The Bay Area Hydrology Model: A Tool for Analyzing Hydromodification
Download
Report
Transcript The Bay Area Hydrology Model: A Tool for Analyzing Hydromodification
The Bay Area Hydrology Model: A
Tool for Analyzing Hydromodification
Effects of Development Projects
and Sizing Solutions
Jill C. Bicknell, P.E., EOA , Inc.
Santa Clara Valley Urban Runoff Program
Doug Beyerlein, P.E., Clear Creek Solutions, Inc.
The Bay Area Hydrology Model: A
Tool for Analyzing Hydromodification
Effects of Development Projects
and Sizing Solutions
This presentation given by Jill Bicknell and Doug Beyerlein at
the September 2006 CASQA Conference in Sacramento, CA.
Acknowledgements
Funding Agencies
– Santa Clara Valley Urban Runoff Pollution
Prevention Program (SCVURPPP)
– Alameda Countywide Clean Water
Program (ACCWP)
– San Mateo Countywide Stormwater
Pollution Prevention Program (STOPPP)
Arleen Feng (ACCWP)
Tony Donigian (Aqua Terra Consultants)
Gary Palhegyi (GeoSyntec Consultants)
Presentation Overview
Background / Permit Requirements
Technical Approach to Control of
Hydromodification
Design Challenges / Need for BAHM
Overview of the BAHM
BAHM Parameter Development
BAHM Application
BAHM = Bay Area Hydrology Model
What is Hydromodification?
Change in the runoff hydrograph (flow
pattern) from an area due to development
Impacts of land development:
–
–
–
–
Increase in impervious surface
Decrease in amount of vegetation
Grading and compaction of soils
Construction of drainage facilities
What is Hydromodification?
(continued)
Effects of land development on the site
runoff hydrograph:
– Less infiltration / evapotranspiration
– More surface runoff (increased volume)
– Runoff leaves the site faster (increased
peak flows)
– Runoff occurs more often (increased
duration)
– Runoff conveyed directly to creek (increased
connectivity)
Hydromodification Control
Requirements
SF Bay Area Phase 1 MS4 Permits
Permit Provision C.3.f.i.:
Increases in runoff peak flow, volume,
and duration shall be managed for all
Group 1 Projects*, where such increased
flow and/or volume can cause increased
erosion of creek beds and banks…
* Group 1 = > 1 acre impervious surface
Hydromodification Control
Requirements
Permit Provision C.3.f.i. (continued):
Post-project runoff shall not exceed
estimated pre-project rates and/or
durations, where the increased storm
water discharge rates and durations will
result in increased potential for erosion…
Must develop and implement HydroModification Management Plans (HMPs)
Hydromodification Control
Requirements
Permit Provision C.3.f.ii. (Exemptions):
Projects that discharge to tidal area, channel
continuously hardened to the Bay, or directly to
the Bay
Projects that are “infill projects” in “highly
developed watersheds”
Other projects where potential for increased
erosion is minimal (e.g., no increase in
impervious area)
Segment 5
Stable stream, bed close to old tree
Segment 4
Channel incision
on Yerba Buena
Creek
Segment 1
Undermining outfall protection structure
Pre- and postproject runoff
characteristics
All Events Flood Frequency
1000
Peak Q, cfs
900
800
Future Peak Q
Existing Peak Q
700
600
500
Pre-Urban Peak Q
400
300
200
100
0
Flow Duration
1
10
10000
1000
Return Period, months
Critical flow (Qc=15 cfs)
Durations (hrs)
100
1000
2-year
100
Pre-Urban
Existing
Frequency of
events and duration
10
1
10
80
150
220
290
360
Flows (cfs)
430
500
570
640
Control Strategies
Peak flow control - not effective for erosion
control (low flows matter)
Single event/design storm approaches –
not adequate hydromod control
Flow duration control - recommended
– Maintain magnitude and duration of postproject flows same as pre-project
– Considers multi-year discharge record
Site design (LID) measures – effective in
reducing flow, use to supplement flow
duration control facility
Flow Duration Histograms
Histogram of Discharge from the 716 Acre Test Subcatchment
10000
10-year
Peak Flow
5-year
Peak Flow
2-year
Peak Flow
Pre-Project Discharge
Post-Project Discharge
Frequency (hours)
1000
Post-Project w/Control
100
10
1
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
Flow Bin (cfs)
80
85
90
95 100 105 110 115 120 125 130 135
Flow Duration Curve Matching
San Jose Small 12-lot Residential Example
3
Pre-Project
Post-Project
2.5
Post-Project w/BMP
Discharge (cfs)
2
1.5
1
0.5
0
1
10
100
Frequency (hours)
1000
10000
Range of Storms to Manage
(Set of Design Storms)
Qc to the 10-year event
Percentage of Total Work Done
100%
90%
80%
70%
60%
50%
40%
30%
20%
2-Year Peak
Flow
10%
5-Year Peak
Flow
10-Year Peak
Flow
0%
0
500
1000
Flow (cfs)
1500
2000
Tale of Five HMPs
Santa Clara Valley
– Submitted Final HMP Report April 2005
– RWQCB adopted July 2005
Contra Costa County
– Submitted Final HMP May 2005
– RWQCB adopted July 2006
San Mateo & Alameda Counties, Fairfield-Suisun
– Submitted final HMPs, under review by RWQCB
– Adopt December 2006?
