May VV FDR 4 3.ppt

Download Report

Transcript May VV FDR 4 3.ppt

May 19-20, 2004

NCSX Vacuum Vessel Manufacture

Mike Viola, Paul Goranson, Brad Nelson, Mike Cole Phil Heitzenroeder, and Tom Brown for the NCSX Engineering Team

NCSX Final Design Review May 19-20, 2004

NCSX FDR

PPPL

Mike Viola 1

Review of the NCSX Vacuum Vessel

Risks Mitigated through a successful PVVS program.

R&D and Vacuum Vessel

May 19-20, 2004 NCSX FDR

Prototypes Complete

Outline

Mike Viola 2

NCSX’s Vacuum Vessel Was Recognized as Unconventional Right from its Conception

• •

Highly shaped Forming of Inconel 625. Need for tight tolerances

Design has to accommodate assembly needs

Modular coils have to be positioned over the VV; this requires all ports except mid period ports to be welded in

– NCSX FDR

installed.

Vessel shape & size has

Mike Viola 3

Manufacture

• •

Dies are machined.

Panels are cold pressed. (Segmentation determined by Vendor.)

Prototype consisted of a 20 segments ° sector which involved about 5

Measurements taken using CMM or gages

• • • • •

Panels welded together on fixture Mirror every half period (60 °) More measurements taken

(Heat treatment requirements evaluated during R&D) 60 ° segments married Ports welded on before cutting holes.

permits leak check

minimizes distortion

• •

Main flanges attached

Leak check entire vessel and port welds between thermal cycling

NCSX FDR

Ports cut off to leave stubs

reinforces vessel

60 Degree Half-Period 6 Piece Segmentation Scheme Mike Viola 4

The PDR Committee considered the Technical Risks Properly Identified and Appropriately Mitigated.

Major Tool has completed its PVVS and qualified their MIT / QA Plan. Rohwedder is right behind.

The forming, welding, machining, polishing, port removal and reattachment, and inspection processes have all been demonstrated and optimized.

The prototype development and R&D Studies have provided a solid understanding of the manufacture techniques and reduced risk factors.

A Final Design is in hand

NCSX FDR • May 19-20, 2004

The VVSA drawings and model are complete

Mike Viola 5

R&D of Vacuum Vessel Prototypes are Complete

Goals:

To produce a prototype VV sector.

To provide experience in manufacturing prototypical parts so firm fixed price proposals can be developed which do not have excessive contingency built in.

Prototype consisted of a 20 ° sector (chosen for good demonstration of

NCSX FDR Mike Viola 6

Tolerances Were Developed with Prototype Suppliers

Profile tolerance on outer vacuum surface is bilateral i.e. 0.1875 either side of reference surface.

Material thickness tolerance shall be per requirements set forth in ASTM B443. The minimum thickness after forming shall be 0.338. Thinning below the stock thickness shall not occur over more

NCSX FDR

circumference of any cross-section.

Mike Viola 7

Phase II of the Manufacturing Studies Is Now Underway Goals:

The two Prototype suppliers Major Tool and Rohwedder submitted their MIT plans and were authorized for fabrication on August 7 th .

Both suppliers have completed their PVVS fabrication.

Initial review of Major Tools data package .

Mike Viola 8

Phase II of the Manufacturing Studies Is Now Underway (Major Tool Die/Punch set)

May 19-20, 2004 NCSX FDR Mike Viola 9

Phase II of the Manufacturing Studies Is Now Underway (Major Tool Inspection Gages)

May 19-20, 2004 NCSX FDR Mike Viola 10

Phase II of the Manufacturing Studies Is Now Underway (Major Tool Welding Form)

May 19-20, 2004 NCSX FDR Mike Viola 11

Plans for the “Production” Subcontract

It is our intent to select one subcontractor for the (18) “production” modular coil winding forms from the two Phase II subcontractors .

However, we are open minded about possibly of “splitting” the subcontract between the two subcontractors if advantageous.

The selection will be based on:

Evaluation of the prototypes,

May 19-20, 2004 • NCSX FDR Mike Viola

“Best value” evaluation of the proposals.

12 •

Business factors, including experience in

Statement of Work (SOW) Summary

Quality Assurance Section specifically addresses:

Inspection / surveillance / audit by PPPL

• • • • • • • • • •

Subcontrctor’s responsibility for conformance Nonconforming items Deviations to the Apprived MIT / QA plan Subcontractor’s QA Program Inspection and Test Procedures.

