Office of Innovations and Solution ACB-1 Project Management Principles and Practice for Managers

Download Report

Transcript Office of Innovations and Solution ACB-1 Project Management Principles and Practice for Managers

Office of Innovations and Solution
ACB-1
Project Management
Principles and Practice for Managers
Presented by: Pat A. Eigbe, PMP®
Office of Innovations and Solutions, ATO-P
February 17, 2004
Briefing Outline
Project Management (PM) as a Tool
 Project Management Terminology
 PM Relationship to other Disciplines
 Project Management Processes
 Project Management Tools & Techniques
 Summary/Conclusion
 Questions

February 17, 2004
Pat A. Eigbe, PMP®
2
Project Management as a Tool
Minimize Fire Drills
 Efficient Use of Resources
 Develop Better Metrics
 On-time and On-budget Product Delivery
 Apply Lessons Learned
 Better Communications Between
Stakeholders
 Make Proactive Decisions

February 17, 2004
Pat A. Eigbe, PMP®
3
Project Management (PM) Terms
Project - A temporary endeavor undertaken
to create a unique product or service.
 ATOP or VSCS - Project has a specific
purpose with a start and an end date.
 Project Management - the Application of
Knowledge, Skills, Tools, and Techniques to
Project Activities to Meet Project
Requirements.

February 17, 2004
Pat A. Eigbe, PMP®
4
Project Management Terms II

Program - A group of related projects
managed in a coordinated way. Programs
usually include an element of ongoing
activity.
CPDLC, SMA, URET CCLD, pFAST,as FFP1
 PM Tools Development as part of Program
Management


A Project/Program Manager (PM) - The
Individual Responsible for Managing a
Project/Program.
February 17, 2004
Pat A. Eigbe, PMP®
5
Project Management Terms III
 Work
Breakdown Structure (WBS) “A deliverable-oriented grouping of
project elements that organizes and
defines the total scope of the project.
Each descending level represents an
increasingly detailed definition of a
project work.
February 17, 2004
Pat A. Eigbe, PMP®
6
Project Management Terms IV
 FAA standard
wbs1-0.ppt
 WBS Dictionary 3.1
 Requirement to use FAA Standard
WBS – Mandatory
February 17, 2004
Pat A. Eigbe, PMP®
7
Project Management Terms V



Deliverable – Tangible, verifiable work product or service.
Work Package – A deliverable at the lowest level of the
work breakdown structure. A work package may be
divided into activities.
Activity - Work elements with expected duration, cost, &
resources that may be subdivided into tasks.
February 17, 2004
Pat A. Eigbe, PMP®
8
Project Management Terms – VI
Stakeholder – Individuals or Organizations
that will be Impacted by the Outcome of a
Project.
 OBS: An Organizational Chart Relating
Work Packages to Organization Units.
 Responsibility Matrix: Relates Organization
Structure to WBS & Ensures that each
Element of the Project’s Scope is Assigned
to a Responsible Individual(s).

February 17, 2004
Pat A. Eigbe, PMP®
9
Project Management:
Relationship to Others Disciplines
The PMBOK™
Project Management
Knowledge and
Practice
General Management
Knowledge and
Practice
Application Area
Knowledge and
Practice
Figure is conceptual and overlaps are NOT proportional
February 17, 2004
Pat A. Eigbe, PMP®
10
Systems Engineering/PM
Relationship – I

PM Needs SE for
Integrated PM System Design
 Requirements for HW and SW Tools


SE Needs PM for
Planning and tracking
 Managing Resources

PM System Designer Must Understand both
 SE Not Necessary for PM Practitioners

February 17, 2004
Pat A. Eigbe, PMP®
11
Systems Engineering/PM
Relationship - II

Risk Management
PM - Schedule, Cost & Technical/Quality
 SE – Compatibility of Components of a System
or Sub-System


Quality Management
PM - Process for Producing the Product
 SE - Ensure Product Meets the Quality
Specifications

February 17, 2004
Pat A. Eigbe, PMP®
12
Systems Engineering/PM
Relationship - III

Configuration Management
PM - Ensure Integrity of Schedule and System for
Schedule Management
 SE - Ensure Integrity of the System as Designed


Change Management
PM - Changes to Project Scope
 SE - Changes to System Requirement


