16th ALICE RRB Collaboration Status Project Status
Download
Report
Transcript 16th ALICE RRB Collaboration Status Project Status
16th ALICE RRB
Collaboration Status
Project Status
Integration, large structures
Detectors (selection)
Planning, Milestones
28 April 2004
16th ALICE RRB J. Schukraft
CERN-RRB-2004-044
Collaboration Status
Institutes
new: CTU Prague (Czech Republic)
participates in ITS and TDR
contacts: Turkey, Brazil, Spain, Pakistan …
Organization
Chris Fabjan re-elected as Technical Coordinator for 3 years
elections in 2004: CB chair (cur: L. Riccati), Deputy Spokesperson (cur: Y. Schutz)
Funding Issues
US participation (~ 10 M$): EMCAL for jet physics
NSAC sub committee on US heavy ion program (GSI/RHIC/LHC)
intermediate report by July, final report by September 2004
Japanese participation (~ 10 M$): TRD, PHOS
proposal re-submitted end 2003, feedback expected spring 2004
Chinese participation (~ 3 MSF): PHOS
new proposal at NSFC, no reaction so far..
Consequences for PHOS
with the resources available we will be able to built only 3 modules
1 ready for installation in 2006/2007/2008 each..
2
28/4/2004 16th RRB J. Schukraft
ACCORDE
HMPID
TOF
TRD
TPC
PMD
PHOS
ITS
Muon arm
ALICE Detector
3
28/4/2004 16th RRB J. Schukraft
Installation, Services, Large Structures
Services, electronic racks
design work to root services, cables etc..
first services installed at back door of L3
concern: magnetic stray field at electronics rack locations (50 G – 200 G)
miniaturization of components since L3-times (eg cooling fans !)
=> more sensitive to stray fields
implications & remedies under investigation
Space frame & support frames all finished
transferred to SXL2 for load tests and integration with TPC & ITS
additional activity planned for summer 2004
initiated after discussions during the LHCC installation reviews
L3 magnet: back door permanently closed in March
Muon Magnet: Yoke pre-assembly finished
power test: after summer
installation in final position: starting October
Muon absorber
4
most pieces at CERN, assembly to start in May
28/4/2004 16th RRB J. Schukraft
LAYOUT : STABLE; SYSTEMS (CABLES, COOLING,
GAS…) ENTERED INTO EUCLID
CR4 22.03.2004
C.W.Fabjan
5
Services
CR4 22.03.2004
C.W.Fabjan
6
7
28/4/2004 16th RRB J. Schukraft
Preparing Space Frame for
TPC/ITS/TRD/TOF Integration
CR4 22.03.2004
C.W.Fabjan
8
Closing of L3 back Door
Major milestone, achieved on 5 March 2004
9
28/4/2004 16th RRB J. Schukraft
Permanent closure of L3 door in RB26 (05/03/04)
10
28/4/2004 16th RRB J. Schukraft
L3 Magnet with Support Beams & Service Wheel
11
28/4/2004 16th RRB J. Schukraft
Muon Magnet Yoke
Muon Yoke arrived from JINR between Oct and February
> 8 months delay ! However, assembly went very smooth
Consequences for Installation: Parallel work in the pit required
12
28/4/2004 16th RRB J. Schukraft
ALICE CR-4
March 2004
L. Leistam
13
Yoke Assembly completed 19 Feb 2004
14
28/4/2004 16th RRB J. Schukraft
Muon Absorber Components
Aluminum from Armenia
cone from Finland
Steel
complex
mechanical piece ~ 100 tons (W, Fe, C, concrete, ..)
Material mostly at CERN, assembly will start in May
after extensive re-design ‘to cost’ now slightly below CORE cost !
