EN LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K.

Download Report

Transcript EN LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K.

EN
LS1 general planning and
strategy for LHC, LHC injectors
LHC Performance Workshop
Chamonix 2012
K. Foraz
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
1
EN
Outline
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
2
EN
Draft 10 years plan (27/10/11)
2012
2013
Operation period 1
2014
2016
Operation period 2 (OP2)
Long Shutdown 1 (LS1)
(OP1)
2015
•
•
•
•
Machine : Splices consolidation…
ATLAS: - Consolidation and new forward beam pipes
ALICE: detector completion
CMS:FWD muons upgrade + Consolidation & infrastructure
improvements
• LHCb: consolidations
2017
OP2
2018
2019
Long Shutdown 2
(LS2)
2020
Operation period 3 (OP3)
• Machine: Collimation & prepare for crab
cavities & RF cryo system
• ATLAS: new pixel detect. - detect. for
ultimate luminosity.
• ALICE - Inner vertex system upgrade
• CMS - New Pixel. New HCAL
Photodetectors. Completion of FWD muons
upgrade
• LHCb - full trigger upgrade, new vertex
detector etc.
Feb. 8th 2012
2021
K. Foraz - LHC Performance Workshop 2012
LINAC 4 connection ?
3
EN
LS1 - Goal
Take all measures for a safe and reliable
operation of LHC @ 7TeV/beam
Full maintenance
Consolidation & upgrade
LHC machine & experiments
Injectors
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
4
EN
LS1 - Time window
• 20 months from Beam OFF to Beam ON
– Actual total duration agreed between experiments and
machine
•
•
•
•
•
LHC machine:
ALICE:
ATLAS:
CMS:
LHCb:
20 months
12 months (up to 15 months)
15 months (but from April 2013)
20 months
12 months
Marzio: “ LHC experiments
upgrade & maintenance”
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
5
EN
Requests Approval
•
Meetings being held with stakeholders to
understand