Document Traceability and Records Equipment / Material Identification and Status Calibration of Test and Measuring Equipment Control of Special Processes PPPL Receiving and Inspection Deliverables include:

Weekly reports

Monthly reports indicating schedule progress.

• May 19-20, 2004

(18) winding forms conforming to Spec. NCSX-CSPEC-141 03, in accordance with the supplier’s MIT/QA Plan and associated procedures.

NCSX FDR Mike Viola •

Shipping release form

13 •

Process History

Evaluation Criteria

I. Past Performance – 60%

• • • • •

Prototype Quality - performance relative to specification (40%

Dimensional tolerances

Mechanical and Physical Properties of Casting Alloy Poloidal break Magnetic permeability Non-destructive testing Surface finish Non-conformances Management (Performance relative to the SOW) 20%

Communication

Adequacy of Proj. Mgt. staff

• •

Response to technical issues & problems Reliability of estimates

Cost growth

Schedule growth

• •

Quality of the MIT/QA plan for the prototype

Mike Viola 14

Compliance with the Subcontractor’s QA documentation

Evaluation Criteria (cont’d.)

Capability for the Production Winding Forms – 40%

• −

Technical Capability (25%) Adequacy and commitment of facilities and personnel and / or subcontract arrangements.

− −

Technical approach Risk management

− May 19-20, 2004 − − − − −

Management (15%) Review of Annual Financial reports for the past 2 yrs.

Organizational structure Key personnel Letters of commitment Evidence of sufficient machine,skilled labor, and floor space to produce to the schedule and has an adequkate document control system.

Mike Viola −

If a large business, their Small Business Subcontracting Plan.

15

Source Selection Schedule Overview

Initial meeting of SPEB 18 March 04 Draft copies of Specification & SOW released to subcontractors for comment Specification and SOW updated to reflect subcontractor’s comments Prototypes due at PPPL Firm fixed price and schedules proposals due PPPL inspections of prototypes complete Oral Presentations by Offerors

May 19-20, 2004 NCSX FDR

SPEB completes report on their evaluations 23 April 04 14 May 04 28 June 04 02 July 04 19 July 04 21-22 July 04

Mike Viola 16

29 July

Statement of Work (SOW) Summary

Quality Assurance Section specifically addresses:

Inspection / surveillance / audit by PPPL

• • • • • • • • • •

Subcontrctor’s responsibility for conformance Nonconforming items Deviations to the Apprived MIT / QA plan Subcontractor’s QA Program Inspection and Test Procedures.

Document Traceability and Records Equipment / Material Identification and Status Calibration of Test and Measuring Equipment Control of Special Processes PPPL Receiving and Inspection Deliverables include:

Weekly reports

Monthly reports indicating schedule progress.

• May 19-20, 2004

(18) winding forms conforming to Spec. NCSX-CSPEC-141 03, in accordance with the supplier’s MIT/QA Plan and associated procedures.

NCSX FDR Mike Viola •

Shipping release form

17 •

Process History

Vacuum Vessel Phase II Manufacturing Studies / Prototype Fabrication Schedules

Prototypes Completed •

The Phase II manufacturing studies are well underway.

The expected delivery for both prototypes is

March 04

provide technical input for the Final Design Review.

to

The FDR on the Vacuum Vessel is scheduled for

April 04

.

Produce a Final Manufacturing / Inspection / Test / Quality Assurance Plan for the “Production” Vacuum Vessel • Mid May 04 •

This will be refined based on their experience in manufacturing the prototype.

Their Firm Fixed Price and Schedule Proposal will be developed based on this.

Produce a Firm Fixed Price and Schedule Proposal •

To be completed by the

end of May 04

.

• • May 19-20, 2004

A Subcontract Proposal Evaluation Board (SPEB) will begin evaluations of the two teams’ Prototype performance in

June 04

. They will evaluate the two teams’ Proposals when received in late June and submit their findings and recommendations for the Production Subcontractor to the Procurement Official by

July 04

.

NCSX FDR Mike Viola 18 •

This will lead to the Production Subcontract Award in

July

Phase III of the Vessel Fabrication Is Upcoming

• • •

Goal:

To build the Vacuum Vessel within Specification, On Time & Within Budget.

Scheduled to begin fabrication in

July 04

with delivery in

September 05

The detailed manufacturing studies have yielded a composite (i.e., neither the highest or lowest cost was chosen) projected budgetary cost of the VVSA of

$2.729M

before overhead.