Measurement
PM – Program cost & schedule performance
 SE – Technical Performance

February 17, 2004
Pat A. Eigbe, PMP®
13
PMI Certification
What is PMP®
 What PMP® is not
 PMP® Value to Holder & Employer
 PMP® Certification Process link – visit
 http://pm.act.faa.gov

February 17, 2004
Pat A. Eigbe, PMP®
14
PM Process Groups
Project Information Flow
Initiating
Processes
Planning
Processes
Executing
Processes
Control
Processes
Closing
Processes
February 17, 2004
Pat A. Eigbe, PMP®
15
Create Project Agreement/PD/SLA
Identify Project & Sponsor
Initiation
PM Process Flow
Start
No
1.5.1.5
1.5.1.1
PD/SLA OK?
Create the Project Plan (PMIP)
1.5.1.6
1.5.2
Yes
Planning
Create Project Team & Team Contract
Review/ Revise Plan (PMIP)
No
1.5.2
Yes
Plan OK?
Yes
Execution
Execute Plan & Create Deliverables
Need Changes/
Corrective Action?
1.5.3
Control
Monitor/Review Progress & Deliver Products
1.5.4
No
No
Deliver Final Deliverables/
Deliverables
Accepted?
1.5.4.5
Yes
Closing
Perform Post Project Evaluation & Prepare Close-Out report
1.5.5
No
February 17, 2004
Report
OK?
Yes
Project
Completed!!!
Pat A. Eigbe, PMP®
16
Initiation Processes



Identify project and sponsor
Appoint Project Manager
Train team on
Project Management Process
 Project Plan (PMIP)


Develop Program Directive to Include
WBS that Covers the Scope
 High-level Milestones
 Budget resources

February 17, 2004
Pat A. Eigbe, PMP®
17
Planning Processes I

Identify Life Cycle approach
Evolutionary (AMS 6101, Section 2.2)
 Incremental
 Waterfall


Risk Management plan
February 17, 2004
Pat A. Eigbe, PMP®
18
Planning Processes II
Get approval for Program Directive
 Identify quality standards - use specs,
IEEE, ISO, PMBOK®
 Organizational structure
 Communications - who needs, what
 Acquire human resources for projects

February 17, 2004
Pat A. Eigbe, PMP®
19
Planning Processes III (Schedule
Development)
Update & Decompose WBS
 Identify activities
 Sequence
 Estimate duration
 Estimate cost
 Allocate resources to work packages
 Baseline schedule

February 17, 2004
Pat A. Eigbe, PMP®
20
Planning Processes IV

Risk management detail:
Identification
 Analysis
 Response
 Procurement

February 17, 2004
Pat A. Eigbe, PMP®
21
Implementation/Execution
Processes
Use the PMIP to execute project activities
 Assess Technical Performance to assure
product acceptance
 Distribute project information
 Make purchases
 Develop team skills/competencies
 Develop a Change Management plan

February 17, 2004
Pat A. Eigbe, PMP®
22
Performance Measurement Tools
Variances
 Performance Indices

Schedule performance Index (SPI)
 Cost performance Index (CPI)


Earned Value Management System (EVMS)
February 17, 2004
Pat A. Eigbe, PMP®
23
Earned Value Management System
Highlights
What is EVMS
 Planning for EVMS
 Tracking & Analysis
 Elements of EV Analysis
 Project Cost & Schedule Forecasting
 EV Reporting

February 17, 2004
Pat A. Eigbe, PMP®
24
Earned Value Management
System (EVMS) - I
EV - Tool for Measuring Project
Performance
 Integrates Cost, Scope & Schedule
measurements
 Compares work actually accomplished to
work planned
 EV is an Early Warning System
 Helps management make proactive
decisions to keep projects on course

February 17, 2004
Pat A. Eigbe, PMP®
25
Earned Value Management
System (EVMS) - II

Involves Calculating 3 key Elements
Budget - BCWS
 Actual Cost - ACWP
 Earned Value/Physical Progress - BCWP


Basis for variance analysis
February 17, 2004
Pat A. Eigbe, PMP®
26
Planning for EVMS - I
Create a work breakdown structure
 Organize work into discrete work packages
and activities
 Allocate a budget to each of the activities
 Develop a schedule and Assign resources
 Must include all project work in the
schedule
 Establish the Project Baseline

February 17, 2004
Pat A. Eigbe, PMP®
27
Planning for EVMS - II
Award performance credit for physical %
complete:
 0-100

Short duration tasks < 160 hours
 EV is Zero until activity is complete


50-100
Duration less than 600 hours
 50% at start of activity & 50% at completion

