Definition of a PDR
NCSX
PDR (pe’de-ar) n. 1. A project-level DOE review to
determine if the maturity of the project’s design and
cost and schedule estimates is adequate to establish
the performance baseline. 2. A subsystem-level
internal review to determine if all the deliverables for
Preliminary Design have been satisfactorily
completed.
The June PDR will be both a project-level DOE review
and a subsystem-level internal review of the Vacuum
Vessel (WBS 12) and the Modular Coils (WBS 14)
21 March 2003
Reiersen - 2
NCSX
Requirements for the project
level DOE review
We need to establish the Preliminary Design Baseline
• Update the design of the stellarator core to reflect
configuration changes since the CDR and incorporate the
new modular coil design and vacuum vessel design
• Update the design of ancillary systems consistent with the
updated stellarator core design
• Update all cost and schedule estimates
We need to document the Preliminary Design Baseline
• Write a Preliminary Design Report (similar to CDR)
• Provide backup documentation for cost and schedule
estimates
21 March 2003
Reiersen - 3
Requirements for an internal PDR
NCSX
Performance requirements have been defined
A design has been developed that fully meets those requirements
All feasibility issues have been resolved
Interfaces with other systems have been fully defined
Plans for assembly, installation, and test are established
Models and drawings have been developed, reviewed, and
released at the Preliminary Design level
Activities needed to address PDR requirements for the VV and
modular coils should be identified in the SEMLs
21 March 2003
Reiersen - 4
Foundational milestones
NCSX
Define geometry of stellarator core (21 Feb)
• Modular coil design from Physics (16 Dec)
• Winding pack geometry (17 Jan)
• MC shell and VV geometry (14 Feb)
• TF/PF geometry (21 Feb)
Define turns and current waveforms (14 Mar)
Perform flexibility studies (11 Apr)
21 March 2003
Reiersen - 5
Key VV PD milestones
NCSX
representative dates
Prepare performance specification (28 Feb)
Finalize port geometry consistent with diagnostic viewing
requirements (14 Mar)
Design closure joint (14 Mar)
Establish envelopes and location for in-vessel components (4 Apr)
Establish port allocations (18 Apr)
Complete FMECA, structural, and thermal analyses (25 Apr)
Prepare ICDs (9 May)
Perform mfg development activities for PDR (9 May)
Develop cost and schedule estimates (16 May)
Prepare PDR documentation (30 May) and presentations (13 Jun)
21 March 2003
Reiersen - 6
Key modular coil milestones
NCSX
again, representative dates
Prepare performance specifications (28 Feb)
Develop design features – bolted joints, VV supports, shell cutouts,
clamps, cooling lines, wings, instrumentation (18 Apr)
Perform winding R&D - keystoning tests (7 Feb), material properties
and allowables (7 Mar), molding process and VPI in autoclave
(21 Mar)
Perform FMECA, structural, and thermal analyses (25 Apr)
Prepare ICDs (9 May)
Perform mfg development activities for PDR for MCWF (9 May)
Develop cost and schedule estimates (16 May)
Prepare PDR documentation (30 May) and presentations (13 Jun)
21 March 2003
Reiersen - 7
Other key milestones
NCSX
again, representative dates
Procure SLA model to confirm field period and final
assembly (11 Apr)
Document plans for field period and final assy (2 May)
Complete preliminary design for all systems (2 May)
Develop cost and schedule estimates (16 May)
Prepare PDR documentation (30 May) and
presentations (13 Jun)
21 March 2003
Reiersen - 8
Summary
NCSX
We have a coil design!
The PDR has slipped until the week of 23 Jun because of
the delayed arrival and to put some time between the
PDR and the QPS CDR (26 Apr)
The PDR will serve two purposes – DOE’s requirements
for establishing the performance baseline and our own
requirements for proceeding with the Final Design of
the VV (WBS 12)and Modular Coils (WBS 14)
21 March 2003
Reiersen - 9