Britannia Village Flood Control System Information Meeting for Directly Affected Landowners
Download ReportTranscript Britannia Village Flood Control System Information Meeting for Directly Affected Landowners
Britannia Village Flood Control System Information Meeting for Directly Affected Landowners February 5, 2009 Agenda Introductions (D.Downey) The Project’s History to date (B.Reid) The Planning and Design Process (D.Yaeger) The Project Schedule (D.Yaeger) About Easement Agreements (B. Reid) The Special Service Charge Process (G.Gill) Introductions Moderator – Diane Downey (RVCA Communications) Speakers: • Dave Yaeger – Delcan Corporation • Gina Gill – Ottawa, Infrastructure Services • Bruce Reid – RVCA Waterfront Landowners The “Island” The Flood Plain Project History to Date May, 1979: max. water level = 60.26m 1980: Construction of some sea walls and berms to 60.3m+ 1984: 1:100 year flood = 60.77m 1992: flood damage reduction study 1996 to 2007: community discussions Sept 2007: Council approval to proceed with a remedial flood control project Design Criteria & Considerations Protection against 1:100 year flood level under calm winds, with 30 cm freeboard = 61.1 m Berms and seawalls Land-side drainage Permits and easements • Ministry of Natural Resources • Fisheries and Oceans Canada • Private landowners Planning and Design Process Engineering Phase 1: • review background • update cost estimate • Completed Aug. 2008 “Novatech’s 2005 preliminary design can be used as the starting point for detail Design.” Updated Construction Cost = $525,000 Conceptual Design Conceptual Design Conceptual Design Conceptual Design Conceptual Design Conceptual Design Conceptual Design Conceptual Design Planning and Design Process Engineering Phase 2: • Initiated November 2008 • Environmental impacts analysis • Site meetings with Landowners • Detailed physical surveys • Preliminary design drawings • Finalized Drawings Environmental Assessment In accordance with: Conservation Ontario’s Class Environmental Assessment for Remedial Flood and Erosion Control Projects” (approved by Ont. Min. of the Environment, June , 2002) Environmental Assessment “Notice of Intent” Community Liaison Committee Environmental Impacts Analysis Project Plan “Notice of Filing” 30 day public review period Project Plan Amendment (if necessary) “Notice of Project Approval” “Notice of Project Completion” Project Schedule Preliminary Field Layout Early April Site meetings/negotiations with landowners Early April to mid-May Establish preferred layout Mid-May Preliminary Design Drawings Mid-June Plan Circulation – City, agencies, landowners Mid-June Notice of Filing of Project Plan June 30 Final Design/Tender Package July 31 Notice of Project Approval July 31 Project Schedule (continued) Call for Tenders* Early August Award of Contract* (RVCA Board of Directors) August 27 Construction Commences Early September Substantial Completion of Construction Late November Final Site Restoration May, 2010 * Subject to confirmation that pre-tender construction cost estimate and lowest acceptable tender amount remain within City Council’s approved budget Permanent Easements convey rights to enter and occupy a specific area of the property for a specific purpose registered against title, runs with the deed The Area – defined by registered plan Purpose – for construction and maintenance of the flood control system and its component parts Easement Process Step 1 (April - May): “permanent easement acquisition agreements” sets out RVCA’s obligations: • • • • installations per engineering drawings site restoration, warranty provisions protection of adjacent works reimbursement of legal fees landowner agrees to grant permanent easement re: filled crown land MNR approval requires consultation with owners of immediately adjacent upland property Easement Process Step 2: construction proceeds in accordance with “permanent easement acquisition agreements” Step 3 (after construction): R-Plan prepared by surveyor and deposited at Land Registry Office Step 4: execution and registration of documents for transfer of easement Special Service Charges Ontario Regulation 305/02 and Section 326 of the Municipal Act 2001 allow the recovery of costs related to Special Service works from landowners via their tax bill Additional funding request currently scheduled to proceed to committee and council in April 2009 No change to cap on cost recovery amount from property owners Special Service Charges All costs will be recovered over the course of a ten-year period, with carrying costs as necessary Yearly charge amount for a property will be based on the property's assessed value relative to that of the rest of the properties in the Special Service area Charge will be an additional levy amount on the final tax notice for each property, due and payable at the same time as the property taxes Approximately $60 per year, per $100,000 of assessed value, for each property assessed in a single-family residential tax class Next Steps Field Layout and Site Meetings with Landowners – early April to mid-May Please sign a consent form for the field layout Please leave your contact info with us Questions?