EN LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K.
Download ReportTranscript EN LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K.
EN LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K. Foraz Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 1 EN Outline • General frame • Injectors • LHC machine : Main activities and risks • Organization • Conclusion Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 2 EN Draft 10 years plan (27/10/11) 2012 2013 Operation period 1 2014 2016 Operation period 2 (OP2) Long Shutdown 1 (LS1) (OP1) 2015 • • • • Machine : Splices consolidation… ATLAS: - Consolidation and new forward beam pipes ALICE: detector completion CMS:FWD muons upgrade + Consolidation & infrastructure improvements • LHCb: consolidations 2017 OP2 2018 2019 Long Shutdown 2 (LS2) 2020 Operation period 3 (OP3) • Machine: Collimation & prepare for crab cavities & RF cryo system • ATLAS: new pixel detect. - detect. for ultimate luminosity. • ALICE - Inner vertex system upgrade • CMS - New Pixel. New HCAL Photodetectors. Completion of FWD muons upgrade • LHCb - full trigger upgrade, new vertex detector etc. Feb. 8th 2012 2021 K. Foraz - LHC Performance Workshop 2012 LINAC 4 connection ? 3 EN LS1 - Goal Take all measures for a safe and reliable operation of LHC @ 7TeV/beam Full maintenance Consolidation & upgrade LHC machine & experiments Injectors Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 4 EN LS1 - Time window • 20 months from Beam OFF to Beam ON – Actual total duration agreed between experiments and machine • • • • • LHC machine: ALICE: ATLAS: CMS: LHCb: 20 months 12 months (up to 15 months) 15 months (but from April 2013) 20 months 12 months Marzio: “ LHC experiments upgrade & maintenance” Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 5 EN Requests Approval • Meetings being held with stakeholders to understand • Goal of activities Time key drivers Support needed For accelerator complex: database of requests is being filled : LHC and injectors To detect conflicts/overloads & to decide what is compulsory, what we can afford & what we have to postpone to LS2 Priorities set for LHC machine – – – – Feb. 8th 2012 P1: Beam to 6.5-7TeV, nominal performance P2: Reliable operation • Mauro : “EN-CV upgrade & consolidation” P3: CERN approved projects • Francois: “EN-EL upgrade & consolidation” • Erk : “RF upgrade program in LHC injectors P4: no CERN approved projects and LHC machine“ K. Foraz - LHC Performance Workshop 2012 6 EN Outline • General frame • Injectors • LHC machine : Main activities and risks • Organization • Conclusion Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 7 EN 2014 AD $ ELENA HI-ISOLDE CTF Linac 4 Linac 3 Sec. 4 Sec. 3 Sec. 2 Sec.1 Sec. 6 Sec. 5 Sec. 4 Sec. 3 Sec. 2 Sec.1 BA80 TI8 TI2 BA7 BA6 BA5 BA4 BA3 BA2 PS Booster PS General Shutdown works: ABT, Magnets, RP, lifts… Survey Will be detailed during IEFC workshop Survey Survey Decabling campaign RF Upgrade Survey: Tilt & vertical - Quads Irradiated cables Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. Irradiated cables 2013 BA1 SPS Linac 2 Injectors v v Survey: Alignment maintenance Survey: Vertical & Radial measurements & Alignment General Shutdown works: ABT, Magnets, RP, lifts… • “Normal” Xmas shutdown (*2) • Survey: measurements, til, alignment • SPS: • EL: clear unused cables & irradiated cables in SPS • RF upgrades • Power converter consolidation • Other groups works Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 Courtesy D. McFarlane V. Chohan 8 EN 2014 AD $ ELENA HI-ISOLDE CTF Linac 4 Linac 3 Sec. 4 Sec. 