– Status Report ALICE TPC

Download Report

Transcript – Status Report ALICE TPC

ALICE TPC – Status Report
Project leader: Peter Braun-Munzinger, GSI Darmstadt
Deputy project leader:
Johanna Stachel, Heidelberg
Technical coordinator:
Peter Glässel, Heidelberg
Bergen
Bratislava
CERN
CERN
Copenhagen
Krakow
Darmstadt GSI
D. Röhrich
B. Sitar
T. Meyer
L. Musa
B.S. Nielsen
M. Kowalski
H.R. Schmidt
Darmstadt TU
Frankfurt
Heidelberg KIP
Heidelberg PI
H. Oeschler
R. Renfordt
V. Lindenstruth
J. Stachel
Lund
H.A. Gustafsson
ALICE TPC Status, Meeting with LHCC referees 30.6.03
Data acquisition
1/2 IROC series production
Field cage
Electronics
Laser system
Simulations
ROC engineering, prototyping,
series production, simulations
Electronics testing
Electronics testing, installation
Data acquisition, HLT
Electronics, engineering,
IROC production, OROC production
Electronics
1
Outline
Field cage
Readout chambers
Laser system
Cooling system
Gas system
Readout electronics
Schedule
ALICE TPC Status, Meeting with LHCC referees 30.6.03
2
TPC Field Cage Overview
Inner and outer
Isolation vessels
Aluminum End
Plates housing
ROC’s
Field defining
system: strips
supported by rods
ALICE TPC Status, Meeting with LHCC referees 30.6.03
3
Field Cage Parts, Overview
Isolation volume
OFV
Central membrane
Drift volume
5560
Isolation volume
IFV
cone
Central drum
End wheel
OCV
ICV
5000
ALICE TPC Status, Meeting with LHCC referees 30.6.03
4
Field Cage: Mounting Rod Supports
ALICE TPC Status, Meeting with LHCC referees 30.6.03
5
Field Cage: Rod Assembly
ALICE TPC Status, Meeting with LHCC referees 30.6.03
6
Resistor Rod status
Completed:
Gas-cooled prototype
Contacts ok
Still a few improvements needed
Rather complicated to produce
Needs separate CO2 gas system
Water-cooled prototype
Full prototype end July03
HV tests both successful
Resistor tests: stability, overvoltage tolerance
Water-cooled rod preferred solution
In progress:
Tooling and pieces for production (water cooled)
Concerns:
Tight schedule (first 2 rods needed Dec03), manpower
ALICE TPC Status, Meeting with LHCC referees 30.6.03
7
Resistor Rod Cooling
gnd
100 kV
gas cooled
insulation volume
(gas)
water cooled
Resistor
10
Ceramic pipe
Resistor
G10 Separator
High-resistivity
water
Cu-heat bridges
ALICE TPC Status, Meeting with LHCC referees 30.6.03
8
Field Cage Inner Drum
Delivered by Fischer
Al strips (ground)
prepared
ALICE TPC Status, Meeting with LHCC referees 30.6.03
9
The Inner FC vessel is being rebuilt
What happened:
Leak test: 25 Feb03 --> leaks at glue joint
between composite and flange
Ultrasonic test: 27 Feb03 --> faulty glue bonds
First repair by Fischer: 10-14 Mar03,
only on outer joint
Decision to rebuild: 24 Apr03, order 6 May03
Consequences:
Repeat work:
Assembly at CERN Jul03
Leak test, guard rings, vias,
Resistor chain, rod supports
Total delay 7 months,
Ready to install rods Dec03
Complete FC equipment Jul04
ALICE TPC Status, Meeting with LHCC referees 30.6.03
Defective vessel
10
7 months
3 month float
Impact of FC Schedule on Pre-Installation
Pre-commissioning of TPC shortened from 13 to 6 month
ALICE TPC Status, Meeting with LHCC referees 30.6.03
11
Field Cage: Central Electrode
ALICE TPC Status, Meeting with LHCC referees 30.6.03
12
Field Cage: Central Electrode
Completed:
Modification of
stretching machine
Stock of 6m wide glued
mylar foil
Stretching and rupture
test
electrode frames and
manipulation tool
Not started yet:
Production of 3
electrodes (not earlier
than needed)
ALICE TPC Status, Meeting with LHCC referees 30.6.03
13
Field Cage Status Summary
Completed:
Mounting rod supports on OFV
Inner cones
Central drum
In progress:
Gluing standard rods
Gluing laser rods
Not started yet:
Rebuild of IFV (assembly at CERN Jul03)
Testing and equipment of new IFV
Load test on outer insulation volume
Rebuild of one inner cone (change of dimensions at muon absorber)
ALICE TPC Status, Meeting with LHCC referees 30.6.03
14
Service Support Wheel
Carries FEE and services
Completed:
Design of frame and
services
Prototype sectors for
FEE assembly trial
In progress:
Construction
Design of details for
connection to ITS
services and beam pipe
Concerns:
Installation of FEC’s
difficult, tight space
