- SEWER REHABILITATION - A TEN-STEP STRATEGIC PLAN GEORGE KURZ, P.E., DEE
Download
Report
Transcript - SEWER REHABILITATION - A TEN-STEP STRATEGIC PLAN GEORGE KURZ, P.E., DEE
- SEWER REHABILITATION A TEN-STEP STRATEGIC PLAN
GEORGE KURZ, P.E., DEE
615-252-4441 [email protected]
* A significant portion of this work was conducted
with CTE-AECOM as part of the Nashville Overflow
Abatement Program 1991-2005
SEMINAR OBJECTIVE
Teach a proven, successful strategy.
SUCCESSFUL REHAB
FACTORS
• DEFINE GOALS
• EXTENSIVE FLOW MONITORING &
STANDARD PROCEDURES
• LATERAL REHABILITATION
• “TARGETING” – STOP WATER MIGRATION
• ACCOUNTABILITY – VERIFY DESIRED
RESULTS
TOTAL SYSTEM APPROACH
- Nashville Policy GOAL: “CONTAINMENT” FOR FLOWS FROM 5YEAR, 24-HOUR RAINFALL
POLICY:
ALL SERVICE LATERALS CONNECTED TO THE
REHABILITATED PIPES WILL BE RENEWED TO
THE EASEMENT LINE OR THE PROPERTY LINE
ALL MANHOLES CONNECTED TO
REHABILITATED PIPES WILL BE RENEWED
1. Identify Goals
2. Select Target Area
Ten steps
3. Quantify Problem
4. Locate Defects
5. Select Pipe Segments
6. Estimate Cost-Benefit
7. Design & Install
8. Verify Performance
9. Follow-up Flow Monitoring
10. Calculate O & M Savings
1 - IDENTIFY COMMUNITY GOALS
“ELIMINATE OVERFLOWS AND BASEMENT BACKUPS”
• PERIOD OF TIME: 2
YEARS ?, 5 YEARS ?
• RELATE TIME TO
RAINFALL EVENT
RETURN INTERVAL
• NO OVERFLOWS
LEGALLY SANCTIONED
2 - SELECT TARGET AREA
• FLOW MONITORING NETWORK (~100,000
L.F.)
• CALCULATE OBSERVED & POTENTIAL I/I
• HYDRAULIC MODEL
• IDENTIFY CAPACITY PROBLEMS
• PRIORITIZE TRIBUTARY AREAS
DETECT CAPACITY PROBLEMS
(KIRBY 3 - MANNINGS SCATTERPLOT)
5.0
4.5
Velocity (ft/sec)
4.0
3.5
CAPACITY
LOST TO
HINDERED
FLOW
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0
1
2
3
4
HC=5.4, full pipe = 4.766 m gd
5
6
7
8
9
10 11
Depth (inches)
12 13 14 15 16 17 18 19
Mannings Vel
Metered Vel
variable n adjusted
hi-Flow
3 - QUANTIFY PROBLEM CONDITIONS
• INTENSIVE MONITORING IN TOP
PRIORITY TRIBUTARY AREAS (8,000 15,000 L.F.)
• OBSERVED AND POTENTIAL I/I
• ADDITIONAL CAPACITY PROBLEMS
SUM OF TRIBUTARIES
=53.5 mgd
WEST PARK METER
=32 mgd
POTENTIAL I/I = 21.5mgd
WEST PARK PUMPING
STATION - 32 mgd
Clifton 2 - 1.6mgd
1.6mgd Clifton 1
2.0 mgd Clifton 3
11 mgd West End
Clifton 4 - 1.3mgd
Murphy Rd.- 4.2mgd
2.1 mgd White Br
1.5 mgd Sugartree 1
Sugartree 2 - 12.9mgd
15.3 mgd Brentwood
I/I REMOVAL EFFECTIVENESS
- ACCOUNT FOR POTENTIAL I/I !!