3 Sec. 2 Sec.1 Sec. 6 Sec. 5 Sec. 4 Sec. 3 Sec. 2 Sec.1 BA80 TI8 TI2 BA7 BA6 BA5 BA4 BA3 BA2 PS Booster PS General Shutdown works: ABT, Magnets, RP, lifts… Renovation of Vacuum control system Survey Interlck Interlck Interlck Survey Interlck Survey Decabling campaign RF Upgrade Survey: Tilt & vertical - Quads Irradiated cables Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. Irradiated cables 2013 BA1 SPS Linac 2 Injectors v v Survey: Alignment maintenance Survey: Vertical & Radial measurements & Alignment General General Shutdown Shutdown works: works: ABT, ABT, Magnets, Magnets, RP, RP, lifts… lifts… New access system commissioning • PS & PS booster • Renovation of vacuum control system • Cooling & ventilation maintenance and renovation • RF maintenance & upgrade • New access system • Other groups works • Interlock Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 Courtesy D. McFarlane V. Chohan 9 EN Injectors access system Rui: “Access strategy in the accelerator complex and experimental area” Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 Courtesy E. Sanchez 10 EN 2014 AD $ ELENA HI-ISOLDE CTF Linac 4 Linac 3 Sec. 4 Sec. 3 Sec. 2 Sec.1 Sec. 6 Sec. 5 Sec. 4 Sec. 3 Sec. 2 Sec.1 BA80 TI8 TI2 BA7 BA6 BA5 BA4 BA3 BA2 PS Booster PS v Survey: Vertical & Radial measurements & Alignment AD hall preparation for ELENA v Survey: Alignment maintenance CV CTF operational dates TBC Survey Interlck LINAC 4 commissioning Interlck Interlck Survey Decabling campaign RF Upgrade Survey Interlck Set up of Argon & Xenon beam (2) Renovation of Vacuum control system Survey: Tilt & vertical - Quads Set up of Argon & Xenon beam (1) General Shutdown works: ABT, Magnets, RP, lifts… Irradiated cables Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. Irradiated cables 2013 BA1 SPS Linac 2 Injectors General Shutdown works: ABT, Magnets, RP, lifts… New access system commissioning Cold Checkout & Start-up Cold Checkout & Start-up • Early 2014 :Cold check-out and Start up • LINAC3 : set up of Argon and Xenon beam • LINAC4 commissioning • CTF operational – dates TBC • HI-ISOLDE: Cooling & Ventilation works for ELENA Feb. 8th •2012AD & ELENA: AD hallK.preparation Foraz - LHC Performance Workshop 2012 Courtesy D. McFarlane V. Chohan 11 EN Outline • General frame • Injectors • LHC machine : Main activities and risks • Organization • Conclusion Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 12 EN LHC machine – Time key drivers • Time key drivers in LHC machine – Superconducting circuits consolidation – Radiation To Electronics R2E – Maintenance – …. And many other activities (already > 100 entries in the db for LHC machine) Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 13 EN One typical sector Powering and ELQA tests prior to Warm-up (4+4 d) • qualify circuits except mains to 7TeV • fault localization.. • CSCM (1 sector) Mirko: “Powering tests before LHC warm-up: What is new from Chamonix 2011? ” Warm-up: incl. vacuum leak tests at 80K (1wk) to localize leaks Maintenance & consolidation Preparation for & cool-down Powering tests Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 14 EN Splices 2014 2013 P1 Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Feb. 8th 2012 S12 P2 PT Warm-up S23 PT Warm-up P3 S34 P4 PT -> 10K CSCM preparation CSCM S45 PT P5 S56 P6 S67 PT PT Warm-up Warm-up Warm-up P7 S78 P8 S81 PT PT Warm-up Warm-up Warm-up Splices Splices Splices Splices Splices Splices Cool-down Splices Splices Cool-down Powering Tests Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Splices Warm-up Preparation for cool-down K. Foraz - LHC Performance Workshop 2012 Cool-down Jean-Philippe : “LHC consolidation of the superconducting circuits ” 15 EN Other superconducting circuits 2014 2013 P1 Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Feb. 8th 2012 S12 P2 S23 PT P3 S34 PT Warm-up Warm-up PT -> 10K CSCM preparation CSCM P4 S45 PT P5 S56 P6 S67 P7 PT PT Warm-up Warm-up Warm-up S78 P8 S81 PT PT Warm-up Warm-up Warm-up Splices Splices Splices Splices Splices Splices Cool-down Splices Splices Cool-down Powering Tests Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Magnets exchange Consolidation of SAM Y lines DN200 Inner triplets braid Connection Cryostat K. Foraz - LHC Performance Workshop 2012 16 EN Maintenance 2014 PT Warm-up Warm-up P3 S34 P4 PT S45 PT -> 10K CSCM preparation CSCM P5 S56 PT Warm-up Warm-up Warm-up Splices P7 S78 P8 S81 PT PT Warm-up Warm-up Splices Splices Splices Splices Splices Cool-down Powering Tests Cool-down Powering Tests Powering Tests Cool-down Powering Tests Splices Cool-down Cool-down Powering Tests S67 PT Warm-up Splices P6 Cryo Maint. PT S23 Cryo Maint. P2 Cryo Maint. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. S12 Cryo Maint. 2013 P1 Cool-down Cool-down Powering Tests Powering Tests Cool-down Powering Tests Cryogenics : 18 weeks per cryoplant + Maintenance of all the equipment: CV, EL, RF…, mainly in service areas Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 17 EN R2E mitigation measures • Detailed & graphical schedules ready, except P7 in progress Anne-Laure : “R2E strategy and activities during LS1 ” Courtesy M. Barberan Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 18 EN R2E mitigation measures 2014 PT S23 PT P3 S34 P4 S45 PT -> 10K Just in time for CD of s.12 Warm-up Warm-up CSCM preparation Delay by 2 wks CD of S.81CSCM P5 PT S56 P6 S67 PT PT Warm-up Warm-up Warm-up Warm-up Feb. 8th 2012 Delay Cool-down of 56 (1st sector) Splices Delay Powering tests of 56 Splices But 1 month marginw.r.t s45 Splices Cool-down Cool-down Powering Tests Splices Cool-down Powering Tests P8 S81 PT PT Warm-up Warm-up Splices Cool-down Powering Tests Powering Tests Cool-down Powering Tests Splices S78 Splices Cool-down Splices Powering Tests P7 R2E P2 P7 to be finalized S12 R2E Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. R2E 2013 P1 Cool-down Powering Tests Cool-down Powering Tests Powering Tests Splices Cool-down Warm-up Preparation for cool-down R2E K. Foraz - LHC Performance Workshop 2012 19 EN Skeleton schedule – Physics to physics 2014 Feb. 8th 2012 PT Warm-up Warm-up P3 S34 P4 PT S45 PT -> 10K CSCM preparation CSCM P5 S56 PT Warm-up Warm-up Warm-up Splices P7 S78 Splices Splices Splices Cool-down PT Warm-up Warm-up Splices Powering Tests Cool-down Powering Tests Powering Tests Cool-down Powering Tests S81 Splices Cool-down Cool-down Powering Tests P8 PT Splices Cool-down Powering Tests S67 PT Warm-up Splices P6 Cryo Maint. PT S23 Cryo Maint. P2 Cryo Maint. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. S12 Cryo Maint. 2013 P1 Cool-down Powering Tests Cool-down Powering Tests Cold check-out & Beam Commissioning Ezio : What is the maximum reasonable energy Physics 1 week stand-by 2014-2015 K. Foraz - LHC Performance Workshop 2012 20 EN Risks (possible changes in schedule): IC trains From installation experience, first 2 sectors took ~ 20% longer 2014 2013 P1 Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. S12 P2 S23 P3 34 P4 S45 S56 P6 S67 P7 S78 But leak detection and Selectrical testsP5at the end can reserve bad P8 surprises in the last sectors… Warm-up Warm-up -> 10K Warm-up Feb. 