OSU & NBS Updates 2009 October Materials Meeting Federal Aviation Administration

Download Report

Transcript OSU & NBS Updates 2009 October Materials Meeting Federal Aviation Administration

OSU & NBS Updates
2009 October Materials Meeting
Materials Working Group
Michael Burns, FAA Tech Center
October 21st & 22nd, 2009
Federal Aviation
Administration
Agenda
1. NBS Update
• Photometric System Round Robin Results
• Future Follow-On Work
2. OSU Update
• Chapter 5 Equation
3. Maintenance Tips & Reminders
4. Next Steps
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
2
2
NBS Photometric System Round Robin
Photometric System Round Robin Has Been Completed
• Goal Was To Look At The Scatter The Photometric
System Alone May Have On Fleet Test Data
• Test Included A Linearity Check Of Five Data Points
Using Neutral Density Filters.
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
3
3
NBS Photometric System Round Robin
• 20 Labs (24 NBS Smoke Chambers) Were Able
To Participate
• No Furnace Heat Or Pilot Burner Used
• Zero Then Span System
• Gradually Slid Filter Over Lower Glass
Window
• Filter Information:
• Edmund Optics
• http://www.edmundoptics.com/onlinecatalog/
DisplayProduct.cfm?productid=1523
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
4
4
NBS Photometric System Round Robin Participants
AIM COMPOSITES
ISOVOLTA
AIRBUS (2 Labs)
JAMCO (2 Labs)
BOEING
KYDEX, LLC
C&D ZODIAC (2 Labs)
L-3 COMMUNICATIONS
CEAT
LANTAL
CTAERO
NEWPORT SCIENTIFIC
DELSEN TESTING LABORATORIES, INC.
RESCOLL
FAA
SCHNELLER (2 Labs)
HEATH TECNA, INC.
TESTCORP
HERB CURRY, INC.
THE GOVMARK ORGANIZATION,
INC.
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
5
5
ND2 Filter Data
0.3 O.D, 50.1 % Light Transmission, 39.6 S.O.D
Avg. 38.3 / 5.2% SD
45
1 Standard Deviation
40
35
30
Ds
25
20
15
10
5
0
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
V
W
X
Y
Lab Code (V=Calculated Value)
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
6
6
ND4 Filter Data
0.6 O.D, 25.1 % Light Transmission, 79.2 S.O.D
Avg. 86.2 / 3.2% SD
100
1 Standard Deviation
90
80
70
Ds
60
50
40
30
20
10
0
V
A
H
B
D
J
E
M
L
Q
K
P
R
N
C
I
W
U
X
F
O
G
S
T
Y
Lab Code (V=Calculated Value)
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
7
7
ND8 Filter Data
0.9 O.D, 12.6 % Light Transmission, 118.8 S.O.D
Avg. 114.7 / 3.3% SD
140
1 Standard Deviation
120
100
Ds
80
60
40
20
0
A
H
P
M
E
D
L
J
K
B
I
Q
R
C
O
X
G
U
F
S
N
T
W
V
Y
Lab Code (V=Calculated Value)
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
8
8
ND8+2 Filter Data
1.2 O.D, 6.3 % Light Transmission, 158.4 S.O.D
Avg. 153.2 / 3.1% SD
200
1 Standard Deviation
180
160
140
Ds
120
100
80
60
40
20
0
A
H
P
E
L
M
Q
B
D
I
R
J
S
C
O
K
F
U
G
T
N
X
W
V
Y
Lab Code (V=Calculated Value)
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
9
9
ND8+4 Filter Data
1.5 O.D, 3.2 % Light Transmission, 198.0 S.O.D
Avg. 201.7 / 4.6% SD
250
1 Standard Deviation
200
Ds
150
100
50
0
A
P
L
M
I
V
E
H
Q
R
K
J
S
X
B
C
D
U
W
O
G
N
T
F
Y
Lab Code (V=Calculated Value)
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
10
10
NBS Photometric System Round Robin
Calc.
Fleet Avg.
% Delta
% STDEV
% STDEV
(Removing A&Y)
39.6
38.3
-3.4%
5.2%
3.30%
79.2
86.2
8.9%
3.2%
1.60%
118.8
114.7
-3.5%
3.3%
2.20%
158.4
153.2
-3.3%
3.1%
1.10%
198.0
201.7
1.9%
4.6%
1.10%
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
11
11
Filter Calculated Values vs Fleet Avg.
250.0
1.9%
200.0
-3.3%
150.0
-3.5%
Ds
Calc. Values
Fleet Avg.
8.9%
100.0
50.0
-3.4%
0.0
ND2
ND4
ND8
ND8 + ND2
ND8 + ND4
Filter Configuration
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
12
12
NBS Photometric System Round Robin
• Labs Will Be Contacted Identifying Their Lab Codes
And Review Of Data.
• STEP 2
As Follow Up To The Photometric Portion Of The NBS System I
Would Like To Conduct A Round Robin Non-Flaming Test.
• STEP 3 (FINAL STEP)
As Follow Up To The Photometric Portion Of The NBS System I
Would Like To Conduct A Round Robin Flaming Test.
This 3 Step Process Will Hopefully Identify Problem
Areas Fleet Wide.
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
13
13
Chapter 6 Update to FAA Handbook
• 09/29/09: In an effort to provide a constant for
simplifying the calibration factor calculation in
FAR 25, Appendix F, a long standing error was
noted in Chapter 5 (Heat Release Rate Test for
Cabin Materials) of the Handbook. The
constant value located in the equation
(Paragraph 5.6.6) is currently 23.55 and should
actually be 25.31.
• Please verify that your software uses this value.
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
14
14
Maintenance Tips & Reminders
• OSU
– Inspect Cooling Air Manifold Holes / Pipe For
Evidence Of Corrosion
– Inspect Outer Door Seals For Evidence Of
Damage
• NBS
- Remember To Replace The Water Used In
The Pressure Regulator System On A
Regular Basis
- Continually Leak Check NBS Unit Prior To
Testing
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
15
15
Next Steps
• Begin Follow-On Testing To The NBS
Photometric System Round Robin
• Non-Flaming / Flaming
• Look Into How Different OSU Insulation
Densities May Have An Effect On Test Results
• Assist The Flammability Standardization Task
Group As Needed
• FAA Contact Information:
Michael Burns At [email protected]
+1 (609) 485-4985
Materials Meeting – NBS / OSU Updates
October 21st & 22nd, 2009
Federal Aviation
Administration
16
16