Example: 52% I/I REMOVAL
2.5
PROJECTED METER
READING
I/I (mgd)
2
POTENTIAL I/I
1.5
PIPE CAPACITY
RESTRICTED FLOW
1
I/I AFTER REHAB
0.5
0
0
1
2
3
RAINFALL (inches-24 hours)
4
5
“POTENTIAL” I/I
• I/I Which Cannot Enter the Sewer Because
the Pipe is Already Overloaded!
• Overall I/I Removal Goals
• Monitor Depth & Velocity
• Extrapolated
DATA INTERPRETATION
• 24-hour rainfall more reliable than peak hour rain for
predicting peak design I/I
• AMC – Antecedent Moisture Condition is critical for
selecting valid rainfall events
• HINDERED FLOW - POTENTIAL I/I
There are
ways to correct for this, however the analyst must
be aware of this condition
• Underestimating the peak flow can result in the
inadequate design of new facilities
• Need to standardize criteria
PEAK
INFILTRATION/I
NFLOW RATE
(mgd)
REGRESSION ANALYSIS
PEAK I/I vs 24-HOUR RAINFALL
MI-09 YEAR 2004-05
140
120
100
80
60
40
20
0
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
24 HOUR RAINFALL (inches)
PEAK HOUR BEST FIT LINE
95% CONFIDENCE
95% CONFIDENCE
Peak-hour flow
(24-hr rain
vs. Peak-hr rain)
REMAINING CAP.(I/I)
PEAK
INFILTRATION/INFLOW
RATE (mgd)
PEAK HOUR RAIN I/I
COMPARISON OF
RESULTS
REGRESSION ANALYSIS
PEAK I/I vs. PEAK HOUR RAINFALL
MI-09 YEAR 2004-0
0.4
1.6
200
150
100
50
0
0.0
0.2
0.6
0.8
1.0
1.2
PEAK HOUR RAIN I/I
PEAK
HOUR
BEST FIT(inches)
LINE
24
HOUR
RAINFALL
95% CONFIDENCE
95% CONFIDENCE
1.4
1.8
REMAINING CAP.(I/I)
2.0
Which type rainfall pattern puts the most stress
on the system – for a standard return interval,
design storm?
Summer ?
Or Winter ?
TYPICAL RAINFALL
Type II Rainfall* – Characterized by short-term,
high intensity thunderstorms and also by
long-duration frontal storms.
* USDA-SCS 1986
NASHVILLE
5-Year, 24-Hour & 3-Hour Design Rainfall
2
1.8
5-YEAR, 3-HOUR
Peak Rain =1.97"
Depth (inches)
1.6
1.4
5-YEAR, 24-HOUR
Peak Rain =1.26"
1.2
1
0.8
0.6
0.4
0.2
0
0
5
10
15
20
25
Hours
24-Hour rain
3-Hour Rain
Design Storm Peak: 2-Yr, 24-Hr vs. 3-Hr
PEAK I/I vs 24-HOUR RAINFALL
CMC02 - YEAR 2003
4.0
Peak hour I/I from 2-Yr, 24-Hr
Storm is 3.89 mgd with good
3.5
r= 0.91
3.0
level of confidence
95% Conf. =
16%
2.5
2.0
1.5
1.0
0.5
0.0
0.00
0.40
0.80
1.20
1.60
2.00
2.40
24 HOUR RAINFALL (inches)
PEAK HOUR RAIN I/I
95% CONFIDENCE
PEAK HOUR BEST FIT LINE
95% CONFIDENCE
Peak hour I/I from 2-Yr, 3-Hr
Storm is 2.35 mgd with poor
PEAK INFILTRATION/INFLOW
RATE (mgd)
PEAK INFILTRATION/INFLOW
RATE (mgd)
4.5
2.80
4.0
3.20
PEAK I/I vs 3-HOUR RAINFALL CMC02 2003 3-HOUR STO
3.60
REMAINING CAP.(I/I)
3.5
3.0
2.5
2.0
r= 0.47
1.5
95% Conf.= 87%
1.0
0.5
0.0
level of confidence
0.0
0.5
1.0
1.5
2.0
2.5
24 HOUR RAINFALL (inches)
PEAK HOUR RAIN I/I
95% CONFIDENCE
PEAK HOUR BEST FIT LINE
95% CONFIDENCE
REMAINING CAP.(I/I)
4 - LOCATE & IDENTIFY DEFECTS
• TELEVISE TARGET AREA SYSTEM (MAY
BE CONCURRENT WITH MONITORING)
• CATEGORIZE
DEFECTS WITH
RESPECT TO I/I
POTENTIAL
4 - LOCATE & IDENTIFY DEFECTS
(CONT.)