8th 2012 PT Warm-up PT Warm-up PT PT PT CSCM preparation CSCM Warm-up Warm-up + 20% Splices PT PT S81 PT Warm-up + 20% Splices Splices Splices Splices Splices Cool-down Splices Splices Cool-down Powering Tests Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Splices Warm-up Preparation for cool-down K. Foraz - LHC Performance Workshop 2012 Cool-down 21 EN Risks (possible changes in schedule): R2E mitigation measures P1 & P5 are tight in schedule : Effect of 6 weeks delay No direct impact on end dates but will delay the powering tests of 3rd and S12 P2 S23 P3 S34 P4 S45 P5 S56 P6 S67 P7 S78 P8 following sectors. 2014 Harwdware Warm-up Warm-up PT -> 10K commissioning workload 7 PT PT Warm-up Warm-up Warm-up Warm-up 6 Feb. 8th 2012 CSCM preparation CSCM PT 5 4 R2E 3 2 Splices Splices 1 0Splices Nov Dec Jan SplicesFeb 6 weeks delay Mar Apr Splices May no delay Jun Splices Cool-down Powering Tests Powering Tests Cool-down Powering Tests PT PT Warm-up Warm-up Splices Splices Cool-down Cool-down Powering Tests Cool-down Powering Tests Powering Tests Cool-down S81 R2E PT P7 to be finalized PT Nb of sectors Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. R2E 2013 P1 Cool-down Powering Tests Cool-down Powering Tests Powering Tests Splices Cool-down Warm-up Preparation for cool-down R2E K. Foraz - LHC Performance Workshop 2012 22 EN Risk (possible changes in schedule): additional activities Additional activities, especially those requiring supports from other S12 P2 S23 P3 S34 P4 S45 P5 S56 P6 S67 P7 S78 P8 groups can disorganize the global schedule, and induce delays. 2014 PT Warm-up Warm-up PT PT -> 10K CSCM preparation CSCM PT PT Warm-up Warm-up Warm-up Feb. 8th 2012 Splices Splices PT Warm-up Warm-up Splices Splices Splices Splices Splices Cool-down Splices Cool-down Cool-down CSCM Powering Tests PT Cryo Maint. CSCM tests in all sectors will cost around 4 weeks Warm-up S81 Cryo Maint. PT Cryo Maint. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec. Jan. Cryo Maint. 2013 P1 Powering Tests CSCM Cool-down CSCM Cool-down CSCM Powering Tests Powering Tests CSCM Cool-down CSCM Cool-down CSCM Powering Tests Powering Tests Cool-down CSCM Powering Tests Powering Tests Cold check-out & Beam Commissioning Physics K. Foraz - LHC Performance Workshop 2012 23 EN Outline • General frame • Injectors • LHC machine : Main activities and risks • Organization • Conclusion Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 24 EN Organization • Schedule & logistics – Lots’of work still to be done in matter of schedule & logistics for all the other activities w.r.t. skeleton Reiner : “QPS upgrade and machine schedule protection during LS1 ” Miguel : “Vacuum upgrade” Laurent: “Cryogenics system: strategy to achieve nominal performance and reliable operation “ • Preparation – – – – ECR have to be written prior to works Modification of the envelope of your equipment ICL DIMR Materials have to be ready in due time…..This has often induced delays !!! • Follow-up – Weekly coordination and scheduling meeting Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 25 EN Conclusions • Analysis of requests well advanced (LHC & experiments, injectors) – w.r.t. priorities & resources & time & interaction between groups – New requests will be scrutinized, especially the support form overloaded groups (VSC, EL, CV) • “Skeleton” schedules for LHC machine & injectors ready • Workload is huge and the schedule is tight • Worksites have to be well prepared. Please do not forget layout, integration & safety Feb. 8th 2012 K. Foraz - LHC Performance Workshop 2012 26