-Based Registration
with proposal to eliminate Load-Serving Entity (LSE) function.
• AWEA petition to reform Large Generator Interconnection
Procedures and Agreements.