• “INVISIBLE” DEFECTS - ELECTRIC FIELD
LEAK DETECTION, SEGMENTAL
ISOLATION
• GROSS INFLOW (ROOF DRAINS, ETC.)
5 - SELECT SEGMENTS FOR
REHABILITATION
• CATEGORIZE & COLOR CODE LINES
– 3 OR MORE MAJOR DEFECTS
– 1-2 MAJOR DEFECTS
– NO MAJOR DEFECTS
• “3 OR MORE” - RENEW !
• CHECK ADJACENT SEGMENTS
• RENEWAL “INTENSITY” - RANGE OF 1520% FIRST ROUND
CONNECT THE DOTS
> 3 DEFECTS
< 3 DEFECTS
?
0 DEFECTS
25 % intensity
?
METER
?
?
REHABILITATE
SEWER REHAB STRATEGY:
HALT MIGRATION !
INVISIBLE DEFECT
LEAK
"DRY" DEFECT
POTENTIAL LEAK
LEAK
"NEW" LEAKS REVEALED FOLLOWING
TRADITIONAL REPAIRS
LINING OR REPAIR
6 - ESTIMATE COST-BENEFIT
• COMPARE RENEWAL COSTS TO: O&M
COSTS ($1.73 - $1.87/ 1,000 GAL)
• AT LEAST 50% I/I REMOVAL
• COSTS:
– LINING (8-10” CIPP) ~ $43 / LF
– LATERALS ~ $2,250 ea. (1/ 200 LF)
– MANHOLES ~ $1,000 -1,300 ea. (1/200 LF)
– ENGINEERING ~ 12% - 15% OF TOTAL
(GROSS= ~ $132/ft rehab)
7 - DESIGN & INSTALL REHAB
• HALT MIGRATION FROM OUTSIDE PIPE
• HALT MIGRATION (“TRACKING”) INSIDE
PIPE
• PROVIDE SEAL AT MANHOLE JUNCTION
• RENEW SERVICE LATERALS
(over 10,000 rehabilitated in Nashville)
LATERAL REHABILITATION
EFFECTIVENESS
DOWNINGTON, PA -area 5
38 laterals in 1,513’ CIP - 100% treated
97% reduction - 22 mg annually
STEGE SAN. DIST, CA - subarea N
111 laterals in 13,400’ Slip-PE & MH - 100%
86% reduction
NASHVILLE, TN - Oak Valley
63 laterals in 4,400’ CIP - 41% treated
77% reduction (20%-laterals) - 67 mg annually
8 - PERFORMANCE TESTING
• AIR-TEST SEWER SERVICE CONNECTION !
– MOST VULNERABLE PART
– NOT ACCEPTED UNTIL PERFORMANCE
VERIFIED
9 - FOLLOW-UP FLOW MONITORING
• QUANTIFY I/I REDUCTION
• STANDARDIZED I/I ANALYSIS
• TV DURING WET WEATHER
• RERUN HYDRAULIC MODEL
• DETERMINE IF DESIGN GOALS MET !
5-YEAR, 24-HOUR I/I REDUCTION (CU-01 1999-2002)
5.0
4.5
24-hour I/I (m g)
4.0
CAPACITY
3.5
3.0
I/I REDUCTION
BEFORE REHAB
2.5
2.0
1.5
AFTER REHAB
1.0
0.5
0.0
0
0.5
1
1.5
I/I Before Rehab
2
2.5
24-hour rainfall (in.)
