09_Tritium_Retention.PPT

Download Report

Transcript 09_Tritium_Retention.PPT

Tritium Retention in Vessel Tiles & Oil
Charles A. Gentile
D&D Lessons Learned Workshop
June 25-26, 2002
PPPL
June 25-26, 2002
D&D Lessons Learned Workshop
1
Acknowledgement of Others
Working on these Issues:
•
•
•
•
P. LaMarche
G. Gettelfinger
S. Langish
R. Parsells
June 25-26, 2002
•
•
•
•
J. Parker
S. Raftopoulos
K. Rule
R. Feder
D&D Lessons Learned Workshop
2
Presentation Outline
•
•
•
•
•
Introduction to TFTR, Tritium History
Scale Model Testing
Decontamination
Results
Summary/Conclusion
June 25-26, 2002
D&D Lessons Learned Workshop
3
Tokamak Fusion Test Reactor
June 25-26, 2002
D&D Lessons Learned Workshop
4
TFTR Tritium History
• T fueling by neutral beam injection (NBI)
• Small amount by direct gas puffing
• T captured on NB enclosure cryopanels
• Batch processed to holding tanks
• D/T mixture with trace hydrocarbon
• Early stages of TFTR Ops scrap gas oxidized and shipped offsite
for reprocessing
• Total T processed through facility - 99g
June 25-26, 2002
D&D Lessons Learned Workshop
5
Tritium Retention in TFTR 6000 Ci “tenaciously bound” in torus
• Carbon tiles - Major location of T inventory
• Approximately 1 ton of carbon tiles
• Codeposited Layer
• Plasma generated Carbon/Tritium coating
• Most tritium inventory in codeposited layer
• Carbon dust and debris
• Highly contaminated
• Smearable hazard to personnel
• Low total inventory
• Stainless Steel vessel wall
• Modest inventory
• Low outgassing rates at room temperature
June 25-26, 2002
D&D Lessons Learned Workshop
6
Requirements for Safe
VV Segmentation
• Cut up TFTR vacuum boundary while:
• Minimizing worker exposure to T-contaminated and activated
materials
• Leave internal components inside TFTR
• Remove tiles from cut lines
• Minimizing amounts of T or T-contaminated material released to
the environment
• Minimizing waste
• Waste disposal cost is a significant fraction of D&D cost
June 25-26, 2002
D&D Lessons Learned Workshop
7
Concrete/Tile Test
• Mock-up of TFTR VV conditions in a TypeA waste container
• Eight tiles placed in container
• About 10Ci of tritium in tiles
• Three lifts (about 10 gallons each) loaded in
container on successive days
• Passive measurements taken after each lift
• Core samples of cured concrete measured
for T
June 25-26, 2002
D&D Lessons Learned Workshop
8
June 25-26, 2002
D&D Lessons Learned Workshop
9
June 25-26, 2002
D&D Lessons Learned Workshop
10
June 25-26, 2002
D&D Lessons Learned Workshop
11
Test Results
• Great deal of moisture was released as the
concrete cured
• T monitors gave false high signal (moisture
and foam agent) during curing time
• Once concrete cures, smearable
contamination was low
June 25-26, 2002
D&D Lessons Learned Workshop
12
Test Results – Core Samples
Sample
2001-1262
2001-1263
2001-1724
2001-1725
2001-1726
2001-1727
June 25-26, 2002
Tritium (µCi/gm)
0.0178
0.1342
0.0201
0.0226
0.0353
0.0231
D&D Lessons Learned Workshop
13
Empirical Data - Conclusion
• Level of tritium in concrete
• DAC ≈ 40.9 g/m3 (estimate)
• Very difficult to suspend 41 g/m3 and greatly exceeds the TLV for
silica (0.005 mg/m3)
• Miniscule hazard from tritium in the dust!
• Conclusion from empirical data
• Low level of tritium to be released in concrete fill
• Concrete dust will have very low level of T
June 25-26, 2002
D&D Lessons Learned Workshop
14
Safe Disposal of VV - Plan
• Strategy to contain T while concrete filling
and segmenting vessel:
• Concrete/Foam Filling of the vacuum vessel (VV)
• Displaced air passed though bubblers to reduce T release
• Detritiation factor ≈10X
• Possible to go directly to stack via E-trunks
• Segmentation of the VV using Diamond Wire Cutting (DWC)
• Dry process - no large volumes of cutting fluid or gas
• Containment of particulates generated by the DWC during the
segmentation process
June 25-26, 2002
D&D Lessons Learned Workshop
15
June 25-26, 2002
D&D Lessons Learned Workshop
16
Diamond Wire Cutting
June 25-26, 2002
D&D Lessons Learned Workshop
17
Actual Results on TFTR
• Concrete pour on three separate days in
Summer 2001
• Vessel segmentation commenced in
Summer 2001
• Completed Spring 2002
• No whole body doses detected for this task
• Tritium released is modest over plant
chronic release (CY 2001 totals)
• HTO: 191Ci vs 115Ci/yr chronic rate prior to pour
• HT: 39Ci vs 10Ci/yr chronic rate prior to pour
June 25-26, 2002
D&D Lessons Learned Workshop
18
Activity in Stack During D&D Task
Monthly Total Stack Releases (2001-2002)
70
HTO (Ci)
HT (Ci)
Monthly Total (Ci)
59.94
50
August 2001
DWC Started/
NB's on trunks
40
33.173
30.8
30
25.638
21.802
21.428
21.136
18.178
20
15.46
11.044
12.775
12.337
10.482
9.945
7.79
10
5.753
Apr
Mar
Feb
Jan
Dec
Nov
Oct
Sept
Aug
July
June
May
Apr
Mar
Feb
0
Jan
Tritium Release (Ci)
60
Month
June 25-26, 2002
D&D Lessons Learned Workshop
19
Impact on Workers
• Full face supplied air respirators worn in
enclosures
• Reduces/eliminates facial skin exposure
• Facial skin exposure is only credible internal exposure risk
• Full anti-contamination protective clothing
worn in enclosures and cutting lay-down
area
• Minimal T exposure to workers. No whole
body uptakes from activated components
June 25-26, 2002
D&D Lessons Learned Workshop
20
June 25-26, 2002
D&D Lessons Learned Workshop
21
Sector Disassembly
June 25-26, 2002
D&D Lessons Learned Workshop
22
Worker Inside DWC Enclosure
June 25-26, 2002
D&D Lessons Learned Workshop
23
Sector Removal
June 25-26, 2002
D&D Lessons Learned Workshop
24
Tritium Activity in Oil
• 2 types of oil used for TFTR
• Krytox
• Hydrocarbon
• Both types of oil found to have great
affinity for “collecting” tritium
• Personnel exposure to oil is hazardous
• Oil easily sticks to and passes through skin
• High specific activity of tritium in oil – makes it extremely
hazardous
June 25-26, 2002
D&D Lessons Learned Workshop
25
Tritium Activity in Oil
• Oil removed from primary (nuclear)
pumping system measured to levels of
200µCi/g
• Approximately 2-3 g of oil (due to high
specific weight) per drop
• A single drop of tritiated oil exposed to skin
would lead to an uptake of approximately
30 mRem
June 25-26, 2002
D&D Lessons Learned Workshop
26