ALICE TPC Status, Meeting with LHCC referees 30.6.03
15
Front End Card Installation
FEC in Cu sandwich
6 cables per FEC
connectors with locks
Model setup at GSI to
study FEE installation
development of tool
for cable insertion,
connector locking/
unlocking
IROC
ALICE TPC Status, Meeting with LHCC referees 30.6.03
16
IROC Production Bratislava
Quality good
Very uniform wire spacing
Very uniform wire tension
Leak and gain tests lagging behind due to (trivial) technical
problems, mostly solved already
Production running smoothly now at 2 ch/month
not on critical path
ALICE TPC Status, Meeting with LHCC referees 30.6.03
17
OROC Production Heidelberg/GSI
Initial problems with segmented pad planes solved,
but still more difficult than anticipated
(2 padplanes out of 14 have to be redone)
Leak rate lower per area than IROC
Each chamber is surveyed, geometry within specs
Production running at 1 ch/week now
ALICE TPC Status, Meeting with LHCC referees 30.6.03
18
OROC Production Heidelberg/GSI
Survey of
planarity and
pad geometry
ALICE TPC Status, Meeting with LHCC referees 30.6.03
19
OROC Production Heidelberg/GSI
Coarse and fine adjustment of a wire plane
ALICE TPC Status, Meeting with LHCC referees 30.6.03
20
OROC Production Heidelberg/GSI
Measuring
wire tension
ALICE TPC Status, Meeting with LHCC referees 30.6.03
21
OROC Production Heidelberg/GSI
Chamber in
test setup
ALICE TPC Status, Meeting with LHCC referees 30.6.03
22
ROC Status Summary
Completed:
Assembled: IROC 27, OROC 12
Tested:
IROC 18, OROC 5
In progress:
Production rates: OROC 1 ch/week,
IROC 2 ch/mo
Expect to finish early 2004
Concerns:
OROC: gluing of pad plane (4 sectors) more difficult
than anticipated
Testing in Bratislava not yet fully operational
ALICE TPC Status, Meeting with LHCC referees 30.6.03
23
Laser System
Completed:
Micro-mirrors: delivered, tested and selected
Preparation of laser rod segments and mirror holders
Tooling for gluing rods
In progress:
Assembly of laser rods (till Sep03)
Procurement/construction of optics elements
Concerns: none
ALICE TPC Status, Meeting with LHCC referees 30.6.03
24
Electronics Cooling
FEE cooling
27 kW to be removed
System design nearly
completed, draft document
exists
PRR in fall
ROC padplane thermal screen
ALICE TPC Status, Meeting with LHCC referees 30.6.03
25
TPC Gas System
In progress:
System for drift gas Ne/CO2 (90/10)
Construction nearly finished, commissioning till Dec03
Connection to pre-installation site SXL2 (existing lines)
Not yet started:
CO2 for insulation volumes: still to be done
very simple in case of water cooled resistor rod
Concerns: none
ALICE TPC Status, Meeting with LHCC referees 30.6.03
26
TPC PASA
Final submission 27 May03
engineering sample 500 chips Sep03
rest of production (40,000 chips) Jan04, testing Feb-Jul04
*
* typical 12 pF, slope 16.5 e/pF
ALICE TPC Status, Meeting with LHCC referees 30.6.03
27
High Occupancy events from Cosmics
ALICE TPC Status, Meeting with LHCC referees 30.6.03
28
PG:
ALTRO digital tail cancellation and
baseline restoration
ALICE TPC Status, Meeting with LHCC referees 30.6.03
29
Front-end Card final version
128 ch
ALICE TPC Status, Meeting with LHCC referees 30.6.03
30
Front-end Card Status
Completed:
Improved features
EEPROM card id
Improved Front-end Bus design: multilayer-flexible instead of cable
Geographical address
Assembly of prototype
Standalone tests
In progress:
Adaptation of cooling plates
Characterization with ROC
Test equipment
Production of 4500 FEC Nov03-Aug04, test Apr04-Nov04
Concerns: tight schedule
ALICE TPC Status, Meeting with LHCC referees 30.6.03
31
Readout Control Unit (RCU)
Completed:
Production of prototype RCU-2 (small series for test setups)
PCI-card, problems to get them to work reliably
Final design (standalone RCU): motherboard layout done
In progress:
Solve RCU-2 problem (fall-back RCU-1, decision Jul03)
Final design (standalone):
DCS/Trigger cards (common for TPC/TRD) under test
FPGA firmware till end Aug03
System tests from Sep03
Not started yet:
Production (216 cards + spares) Apr04 - Jul04
Testing Aug04 - Mar05
Concerns: tight schedule
ALICE TPC Status, Meeting with LHCC referees 30.6.03
32
Schedule Overview
ALICE TPC Status, Meeting with LHCC referees 30.6.03
33