F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC

Download Report

Transcript F08 – 72 – OUTGRESP First Contingency Outage Response for SIUC

F08 – 72 – OUTGRESP
First Contingency Outage
Response for SIUC
Client: SIUC Physical Plant Engineering Services
Team Members:
Rudy Probst, EE
Kyle Moore, EE
Terry Campanella, PM, EE/CpE
Clint Frederick, EE
Phil Craig, EE
Tanner Jones, EE
Faculty Advisor: Dr. Constantine Hatziadoniu
Client Contact: Steve Lazorchak, PE
Outline of Topics






Executive Summary – Rudy
Description, Options, and Justification – Kyle
Mechanical Considerations Subsystem – Terry
System Protection Subsystem – Clint
Universal Transformer Subsystem – Phil
Summary – Tanner
Executive Summary

Issue: Major transformer failure Summer
2008 causing a major outage

Project: Reduce outage time

Typically SIUC reacts to failure instead of
preparation
Executive Summary

Expectations
◦
◦
◦
◦

Feeder diagram for fault protection
Emergency transformer
Mechanical restrictions
Outage plan
Outcome
◦ Simulation of feeder diagram
◦ Transformer recommendation
◦ Recommendations to reduce outage time
Executive Summary

Results
◦ Feeder diagram not as accurate as desired
◦ On time
◦ On budget
Estimated cost to implement: ~$92,000
 Time to implement: Estimated 8 months
 Cost of study: $0

Options Investigated
Do nothing
 Purchase 1 transformer
 Purchase 2 transformers
 Mobile transformer
 3 banked single-phase transformers
 Form consortium to share costs

Option Chosen

Purchase two transformers
◦ Covers both 480V and 208V transformers
◦ Covers most indoor transformers on feeder 7

Investigate consortium option
◦ Many other institutions have similar issues
◦ Coverage against failure of two transformers
with same secondary voltage
Subsystems Flowcharts
First Contingency
Outage Response for
SIUC
Mechanical
Considerations

System Protection
Universal
Transformer
Replacement
Implementing recommendations:
◦ Will reduce outage time at least eight hours
◦ Saves money after five uses of each transformers
Cost and Time to Implement

Costs
◦ Two $46,000 transformers
◦ Storage facility

Time
◦ Analyze, confirm, and design replacement :
20 man-hours
◦ Finalize contracts to build: eight man-hours
◦ Prepare storage area: unknown
◦ Develop plan to replace transformers: 58
man-hours
Mechanical Considerations

Engineering C – 2 transformers
◦ No clear pathway to the surface
◦ Tunnels covered with desks, coal samples,
chairs, file cabinets, etc.
◦ Will have to avoid steam piping and ledges
Replacement Location

Limited by breaker handles
◦ Block pathway to open area of electrical
room

Wide open space at backside of electrical
room
◦ Need cabling to avoid access locations
◦ Nails in ceiling limit ability to run cabling
Limiting Factors
Problems at Arena
Ideal Tunnel…
Actual Tunnel…
System Protection

Ensure that replacement transformers
and the electrical system will be properly
protected against fault currents

Chose feeder seven to do a protection
study

Built a model in EasyPower

System data
System Protection

Replaced the present transformers with our
specified replacement transformers
◦ 1000 kVA 12,470 V Δ – 4160 V Δ / 480 V Y
%Z = 4.5
◦ 1000 kVA 12,470 V Δ – 4160 V Δ / 208 V Y
%Z = 4.5

Ran the simulation
Time-Current Characteristic Curve
Universal Transformer
Must be electrically and mechanically
compatible
 Several options considered
 Fourteen of fifteen transformers 208 V or
480 V secondary voltage
 Thirteen of fifteen transformers rated
1000 kVA or less
 Most outdoor transformers are noncritical

Mobile Transformer
Determined to be non-feasible
 Cable length to transformer location
presents problems

◦ Voltage drop
◦ Safety hazards
◦ Security of power system
Summary

Reduce outage periods

Save money for SIUC

Recommend database for all power
equipment at SIUC

Estimated cost to implement: ~$92,000

Time to implement: estimated 8 months
Summary - Acknowledgements
 Steve
Lazorchak
 Damon Adams
 Rob Estes
 Justin Harrell
 Rick Martin
 Joe Wolfe
 Keith
Field
 Mrs. Purcell
 Dr. Hatziadoniu