Global collaboration with Institutes & Industry from over the world
Concrete from France,
Assembly team from Russia,
Graphite & Steel from India
Lead from England
Italian polyethylene
Support from Italy
15
Tungsten from China
China 10/2003 J. Schukraft
Silicon Pixel Detector SPD
successful system beam test Oct. ’03
Bump Bonding Yield
~ 300 missing channels
out of > 200 000
including full FEE and DAQ
bump bonding at VTT (Finland)
5 very good assemblies end ’03 & early ’04 (e > 99%)
defects
production schedule agreed with LHCb
40
production start April ’04
35
assembly sites
30
Padova/Legnaro, Bari operational
25
Status
20
15
viable schedule, but tight & little contingency
yield and speed of mass production
to be verified
10
defects
40
Action:
5
35
reduce number of assemblies by ~ 30%
0
30
production & assembly yield now estimated to be better
25
20
15
16
1
2
3
chip no
4
5
ladder 1
ladder 2
ladder 3
ladder 4
ladder 5
28/4/2004 16th RRB J. Schukraft
Silicon Drift Detector SDD
Detectors
NTD raw material now available from 2 (!) suppliers
start of detector mass production April ’04
FEE
engineering runs ok, sufficient chips available for start of production
production runs start by summer
Status
viable schedule, but tight & little contingency
yield and speed of mass production to be verified
Action:
foresee double shifts for assemblies
starting in 2005
17
Pre-production SDD’s
28/4/2004 16th RRB J. Schukraft
Silicon Strip Detector SSD
Production:
sensors
2 producers had production problems (solved now)
Action: additional order to ITC (=> not critical)
FEE electronics: all chips in production
micro-cables & hybrids (Ukraine):
production delayed (funding), now rapid progress
Assembly
funding by ministry starting May
sites ready; small series pre-production validated
Strasbourg, Trieste, Helsinki, NIKHEF, Nantes to follow
Status
viable schedule, but very tight & no contingency
mass production of cables & hybrids on critical path
yield and speed of module assembly to be verified
Action:
startup funding for cables & hybrids found
looking for additional production site in Spain
(make use of existing infrastructure & interested groups)
18
P-Hybrid
Sensor
N-Hybrid
28/4/2004 16th RRB J. Schukraft
TPC
Field Cage
Final Gas system
most of delay recuperated
finished : June ‘04
Chambers finished by May
IROC: 100 % done , OROC: 75 % done
Electronics
well on track for start of installation
decision in rad. tolerant FPGA to be made
Services: Gas system finished
Planning
system test with beam: May – June 2004
IROC, full electronics, DAQ, DCS
integration tests (ITS, Space Frame): 8-10 ’04
ROC installation: start end ’04
FEE installation: start May ’05
pre-commissioning (laser, cosmics): June ’05 – Feb. ’06
19 final installation: 5 ‘06
Laser system 28/4/2004 16th RRB J. Schukraft
Mounting the TPC Central Electrode
20
28/4/2004 16th RRB J. Schukraft
Inside the TPC Field Cage
21
28/4/2004 16th RRB J. Schukraft
ALTRO Mass Production Test
ALTRO TEST SETUP at LUND
22
PHOS
technical progress correct
crystal production (Apatity, Russia):
very smooth, excellent quality
now 5000 (of 18,000) crystals accepted
~650 crystals from Ukraine
(financed by JINR & Poland)
electronics, mechanics, services:
design & prototyping ongoing
Light Yield
but major uncertainties in funding
crystals financed largely from additional resources
in Russia (MinAtom, Kurchatov Inst.)
yearly allocation, recent re-structuring of Govt. in Russia ?
no final decision on participation from China & Japan
very good ‘informal’ collaboration & participation in R&D
Consequence: ‘staging’ of PHOS modules
current finances sufficient for 3 (out of 5) modules
installation of one module each in 2006/7/8
23
ALICE & CMS type crystals
Apatity,
Russia
28/4/2004
16th RRB J. Schukraft
Muon Arm
Tracking Chambers: mass production started
Station 1 & 2: new design validated in lab & in beam
Station 3/4/5: all 4 production sites started
large gain dispersion in FEE (Manas) => calibration needed
Trigger Chambers: mass production started
chambers, FEE, trigger: all well on track
assembly & integration of full trigger only by mid 2006: somewhat tight
Trigger Chambers
Production of R/O strips,
Torino, Italy
24
Module 0 of Station 2
Kolkata, India
28/4/2004 16th RRB J. Schukraft
Other Detector Systems
HMPID: well on track
50% of modules completed, rest by end 2004
beam test performance above specs; system integration & services very advanced
ZDC: well on track
neutron calo’s finished & tested, proton calo’s under construction
PMD: well on track
re-location addendum to TDR approved by LHCC; construction started
Forward Detectors (V0, T0, FMD): progress, to be accelerated
TDR delayed to September (final design choices to be made)
TRD: on track
chamber mass production started (Heidelberg, JINR) or to start in July (GSI, Bucharest)
electronics in production (PASA) or pre-production (TRAP)
TOF: on track
module 0, services & FEE chain validated, mass production about to start (tenders ongoing)
HPTDC production run: very low yield ! (under investigation)
Trigger, DAQ, HLT, Control (DCS, ECS): TDR submitted Jan 2004
25
all systems progressing well and on schedule
major activity of integration of these systems with detectors has started
28/4/2004 16th RRB J. Schukraft
HMPID
MODULE 1: RESULTS FROM BEAM TEST
Sensitivity of 4 cathodes
Required : > 12 clusters
Measured :> 18 clusters
Uniformity of gain across
Cathode plane
PC40
Nominal gain
CR4 22.03.2004
C.W.Fabjan
Nominal gain
26
Chamber production in Heidelberg
TRD
Chamber production lab in JINR
27
Electronics and MCM bonding at28/4/2004
FZ 16th
Karlsruhe
RRB J. Schukraft
TOF: System test in beam
LV-DCDC
HV-DCS
TDC Readout Module
TRM
(PVSS)
FEA - NINO
Module 0
HV system
28
DAQ/Detector integration status
DATE
DDL
data generator
DDL
readout
MOOD
Data quality
monitoring
SDD
TPC
In progress
TRD
TOF
HMPID
Muon
In progress
SPD
SSD
PHOS
ZDC
FMD
T0, V0
PMD
CR4 22.03.2004
C.W.Fabjan
29
Data Challenges
reduced number of components (PC’s etc.) available in 2003
MByte/s
3000
DAQ bw
reliability of new equipment imperfect
2500
DAQ bw ALICE traffic
2000
DAQ bw flat traffic
MByte/s
800
1500
700
M.S. bw milestone
600
M.S. bw achieved
1000
500
500
400
0
1998 1999 2000 2001 2002 2003 2004 2005 2006
300
200
100
0
1998 1999 2000 2001 2002 2003 2004 2005 2006
CR4 22.03.2004
C.W.Fabjan
30
Offline
3rd Physics Data challenge (10% capacity): Jan – June 2004
Goals: Continuous testing of the ALICE computing model:
Reconstruction (AliROOT), production (AliEn) and analysis (AliROOT+AliEn+PROOF)
Produce and analyze the 10% equivalent of the yearly ALICE raw data output.
