JWST-PRES-012901
James Webb Space Telescope
Integrated Science Instrument Module
Status
Jamie Dunn
JWST/ISIM Manager
JWST Partner’s Workshop
May 19, 2009
ISIM CDR
Successfully conducted March 9-12 at GSFC
Major findings
Highly optimistic schedule which was not closing at the time of
CDR
Resolved with new LRD of June 2014
SI flight deliveries not impacted by new LRD
Observatory thermal issues
NGAS/GSFC has chosen a set of minimally invasive options
which result in radiator thermal performance margins above
50%
Options to further reduce IEC backloading are still being
explored
Identify responsible person for each critical test
Ongoing, accomplished as part of test planning
A total of 94 RFAs issued
As of today:
52 responses submitted to the originator
Of those, 29 have been closed
2
DRAFT
REV-H
ISIM MASTER SCHEDULE
2005
TASK
II
III
IV
2006
I
II
III
2007
IV
I
II
PDR
Reviews/Deliveries to NGST
10
III
2008
IV
I
II
T-NAR
III
2009
IV
I
CDR
4
3
1
IV
FLT S/C Sim
CDR
12
7
PDR
CDR
7
3
6
I
IES IES
IES
SDL EMTB OTB
12
2
PDR
CDR
8
12
NIRSpec
PDR
SITS
2
9
PER
1 Cry o1
7
SDR
7
10
6
Array
CDR
SITS
11
CDR
STM
10
1
CDR
2
PDR
2
II
III
IV
LRD
FLT
5
6
Del
9
STM
PDR
10
PER
4
PER
6
Delta
PDR DU
11
CDR
FLT
9
3
ETU
Av ail
S/C SIM
10
3
S/C S/C
SIM Sim CDR
11
1
FLT
11
ETU
2
3
8
FLT
10
ETU 10
TFI/Sy stems
CDR
CDR
ICDH
3 5
2014
I
FLT
2
10
3 4
2
Res
11
IV
FLT
10
PER
3
Guider CDR FVTS
12
9
ETU
9
SITS
5
SRR
PER
1
FLT
12
5
PDR
Cry o2
III
8
CDR
NIRCam
2
II
ETU
8
CDR
12
4
7
2013
I
6
KO
6
SITS
ICDH
FLT
IV
FLT
Rec
OBA
SM
MIRI
III
10 12
PDR
PDR
11
2
II
12
3
6
2012
I
FLT
6
SRR
IV
6
FLT H/W
6
III
FLT
CDR
KO
II
3
PDR
CDR
Flight Software
2011
IV
9
KO
Optical Simulator (OSIM)
ISIM Remote Servicing Unit
III
ICDH
ETU #1
Rec
Stru
1
Thermal Control Subsystem
FGS
II
5
Harness Radiator
Microshutter Subsystem
Detector Subsystem
2010
I
ETU S/C Sim
PDR
ISIM Electronics Compartment
III
NAR
Integration &Test
Structure
II
ETU #1
(to I&T)
6
4 surom 2.4 IC10
8
12
FLT #1 FLT #2
(to I&T) (to I&T)
2 5
IC11
8
FLT
11
IC12
1
10
IC13 IC14 IC15 (Final)
5
8 11
As of 05/14/09
I
Status and Recent Progress - ASICs
Second flight run of ASICs is in process
Teledyne is making excellent progress finalizing the production details, and is
working to a schedule that supports deliveries to flight instrument teams
beginning this November
Pathfinder units begin assembly this week
First flight article builds beginning in July
Have determined that the minimum common mode voltage requirement needs to be
increased
Instrument teams notified, design modifications are in process
4
Status and Recent Progress – NIRSpec Detectors
Pathfinder Detector System testing is progressing well
Delivery to ESA scheduled for mid-July
Flight Detector System is awaiting delivery of flight ASICs
Scheduled for mid-November, supporting a Flight DS delivery of
February 2010
Evaluating options for ASIC common mode voltage requirement
change
Plan to implement on the flight FPE prior to flight ASIC delivery
Have two high quality spare SCA candidates in-hand
Selection agreement with ESA pending
8 Mpix HgCdTe Focal Plane Assembly
Focal Plane Assembly
(FPA)
5
Status and Recent Progress - Microshutters
Flight Microshutter System integration is in progress and on
track for September delivery to ESA
Selected flight arrays
MCE boards in testing
Final magnet motor deliveries from CDA imminent
Final shock requirements agreed to with Mission Systems
Plans envelope cryo and launch environments
Qualification testing at Astrium to begin next week
Microshutter
Array
6
Status and Recent Progress – ISIM Harness Radiator
Critical Design Review scheduled for June 15 at GSFC
Had been postponed due to interface loads issues, which have been
resolved
Incorporation of a spherical bearing assembly reduced loads and
simplified integration with the backplane
Most drawings complete and out for quote
Working toward December delivery
7
Status and Recent Progress – Harness
5
12
7
5
5
4
10
28
Ship
Documentation
Bake out
Clean/Rinse
Therm. Cycling
Elec. Testing
Fabrication
WOAs Opened
Drwgs Released
Parts Procured
Design
Specs Rcvd
Harness
NC ICE to ICP-1 Harn Test - Group #1
NC ICE to ICP-1 Harn Test - Group #2
NC ICE to ICP-1 Harn Test - Group #3 - 300 Series
NC ICE to ICP-1 Harn Test - Group #3 - 400 Series