May 19-20, 2004 NCSX FDR Mike Viola 19

WBS2 12 Budget (loaded $ based on ECP6) Sum of Budget (loaded $) PHASE

1) Title I & II

Resource

LABOR M&S 1) Title I & II Total 2) R&D LABOR

WBS 121 122

$1,004,275 $42,922 $50,552 $1,054,828 $42,922 $339,628

123 124 125 Grand Total

$31,127 $21,574 $20,979 $31,127 $21,574 $20,979 $1,120,878 $50,552 $1,171,430 $339,628 M&S 2) R&D Total 3) Fabrication & Assembly May 19-20, 2004 3) Fabrication & Assembly Total LABOR M&S Grand Total $120,357 $459,985 $228,057 $21,461 $4,743,286 $6,258,098 $131,954 $174,876 $22,939 $321,761 $344,700 $375,827 $9,601 $31,451 $41,052 $62,626 $2,608 $3,132 $5,740 $26,720 $120,357 $459,985 $284,667 $6,898,147

Vacuum Vessel Phase II Manufacturing Studies / Prototype Fabrication Cost & Schedules

May 19-20, 2004 NCSX FDR Mike Viola 21

Bases of Winding Form Production Costs and Schedules

The baseline cost of the (18) winding forms is $ 4.84 M. This is a composite (i.e., neither the highest or lowest cost was chosen) of the two subcontractor’s budgetary estimates developed during the Phase II manufacturing studies.

The baseline schedule is 18 months. This

NCSX FDR Mike Viola 22

developed during the manufacturing

Modular Coil Winding Form Cost Summary

Labor (covers all Title I, Title II, and Title III): PPPL: 2163 hrs. 341,000 ORNL: 8172 hrs. $1,055,000 $ Materials & Supplies: Manufacturing Development (Phase II Studies) 2 suppliers: 1,175.000

Production Winding Forms 4,839,300 Travel for contract monitoring:

May 19-20, 2004

48,000 G&A & Escalation on non labor

Mike Viola 23

Winding Form Cost Breakdown

May 19-20, 2004

29.2 %

Estimated Cost / Winding Form: $270 K

7.4 % 11.4 %

52.1% Mfg. Anal/Patterns Casting/HT/Inspection Machining Proj. Mgt. NCSX FDR Mike Viola 24

Winding Form Schedule Breakdown for Production

The production time for the (18) winding forms is projected to be 18 months. • Manufacturing analyses and pattern making is the first task required for each of the (3) casting types (task time: ~12 wks. – most sub-tasks can be performed in parallel) • Casting / inspection / repair / heat treatment during the production phase is estimated to take ~4 wks. / winding form. • Machining on a 5 axis milling machine is May 19-20, 2004 NCSX FDR Mike Viola required; for the production phase, this is 25 estimated to take ~4 wks. / winding form.

Summary

We are completing the manufacturing development and prototype fabrication phase . During this phase:

[1] we demonstrated that the proposed design is manufacturable [2] we are on track to qualify two suppliers for building the production articles and [3] these two suppliers should be in an excellent position to provide a leaner bid (lower contingency in both cost and schedule) based on their experience fabricating the prototypes.

Our design is well documented in a product specification and accompanying Pro/E models and drawings.

• Pre-proposal versions have been provided to our suppliers for their review and comment and are reflected in the final versions.

We are ready to enter into a contract for the production articles

.

• A SOW has been developed which defines the work to be performed.

We have agreement with the suppliers on the process and quality assurance requirements for fabricating the production articles.

26

Summary

 

We are following a sound acquisition plan.

completing the manufacturing development and prototype fabrication phase. During this phase, [1] we demonstrated that the proposed design is manufacturable [2] we are on track to qualify two suppliers for building the production articles and We are [3] these two suppliers should be in an excellent position to provide a leaner bid (lower contingency in both cost and schedule) based on their experience fabricating the prototypes.

We have a well documented design.

comment. Our design is well documented in a product specification and accompanying Pro/E models and drawings. Pre-proposal versions have been provided to our suppliers for their review and

We are ready to enter into a contract for the production articles.

NCSX FDR Mike Viola A SOW has been developed which defines the work to be performed. We have agreement 27

Summary

• • • •

Phase I is complete.

Risks have been identified and steps put in place to mitigate them.

Phase II - The Prototype Vacuum Vessel is under construction.

The experience gained from this 20 ° segment will provide the experience and knowledge to build the Vacuum Vessel Subassembly with great confidence in the design and cost factors.

– –

Major Tool has fabricated several die components Rohwedder is vigorously working a solution that

NCSX FDR Mike Viola

Phase III is anticipated with great confidence.

28