Detailed study of hard physics for the PPR
Status:
Currently in the first 1/3 of the program (event production)
Successfully using combined AliEn and LCG resources (50/50)
core software manpower: LHCC review 9/2003
a) increase long term staff from < 30% to ~ 50%: discussion with CERN, no progress yet
b) need 3-4 additional FTE: discussion with the major ALICE FA’s
Italy: willing to send 2 young people (from LCG manpower funds)
France: long term mission to CERN of one senior person agreed (incl. base salary)
BUT: ‘non residence allowance’ needed from ALICE
Germany: under discussion (from LCG manpower funds)
BUT: remaining funds for 2004/2005 only ½ FTE
UK: missed ‘eScience’ call (early-mid ’03)
BUT: exploring other options
hopefully sufficient ‘volunteers’ for offline
31
China 10/2003 J. Schukraft
additional funding (~ 100 kSF/y) needed; via Cat A M&O ??
Milestones
ALICE LHCC Milestones - September 2003
October 2003: Significant
number of delays and missed Milestones
500
450
400
nb of milestones
350
300
Baseline
Passed
250
200
150
100
50
0
Jul-98
Aug-99
Oct-00
Nov-01
Dec-02
Jan-04
Feb-05
Mar-06
Apr-07
Jun-08
Action: In depth internal planning and status review of all major projects
32
28/4/2004 16th RRB J. Schukraft
Milestones
January 2004: getting back on track
ALICE LHCC Milestones - January 2004
500
450
nb of milestones
400
350
300
Baseline
250
Passed
200
150
100
50
0
Jul-98
33
Aug-99
Oct-00
Nov-01
Dec-02
Jan-04
Feb-05
Mar-06
Apr-07
Jun-08
28/4/2004 16th RRB J. Schukraft
Installation dates
( unchanged since early 2003, except for Muons and PHOS)
Sub detector
Muon Tracking
Muon Trigger
HMPID
Ready to install
Start installation
End installation
Float
Q4/05 (12/2004 – 12/2005)
10/2005
04/2006
> 3 months
Q4/05 (01/2005)
07/05
01/2006
> 2 months
12/2005
02/2006
4/2006
2 months
Minimize
storage time
TRD
Stage1
Stage 2
09/2005 (n modules, n>3)
04/2006 (18 – n modules)
09/2005
04/2006
02/2006
05/2006
3 months
TOF
Stage 1
Stage 2
09/2005 (n modules)
08/2006 (18 - n modules)
10/2005
11/2006
04/2006
02/2007
3 months
06/2005 (cradle)
06/2006 (1 module)
06/2007 (1 module)
08/2005
11/2006
12/2007
08/2005
12/2006
03/2008
5 months
6 months
TPC
02/2006 (incl.9 months of test)
05/2006
11/2006
3 months
ITS
04/2006 SPD
03/2006 SSD and SDD
06/2006
11/2006
2 months
critical
C.W.Fabjan 11/2006
12/2006
34
5 months
PHOS Stage 1
Stage 2
PMD
CR4 22.03.2004
06/2006
Summary
Collaboration
major decisions outstanding (US, Japan, China)
Funding
major uncertainty :
PHOS, TRD: awaiting decisions in China & Japan
not funded:
40% of TRD, 2 PHOS modules, EmCal (new, USA)
Detector construction
major problems solved:
TPC: inner field cage delay mostly recuperated
muon tracking: start of mass production
muon magnet: all pieces at CERN, pre-assembly finally started
ITS micro-cables: production quickly ramping up
major problems remaining:
ITS: tight schedule, pre-production just started
forward detectors: slow progress in design choices
core software manpower: secure additional contributions & finances
35
28/4/2004 16th RRB J. Schukraft