Performance Criteria
Applicable projects with on-site flow
controls that are designed to provide flow
duration control to the pre-project condition
are considered to comply with the HMP.
Flow duration controls shall be designed to
match pre- and post-project flow rates and
durations from 10% of the pre-project 2year peak flow to the pre-project 10-year
peak flow.
On-Site Options
Use site design techniques to
reduce runoff flow and volume
– Decrease impervious surface area
– Disconnect impervious areas
– Promote infiltration
Select treatment BMPs
that reduce volume
– swales, detention areas,
bioretention, green roofs
On-Site Options, continued
Construct flow control structures
– Retention/detention basins
– Underground vaults/tanks
Combine flow control with flood
control and/or treatment facilities
– Examples: detention basin, wet pond,
constructed wetlands
Overflow provision for peak
events (storage may also be
increased to meet flood
control requirements)
C
Inflows: site runoff after
reductions from site design,
infiltration or other retention
measures
A
D
E - released at
maximum discharge
rate in pipe
Dead storage
(optional)
Discharge to
stream
*
Point of Compliance: drainage
point for comparing post-project
and pre-project Flow Duration
curves
B
Bottom infiltration
where applicable
Legend: A) outlet pipe riser; B) low flow orifice;
C) intermediate orifice (1 shown); D) weir notch
(V-type shown); E) freeboard above riser
(typically 1 foot).
Schematic Flow Duration Control Pond
Integrating Flow Duration Control
(FDC) with Other BMPs
Urban
Runoff
FDC Basin
Bio-infiltration
Swale
FDC
Basin
Stream
FDC
Vault
Bio-infiltration
Swale
On-Site BMPs
LID
Process for Evaluating
Flow Control Requirements
Hydrologic Analysis
Generate pre- vs. post-project flow
duration curves using hydrologic model
Continuous simulation required
Available models:
– Corps of Engineers’ HEC-HMS
– EPA HSPF
– EPA SWMM
– Western Washington Hydrology Model
Design Challenges
Challenge #1: Flow duration control design
– Requires use of continuous simulation
hydrologic model
– Use of these models is data intensive and time
consuming
– Lack of knowledge and experience
Challenge #2: Integrating flow controls
with site design and treatment controls
– How to estimate flow reduction benefits of
other BMPs
– How to estimate treatment capability of flow
control facility
BAHM based on WWHM
BAHM (Bay Area Hydrology Model) uses
the EPA HSPF computational engine and
WWHM (Western Washington Hydrology
Model) software platform.
BAHM hydrology parameter values are
derived from locally calibrated
watersheds.
WWHM
Developed for
the Washington
State Department
of Ecology.
Used in the 19
counties of
Western
Washington.
BAHM
Designed for the San Francisco Bay
Area
– Alameda County
– Santa Clara County
– San Mateo County
BAHM
Components
– user-friendly graphical interface
– automatically loads appropriate parameter
values and meteorological data based on
project location
– uses long-term (30+ year) local precip records
and scales precip based on ratio of project site
MAP and precip gage MAP
BAHM
Graphical interface: Project Site
BAHM
Graphical interface: Pre-Project Land Use
– Based on soil, vegetation, land slope, impervious
area
BAHM
Graphical interface: Project Land Use
– Based on soil, vegetation, land slope, impervious
area
BAHM
Graphical interface: HMP Facility
– Pond, tank, vault, gravel trench bed, bioretention
BAHM
Graphical interface: Runoff Analysis
– AutoPond optimizes (minimizes) pond dimensions
to meet HMP flow duration criteria
BAHM
Calibration of local hydrologic parameter values
– Castro Valley Creek watershed
– Alameda Creek watershed
BAHM
Comparison of simulated and observed
Castro Valley Creek streamflow
BAHM
Comparison of simulated and observed
Alameda Creek streamflow
WWHM Application Examples
Commercial site: Costco store, Woodinville,
WA (14.38 acres)
WWHM Application Examples
Commercial site: Costco store, Woodinville,
WA (6 acre-feet of underground storage)
WWHM Application Examples
Planned community: Snoqualmie Ridge,
King County, WA (1,343 acres)
WWHM Application Examples
Planned community: Snoqualmie Ridge,
King County, WA (10 stormwater ponds
ranging in size from 2 to 20 acre-feet)
Conclusion
BAHM will facilitate compliance with
HMP and design of flow control facilities
in the Bay Area by providing:
– An easier, standardized way to do
continuous simulation modeling
– A means to compute flow control benefits
of site design/LID and treatment measures
– Standardized reporting to assist municipal
staff in design review
For More Information...
Visit our website at:
www.SCVURPPP.org
Click on “New and Redevelopment Related
Products and Reports”