February 17, 2004
Pat A. Eigbe, PMP®
28
Planning for EVMS - III

Interim milestone;
Duration less than 600 hours
 Based on completed milestone for task


Level of Effort (LOE)
Long duration & consistent tasks
 Difficult to measure - no tangible deliverables
 Measured by duration of time used e.g. 10
weeks support is 50% complete at 5 weeks

February 17, 2004
Pat A. Eigbe, PMP®
29
Tracking & Analysis

Each update cycle/Reporting Period:
Obtain physical % complete for each task
 Calculate EV for each task
 Sum up EV for all tasks as project EV
 Calculate actual expenditure for actual work
completed during the period
 Compare the Cumulative EV to Actual
expenditure

February 17, 2004
Pat A. Eigbe, PMP®
30
Elements of EV Analysis - I
Performance indices relate value of work
performed to dollar spent. e.g. CPI = 0.65
means that for every dollar spent, actual
value of the work performed is $0.65.
 Cumulative CPI used to forecast project
cost at completion
 Cumulative SPI used to forecast project
completion date

February 17, 2004
Pat A. Eigbe, PMP®
31
Elements of EV Analysis - II

Cost Variance - Difference between
budgeted cost of an activity & actual cost of
that activity


CV = EV - ACWP
Schedule Variance - Difference between
scheduled completion & actual completion
of an activity

SV = EV - BCWS
February 17, 2004
Pat A. Eigbe, PMP®
32
Elements of EV Analysis - III
SPI – EV/Planned Value
 SPI => 1.0, Project Schedule performing as
planned or better
 SPI < 1.0, Project not performing as
planned - needs help

February 17, 2004
Pat A. Eigbe, PMP®
33
Elements of EV Analysis - IV
CPI – EV/Actual Cost
 CPI => 1.0, Project Cost performing as
planned or better
 CPI < 1.0, Project Cost not performing as
planned - needs help
 % Over/Under Budget = CAC - BCWS

February 17, 2004
Pat A. Eigbe, PMP®
34
Project Cost & Schedule Forecast
Methods

Estimate at Completion (EAC) is total cost
to complete an activity, work package, or a
project expressed as:


EAC = Actuals-to-date + Estimate to complete
(ETC)
Cost EAC = BAC/CPI
February 17, 2004
Pat A. Eigbe, PMP®
35
EV Reporting
Interpret the output of EV calculations
 Take corrective action as necessary
 Recommend or take corrective action as
necessary

February 17, 2004
Pat A. Eigbe, PMP®
36
Control Processes I

Coordinate and control changes to project
scope/requirements
 schedule
 budget

Monitor and manage product quality
 Measure progress and report performance

February 17, 2004
Pat A. Eigbe, PMP®
37
Control Processes II

Monitor and control risks
keep track of identified risks
 monitor residual risks
 identify new risks
 ensure execution of risk plans
 assess effectiveness in reducing risk

February 17, 2004
Pat A. Eigbe, PMP®
38
Closing Processes
Close out contracts
 Resolve any outstanding issues
 Document lessons learned
 Evaluate project
 Archive all project documents

February 17, 2004
Pat A. Eigbe, PMP®
39
Conclusion
Defined Frequently used PM Terminologies
 Discussed Objectives of Adopting Project
Management Principles.
 Discussed PM Processes, Tools &
Techniques
 Discussed EVMS Overview
 Questions

February 17, 2004
Pat A. Eigbe, PMP®
40
References






Project Management Institute (PMI), 2000. A Guide to the
Project Management Body of Knowledge (the PMBOK®
Guide)
Stratton R. W., 1999. Improving SPI and CPI Calculations
on LOE Heavy Programs, Proceedings of the 30th Annual
PMI Seminars & Symposium
Fleming and Koppeman, 1996. Earned Value Project
Management.
Ibbs W & Reginato J., 2002. Quantifying the Value of
Project Management
Kerzner H, 2003. Project Management: A Systems
Approach to Planning, Scheduling, and Controlling.
FAST @ http://fast.faa.gov/wbs/wbssec.htm
February 17, 2004
Pat A. Eigbe, PMP®
41
Questions/Need Help?
http://pm.act.faa.gov
Pat A. Eigbe, PMP®
Ext. 5-7857
[email protected]
February 17, 2004
Pat A. Eigbe, PMP®
42