Overview of the TFTR D&D Project
Erik D. Perry
D&D Lessons Learned Workshop
June 25-26, 2002
PPPL
June 25-26, 2002
D&D Lessons Learned Workshop
1
Overview of TFTR D&D
•
•
•
•
Schedule: October 1999 through September 2002
Original Estimated Project Cost: $40.3M
Projected Project Cost at Completion: $36.8M
Objectives:
– Remove activated and/or contaminated components from
the TFTR Test Cell, Test Cell Basement and Tritium Area.
(Tritium Area later changed to mothball)
– Provide data for the decommissioning of future fusion
projects.
June 25-26, 2002
D&D Lessons Learned Workshop
2
TFTR D&D Summary Schedule
Summary Schedule
FY00
O N
D
J
FY01
F M A M
J
J
A
S
O N
D
J
FY02
F M A M
J
J
A
S
O N
D
J
F M A M
FY02
J
J
A
S
O N
D
J
F M A M
J
J
A
S
A
S
Clear TC Floor Area & Setup Packaging Area
Relocate Elephant Trunk stations/HVAC
Remove Shield Walls & Labyrinths
Electrical Safing
Remove TC/TCB Cable & Trays
Remove MIRI,PF,TF & heating cooling lines
Remove In-vessel Tiles
Remove Tokamak Cable trays & Conduit
Remove Diagnostic & Remaining TC 100' Equipment
Sweeping Procedures
Umbrella Structure, Columns and Lintels
Pump Ducts
VV/TF Supports & Contamination Stops
DWC Hardware & Assembly Fabr
DWC Full Scale Mockup Demo/Training
Fixture Testing
Shear Compression Panels
Vessel Fill Prep
Ready to Fill Vacuum Vessel with Concrete
Fill Vessel and Setup for DWC
Begin Diamond Wire Cutting Operations
DWC Ops and segment disassembly
Complete Diamond Wire Cutting Operations
Center Column and ISS
Clear 100' and 102' Penetrations
TC Decontamination
Final Rad Survey & TC Restoration
Project Complete
FY00
O N
D
J
F M A M
June 25-26, 2002
FY01
J
J
A
S
O N
D
J
F M A M
FY02
J
J
A
S
O N
D
J
F M A M
FY03
J
J
A
D&D Lessons Learned Workshop
S
O N
D
J
F M A M
J
J
3
TFTR Before D&D
June 25-26, 2002
D&D Lessons Learned Workshop
4
Overview of TFTR D&D cont
• Not a typical decontamination and decommissioning
(D&D) project
• Will not be returned to “green field” conditions
• Facility will not be released for unrestricted use
• Not a capital project - funded with operating money
June 25-26, 2002
D&D Lessons Learned Workshop
5
TFTR D&D Organization
TFTR D&D Project Organization
PPPL Director
Engineering
Department
Head
Engineering
June 25-26, 2002
TFTR D&D
Project
Manager
Planning and
Control
Construction
HP /
Radwaste
D&D Lessons Learned Workshop
6
Management of TFTR D&D Project
• Used existing PPPL Project Control Systems (PCS)
• Cost - Performance Measurement System employed
utilizing earned value techniques
• Schedule - PC based “Primavera” System
• Management Meetings / Project Reports
June 25-26, 2002
D&D Lessons Learned Workshop
7
Work Breakdown Structure
• 1.0 Engineering
• 1.1
Oversight & Planning
• 1.2
Area Preparations
• 1.3
Non-Tokamak Removals
• 1.4
Tokamak Removal Engineering
• 2.0 Field Operations
• 2.1
Oversight & Support (Field Ops)
• 2.2
Area Preparations (Field Ops)
• 2.3
Non-Tokamak Removals (Field Ops)
• 2.4
Tokamak Removals (Field Ops)
June 25-26, 2002
D&D Lessons Learned Workshop
8
Work Breakdown Structure cont
• 3.0 Project Management
• 3.1
Project Office
• 3.2
Work Control Center
• 3.3
Configuration and Document Control
• 4.0 Health Physics and Safety
• 4.1
HP Oversight
• 4.2
Safety Oversight
June 25-26, 2002
D&D Lessons Learned Workshop
9
Work Breakdown Structure cont
• 5.0 Radwaste Operations
• 5.1
Radwaste Management
• 5.2
Containers and Supplies
• 5.3
Transportation and Disposal
• 5.4
Mixed Waste
June 25-26, 2002
D&D Lessons Learned Workshop
10
Conduct of Operations
•
•
•
•
•
•
Worker safety highest priority
Protecting environment from tritium release
Different set of hazards than TFTR operations
Centralized control of work activities
Procedure compliance mandatory
Clear responsibility and accountability
June 25-26, 2002
D&D Lessons Learned Workshop
11
Work Package Process
• Engineering
»
»
»
»
»
June 25-26, 2002
Define work scope
Conduct Peer Reviews and Design Reviews
Prepare installation/removal procedure
Define prerequisites for field work
Update or void drawings after removal is complete
D&D Lessons Learned Workshop
12
Work Package Process cont
• Work Control Center
» Review Engineering Package for completeness
» Ensure prerequisites are completed prior to issuing
package for work
» Arrange for all permits
» Release work package to field per schedule
» Arrange for resolution of field problems
» Return completed work package to Engineering for
drawing update/voiding
June 25-26, 2002
D&D Lessons Learned Workshop
13
Work Package Process cont
• Construction
» Verify and/or perform safing / lockout/tagout per
PPPL procedures as required
» Perform field work per procedure
» Return completed work package to Work Control
Center
June 25-26, 2002
D&D Lessons Learned Workshop
14
Summary
• The T FTR D&D Project has been
performed safely, on time and within budget
June 25-26, 2002