I/I After Rehab
3
3.5
4
Linear (I/I Capacity)
4.5
STANDARDIZED I/I ANALYSIS
• DEFINES LEVEL OF CONFIDENCE FOR
PROJECTED I/I
• USES QA/QC CONTROLS THAT ARE
SIMILAR TO “STANDARD METHODS”
(nationally recognized)
Example: Typical Nashville Rainfall Event Analysis
1.600
FLOW (MGD)
ADF= 0.3 mg
(adjusted to match
beginning of storm
flow @ 0.99 mg)
WL02 2-01
1.200
0.3
1.000
0.25
0.800
0.2
0.600
0.15
0.400
0.1
0.200
0.05
0.000
0
Total Flow
A
2: M
00
A
4: M
00
A
6: M
00
A
8: M
00
10 AM
:0
0
12 A M
:0
0
P
2: M
00
P
4: M
00
P
6: M
00
P
8: M
00
10 PM
:0
0
12 P M
:0
0
AM
Hour
0.4
0.35
TIME (HOURS)
DRY WEATHER
ADF
0.45
1.400
05:45 07:45 09:45 11:45 13:45 15:45 17:45 19:45 21:45 23:45 01:00 03:00 05:00
:0
0
12
Average Flow, MGD
0.45
0.40
0.35
0.30
0.25
0.20
0.15
0.10
0.05
0.00
WET WEATHER
HYDROGRAPH
1.800
7 day dry flow
Characteristic Base Flow Curve
0.5
Infiltration/Inflow
Base Flow
Rain
2.11” Rainfall
24-hr I/I
=0.37 mg
RAINFALL (INCHES)
2.000
Peak-hr I/I
=0.738 mgd
NASHVILLE REHABILITATION EFFECTIVENESS
ANNUAL I/I REDUCTION FROM REHABILITATION
ANNUAL I/I REDUCTION (MG)
800
700
600
500
400
300
200
100
0
0
10,000
20,000
30,000
40,000
50,000
REHABILITATION LENGTH (FT)
ANNUAL I/I REDUCTION (MG)
Linear (ANNUAL I/I REDUCTION (MG))
60,000
EFFECTIVENESS
(a “rule of thumb”)
15-20%
REHABILITATION
INTENSITY
(including MH & laterals,
& in deteriorated areas)
~ 8-10 MILLION
GALLONS ANNUALLY
per 1,000 ft.
LINING or
REPLACEMENT
10 - CALCULATE O&M SAVINGS
• POSSIBLE 7-11 YEAR PAYBACK
(construction)
• PROVIDES DATA FOR FUTURE
PROGRAM PLANNING
• ACCOUNTABILITY TO COMMUNITY
PROGRAM PAYBACK COMPARED TO O&M
CHARGED
Years to Payback
35
8 Mill Gal Removed per Year/1,000 ft Lining
Total Program costs ~ $ 700,000/ mile
20% intensity
30
25
20
15
10
5
0
$0.80
$1.00
$1.20
$1.40
O & M ($ per 1,000 gal)
$1.60
$1.80
$2.00
Payback years
SUCCESSFUL REHAB
FACTORS
• EXTENSIVE FLOW MONITORING
• LATERAL RENEWAL TO EASEMENT
• “TARGETING” - LINING SELECTED BY
OBSERVED DEFECTS, AGE, PROXIMITY,
MIGRATION POTENTIAL, SURFACE
WATER
• PERFORMANCE (AIR) TEST LINE &
LATERAL
STRATEGIC GOALS MET
• I/I REDUCTION
• SSO REDUCTION
• STREAM IMPROVEMENT
NASHVILLE MEASURED RESULTS
For the 27 areas (94 miles) analyzed so far:
3.6 billion gallons I/I eliminated annually
49.6%
Annual I/I eliminated
53%
24-hour, 5-year I/I reduction
52.2%
Peak-hour, 5-year I/I reduction