Calais, ME-St. Stephen,NB Border Crossing Project A Case Study
Download
Report
Transcript Calais, ME-St. Stephen,NB Border Crossing Project A Case Study
Calais, ME-St. Stephen,NB
Border Crossing Project
A Case Study
Agenda
Introduction
Planning,
coordination, and permitting
Considerations during Design
Considerations during Construction
Lessons learned
Introduction
New crossing discussed for about 30 years
8th busiest commercial crossing along the U.S. /
Canadian border
Annual traffic – 2.9 million vehicles
7,500 AADT including 550 heavy trucks
Delays inbound to the U.S. can be up to
2 hours
Truck traffic entering Maine has doubled since
NAFTA implementation (70,000 to 140,000 annually)
Project Management
Maine
and New Brunswick DOTs
share the costs of bridge
design/construction on a 50/50
basis
MaineDOT: Bridge design lead
MaineDOT: Project Manager for the
bridge construction portion
Agencies — U.S.
FHWA
– lead federal agency
MaineDOT
GSA – cooperating agency
U.S. Department of Homeland Security
Customs and Border Protection
U.S. Border Patrol
U.S.
Department of State
Agencies — Canada
New Brunswick Department of Transportation
Transport Canada
Canada Border Services Agency
Canada Revenue Agency
Citizenship & Immigration Canada
Foreign Affairs Canada
Royal Canadian Mounted Police
Four Alternatives
including no
action
considered
Alternatives 2A
and 3 deemed
viable
Chosen:
Alternative 3
Calais Industrial
Park
Timeline
Preliminary design and NEPA compliance –
started 1999
FHWA issued FONSI in July 2002
Final design and permitting
July 2002 – September 2006
Construction Begins
NBDOT - Spring 2006
MaineDOT – Spring 2007
GSA and CBSA - 2007
Open to traffic - Fall 2008
This Last Year…
January 2006 – Reevaluation of 2001
Environmental Assessment
May 2006 – Army Corps of Engineers request
for details
June 2006 – Maine DOT replies
June 2006 - US Coast Guard Approval
Sept 2006 – Army Corps of Engineers approval
Project tendered September 27, 2006
Planning
Maine
and New Brunswick circulated
studies at same time
Changes in process
(New Brunswick was very flexible)
Public Involvement
9 PAC meetings, 2 public meetings,
and 1 formal public hearing
MaineDOT
– GSA enter into a cost
reimbursement agreement for NEPA
International Coordination
Partnership, respect for others’ process,
flexibility
International Stakeholders workshops
Every 6 months to 1 year throughout the process
International partnering agreement
Master schedule discussed and developed
Good forum for troubleshooting problems like
labor issues
Communication between workshops
Find ways to maintain national focus for
future funding purposes
TBWG, BSPC, etc.
Permitting — Coast Guard
Bridge Permit
Required for an international bridge
Cooperating agency under NEPA
Bridge permit
40% plans required
Approved Presidential Permit is also
required
Long lead time is necessary
Permitting – Presidential
Permit
U.S. Department of State 2003-2005
No precedent for the northern border
First one in at least 30 years
Guidelines for complete application
State Dept. distributes application to at least
55 agencies for comment and determinations
Prepared and circulated own EA and FONSI as
part of their process as well
Treaties and Approvals
Transport Canada – New Brunswick
agreement
This project spurred a new Canadian equivalent
of the U.S. Presidential Permit process
International Boundary Commission
approval
International Joint Commission or exchange
of diplomatic notes required between
Foreign Affairs Canada and U.S. State
Department
MaineDOT - New Brunswick agreement to
construct and reimburse
Design Considerations — U.S.
Inspection facility – increased in size from 20 to
50 acres. (Post 911)
MaineDOT – GSA cost reimbursement agreements
Advance notice for materials and people crossing
the border
Buy America clause for steel
MaineDOT – NBDOT funding and management
agreement
Bridge contractor ‘fact sheet’ and prequalification
Coordination between GSA and MaineDOT of design
issues; staging issues, exchange of plans, etc.
Considerations During
Construction - Labor
Labor
and requirements for foreign
workers
Human Resources Development
Canada-Canadian Labor Market
Opinion
CBSA – immigration
Maine Dept of Labor
Security and background check
Ideal worker – dual citizenship, no
Considerations During Construction Security
Security
during construction
U.S. Border Patrol
RCMP
Movement of workers; must be
able to cross border within project
limits
No precedent on this issue
Considerations During
Construction - Taxes
U.S
Canada
Customs Duties
EXEMPT
All international
bridge projects are
exempt
Exempt – but imports
need NAFTA certificate
of origin
Sales Tax
EXEMPT
None
Value Added Tax
(GST/HST)
None
6% GST collected at
border
14% HST
Income Tax
Withholding
Non-resident
withholding
NB responsible for 15%
non-residents
Lessons Learned
Partnerships among agencies on both sides of
the border that are built to last
Respect for others and stay flexible
Communicate and communicate some more
Combine NEPA/Presidential Permit Process as
much as possible
Maximize the use of the cooperating
agencies
Taxation issues for international bridge
projects are complex
Project Status
International Bridge Construction (11.58 Million)
March 2007 – Summer 2008
U.S. Inspection Facility
Summer 2007 – Fall 2008
US Route 1 (9.33 Million):
April 2007 – Summer 2008
NB Route 1:
Spring 2007
Canadian Inspection Facility
Summer 2007 – Fall 2008
Calais, ME-St. Stephen,NB
Border Crossing Project