NC ICE to ICP-1 Harn Test - Group #4 - 300 Series
NC ICE to ICP-1 Harn Test - Group #4 - 400 Series
NC ICE-OA ICE-ICP2 Harn FLT (to IEC)
NC ICE-OA ICP2-ICP1 Harn FLT (to II&T)
Quantity
Have shipped over 150 harness assemblies in support of
Instrument ETU and flight builds
EGSE (SITS, etc…)
ISIM integration and test preparations
Held a successful NIRSpec Detector Harness Manufacturing Readiness Review
on May 5, 2009
Tayco has improved the application and control of the potting where the cable
meets the backshell
N/A N/A
N/A
N/A
8
Status and Recent Progress – ICDH and IRSU
ICDH ETU I&T scheduled to complete in June
Support of instrument thread testing and FSW
development will continue
Helping out GLORY…
Failure of their flight spacecraft computer
boards has jeopardized the January 2010
launch date
JWST flight assets will be utilized, and can be
implemented in time to preserve GLORY’s
schedule
ICDH
Resultant 3 month impact to ISIM ICDH can be
absorbed
IRSU Protoflight boards build in process
Box level I&T to begin in September
IRSU
9
Status and Recent Progress – ISIM Software and ITSS
Flight Software
Build IC11 testing to begin next month
NIRSpec MSS FSW
Began development of MSS C4.1 (final build)
NIRSpec DS FSW has transitioned into “maintenance”
mode
ITSS
Focus is now shifting to:
Build and test of the
Certification Lab at GSFC
for ISIM I&T
Build and test of ISIM
Electrical Simulators for
testbeds at Northrop
Grumman
Continuing to support systems
in the field in maintenance mode
Continuing to support
instrument interface testing
10
Status and Recent Progress – ISIM Electronics Compartment
The first cure cycle of the IEC shell is complete. Co-cure
inserts and final fiberglass layer fabrication begins in the
first week of May. Inserts ready for installation
Integration of the prototype baffle test unit completed and
the first unit is being tested.
11
Status and Recent Progress – ISIM Structure Nearly Complete
Flight Structure delivery on schedule for July!
Assy Sequence Left to Right, Top to Bottom
A
B
C
E
F
G
H
J
K
L
M
N (GE2070600)
Status and Recent Progress – ISIM Structure Deck M
13
Status and Recent Progress – ISIM Optics
LOTS of work on test data sets in support of ISIM cryo performance testing
Extensive analysis efforts in support of test budgets, wavefront sensing,
calibrations, stray light, etc…
Cryogenic metrology equipment/plans nearly complete (photogrammetry, laser
radar, MATF, IATF, scale bars, etc…)
Optics Summit scheduled for June 16-19 at the ECO
Agenda/Objectives:
Update on ISIM optical alignment and verification plan, flows, and test error budgets
not previously covered
Follow-up on actions from IOTA in 2008 and ISIM CDR
Cryogenic metrology hardware
14
Status and Recent Progress – OSIM
Ball components are completing assembly and most Goddard
components are in fabrication
Primary mirror scheduled for shipment next week
Ball deliveries on target for end of June
OSIM integration at GSFC will begin in July
Pupil Select Mechanism wheel
Alignment Diagnostics Module
15
Status and Recent Progress – OSIM
Primary Mirror Interferometric testing
Optical Bench Assembly
Fold Mirror 2 after
coating
Fine Phase Plate after coating
16
Status and Recent Progress – MGSE
Lower GESHA
SAMORAI
• Assembled and ready for
proof testing
Upper GESHA
• Assembled w/ spare h/w,
ready for chem film
• Ship Date May, following
ITP to GESHA mating
interface work
17
Status and Recent Progress – MGSE
Received March 24, 2009
Received March 24, 2009
ISIM Support Stand Dolly (ISSD)
ISIM Metrology Integration Stand (IMIS)
-Full assembly to be complete at GSFC
(April 2009)
-Full assembly to be completed at GSFC
(April 2009)
Dolly-to-Stand Kinematic Interface
3
2
1
18
Status and Recent Progress – Integration and Test
Space Environment Simulator modifications are
complete, and helium shroud is undergoing
acceptance testing
Operations team lead by Debbie Ramey is focusing
on procedure development and pending instrument
ETU deliveries starting late summer
Beginning in June…
Internal transition to the GSFC I&T complex
begins
Major MGSE build-up and integration space
secured
8 Mpix HgCdTe Focal Plane Assembly
19
ISIM Year Ahead
In a year…
Flight ISIM Integration and Test begins!
20