Electrical Procurements
Thomas C. Nehring, PE
Lead Electrical Engineer
Conventional Facilities Advisory Committee - Review
March 10-11, 2009
1
BROOKHAVEN SCIENCE ASSOCIATES
Outline
•
Substation Expansion
•
Secondary Unit Substations – for Ring Building Contract
•
•
•
•
•
•
69 kV to 13.8 kV Substations Expansion
Pre-Purchased Equipment
Estimated Costs
Construction/Procurement Schedule
Construction Package Management/Oversight
• Pre-Purchased Equipment
• Estimated Cost
• Procurement Schedule
Concerns
2
BROOKHAVEN SCIENCE ASSOCIATES
69 -13.8 kV Substation Expansion
• Scope
• Modify 69 kV Yard and Tower @ B 603
• Add 69 kV Breaker
• Install 20 MVA Transformer and oil retention pit
• Install 15 kV Switchgear and bus duct
• Install new ductbank to vicinity of NSLS-2 Site
3
BROOKHAVEN SCIENCE ASSOCIATES
Overall Electrical Utility Plan
Substation
expansion
and new
ductbank
4
BROOKHAVEN SCIENCE ASSOCIATES
Pre-Purchased Equipment
• Pre-Purchased Equipment
• 69 kV Breaker
• 20 MVA Transformer
• 15 kV Switchgear
5
BROOKHAVEN SCIENCE ASSOCIATES
Estimated Costs
• Estimated Costs
• $1,975K Construction Contract
• $80K 69 kV Breaker
• $1,200K 20 MVA Transformer
• $445K 15 kV Switchgear
6
BROOKHAVEN SCIENCE ASSOCIATES
Construction/Procurement Schedule
•
Construction Package Schedule
•
•
•
•
•
•
Baseline
CWE
Bid Package available
3/20/09
3/23/09
Bid Solicitation
4/14/09
4/13/09
Bids Returned
5/6/09
4/28/09
Contract Award
6/17/09
5/29/09
Notice to Proceed (Construction Start)
6/24/09
6/17/09
Construction Complete
4/14/11
4/14/11
7
BROOKHAVEN SCIENCE ASSOCIATES
Construction/Procurement Schedule
• Equipment Procurement Schedule
Procurement
4/14/09
Est. Delivery
2/05/10
•
69 kV Breaker
•
20 MVA Transformer
5/18/09
7/01/10
•
15 kV Switchgear
5/05/09
2/12/10
8
BROOKHAVEN SCIENCE ASSOCIATES
Construction Package Management/Oversight
•
•
•
Design
• Design by HDR
• Design review by NSLS-II
Procurement
• Bid solicitation by NSLS-II Procurement & Property Management
Group (PPM)
• Review by NSLS-II Conventional Facilities (CF)
Construction
• Construction management/oversight by NSLS-II CF
9
BROOKHAVEN SCIENCE ASSOCIATES
Pre-Purchased Equipment for Ring Bldg
• Secondary Unit Substations (SUS)
• 8 SUS’s that include:
•
•
•
•
•
15 kV Switching
15 kV Circuit Breaker
2.5 MVA Transformer
480 Outdoor Switchgear
480 Indoor Switchgear
10
BROOKHAVEN SCIENCE ASSOCIATES
Site Plan
Substations
11
BROOKHAVEN SCIENCE ASSOCIATES
Construction/Procurement Schedule
• Equipment Procurement Schedule
Procurement Est. Delivery
4/15/09
12/16/09
•
SUS outdoor portion(1,5,RF-1, RF-2)
•
SUS outdoor portion(2,3,4,LB)
4/15/09
1/13/10
•
SUS indoor portion(1,5,RF-1, RF-2)
4/15/09
2/10/09
•
SUS indoor portion(2,3,4,LB)
4/15/09
3/10/10
12
BROOKHAVEN SCIENCE ASSOCIATES
Concerns
• Storage of indoor pre-purchased equipment
•
•
To be received around the time it can be installed
Indoor Storage Space is available in C-AD complex if needed
• Work in 69 kV yard
•
•
•
•
Needs to be coordinated around the Lab’s operating schedule
Needs to be coordinated around LIPA’s summer demands
Need to be able to de-energize a portion of the 69 kV bus
Construction scheduled extended to incorporate two summer/fall
periods to allow ample time for shutdowns and coordination with
site operating schedules
13
BROOKHAVEN SCIENCE ASSOCIATES
69 kV Gas Insulated Circuit Breaker
14
BROOKHAVEN SCIENCE ASSOCIATES
20 MVA Main Transformer
15
BROOKHAVEN SCIENCE ASSOCIATES
15 kV Switchgear
16
BROOKHAVEN SCIENCE ASSOCIATES
Main Substation Installation
17
BROOKHAVEN SCIENCE ASSOCIATES
Secondary Unit Substation
18
BROOKHAVEN SCIENCE ASSOCIATES