•
Goal of activities
Time key drivers
Support needed
For accelerator complex: database of requests
is being filled : LHC and injectors
 To detect conflicts/overloads & to decide
what is compulsory, what we can afford &
what we have to postpone to LS2
 Priorities set for LHC machine
–
–
–
–
Feb. 8th 2012
P1: Beam to 6.5-7TeV, nominal performance
P2: Reliable operation
• Mauro : “EN-CV upgrade & consolidation”
P3: CERN approved projects
• Francois: “EN-EL upgrade & consolidation”
• Erk : “RF upgrade program in LHC injectors
P4: no CERN approved projects
and LHC machine“
K. Foraz - LHC Performance Workshop 2012
6
EN
Outline
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
7
EN
2014
AD $ ELENA
HI-ISOLDE
CTF
Linac 4
Linac 3
Sec. 4
Sec. 3
Sec. 2
Sec.1
Sec. 6
Sec. 5
Sec. 4
Sec. 3
Sec. 2
Sec.1
BA80
TI8
TI2
BA7
BA6
BA5
BA4
BA3
BA2
PS Booster
PS
General Shutdown works: ABT, Magnets, RP, lifts…
Survey
Will be detailed
during
IEFC workshop
Survey
Survey
Decabling campaign
RF Upgrade
Survey: Tilt & vertical - Quads
Irradiated
cables
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
Irradiated
cables
2013
BA1
SPS
Linac 2
Injectors
v
v
Survey: Alignment maintenance
Survey: Vertical & Radial measurements
& Alignment
General Shutdown works: ABT, Magnets, RP, lifts…
• “Normal” Xmas shutdown (*2)
• Survey: measurements, til, alignment
• SPS:
• EL: clear unused cables & irradiated cables in SPS
• RF upgrades
• Power converter consolidation
• Other groups works
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
Courtesy D. McFarlane
V. Chohan
8
EN
2014
AD $ ELENA
HI-ISOLDE
CTF
Linac 4
Linac 3
Sec. 4
Sec. 3
Sec. 2
Sec.1
Sec. 6
Sec. 5
Sec. 4
Sec. 3
Sec. 2
Sec.1
BA80
TI8
TI2
BA7
BA6
BA5
BA4
BA3
BA2
PS Booster
PS
General Shutdown works: ABT, Magnets, RP, lifts…
Renovation of Vacuum control
system
Survey
Interlck
Interlck
Interlck
Survey
Interlck
Survey
Decabling campaign
RF Upgrade
Survey: Tilt & vertical - Quads
Irradiated
cables
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
Irradiated
cables
2013
BA1
SPS
Linac 2
Injectors
v
v
Survey: Alignment maintenance
Survey: Vertical & Radial measurements
& Alignment
General
General Shutdown
Shutdown works:
works: ABT,
ABT, Magnets,
Magnets, RP,
RP, lifts…
lifts…
New access system commissioning
• PS & PS booster
• Renovation of vacuum control system
• Cooling & ventilation maintenance and renovation
• RF maintenance & upgrade
• New access system
• Other groups works
• Interlock
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
Courtesy D. McFarlane
V. Chohan
9
EN
Injectors access system
Rui: “Access strategy in the accelerator
complex and experimental area”
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
Courtesy E. Sanchez
10
EN
2014
AD $ ELENA
HI-ISOLDE
CTF
Linac 4
Linac 3
Sec. 4
Sec. 3
Sec. 2
Sec.1
Sec. 6
Sec. 5
Sec. 4
Sec. 3
Sec. 2
Sec.1
BA80
TI8
TI2
BA7
BA6
BA5
BA4
BA3
BA2
PS Booster
PS
v
Survey: Vertical & Radial measurements
& Alignment
AD hall preparation for ELENA
v
Survey: Alignment maintenance
CV
CTF operational dates TBC
Survey
Interlck
LINAC 4 commissioning
Interlck
Interlck
Survey
Decabling campaign
RF Upgrade
Survey
Interlck
Set up of Argon &
Xenon beam (2)
Renovation of Vacuum control
system
Survey: Tilt & vertical - Quads
Set up of Argon
& Xenon beam
(1)
General Shutdown works: ABT, Magnets, RP, lifts…
Irradiated
cables
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
Irradiated
cables
2013
BA1
SPS
Linac 2
Injectors
General Shutdown works: ABT, Magnets, RP, lifts…
New access system commissioning
Cold Checkout & Start-up
Cold Checkout & Start-up
• Early 2014 :Cold check-out and Start up
• LINAC3 : set up of Argon and Xenon beam
• LINAC4 commissioning
• CTF operational – dates TBC
• HI-ISOLDE: Cooling & Ventilation works
for ELENA
Feb. 8th •2012AD & ELENA: AD hallK.preparation
Foraz - LHC Performance
Workshop 2012
Courtesy D. McFarlane
V. Chohan
11
EN
Outline
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
12
EN
LHC machine – Time key drivers
• Time key drivers in LHC machine
– Superconducting circuits consolidation
– Radiation To Electronics R2E
– Maintenance
– …. And many other activities (already > 100 entries in the db for LHC
machine)
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
13
EN
One typical sector
Powering and ELQA tests prior to Warm-up (4+4 d)
• qualify circuits except mains to 7TeV
• fault localization..
• CSCM (1 sector)
Mirko: “Powering tests before
LHC warm-up: What is new
from Chamonix 2011? ”
Warm-up: incl. vacuum leak tests at 80K (1wk) to localize leaks
Maintenance & consolidation
Preparation for &
cool-down
Powering tests
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
14
EN
Splices
2014
2013
P1
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Feb. 8th 2012
S12
P2
PT
Warm-up
S23
PT
Warm-up
P3
S34
P4
PT
-> 10K
CSCM preparation
CSCM
S45
PT
P5
S56
P6
S67
PT
PT
Warm-up
Warm-up
Warm-up
P7
S78
P8
S81
PT
PT
Warm-up
Warm-up
Warm-up
Splices
Splices
Splices
Splices
Splices
Splices
Cool-down
Splices
Splices
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
Cool-down
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering Tests
Splices
Warm-up
Preparation for cool-down
K. Foraz - LHC Performance Workshop 2012
Cool-down
Jean-Philippe : “LHC
consolidation of the
superconducting circuits ”
15
EN
Other superconducting circuits
2014
2013
P1
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Feb. 8th 2012
S12
P2
S23
PT
P3
S34
PT
Warm-up
Warm-up
PT
-> 10K
CSCM preparation
CSCM
P4
S45
PT
P5
S56
P6
S67
P7
PT
PT
Warm-up
Warm-up
Warm-up
S78
P8
S81
PT
PT
Warm-up
Warm-up
Warm-up
Splices
Splices
Splices
Splices
Splices
Splices
Cool-down
Splices
Splices
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
Cool-down
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Magnets exchange
Consolidation of SAM
Y lines
DN200
Inner triplets braid
Connection Cryostat
K. Foraz - LHC Performance Workshop 2012
16
EN
Maintenance
2014
PT
Warm-up
Warm-up
P3
S34
P4
PT
S45
PT
-> 10K
CSCM preparation
CSCM
P5
S56
PT
Warm-up
Warm-up
Warm-up
Splices
P7
S78
P8
S81
PT
PT
Warm-up
Warm-up
Splices
Splices
Splices
Splices
Splices
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
Splices
Cool-down
Cool-down
Powering
Tests
S67
PT
Warm-up
Splices
P6
Cryo Maint.
PT
S23
Cryo Maint.
P2
Cryo Maint.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
S12
Cryo Maint.
2013
P1
Cool-down
Cool-down
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
Cryogenics : 18 weeks per cryoplant
+ Maintenance of all the equipment: CV, EL, RF…, mainly in service areas
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
17
EN
R2E mitigation measures
• Detailed & graphical schedules ready, except P7 in progress
Anne-Laure : “R2E strategy
and activities during LS1 ”
Courtesy M. Barberan
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
18
EN
R2E mitigation measures
2014
PT
S23
PT
P3
S34
P4
S45
PT
-> 10K
Just in time
for CD of s.12
Warm-up
Warm-up
CSCM preparation
Delay by 2 wks CD of S.81CSCM
P5
PT
S56
P6
S67
PT
PT
Warm-up
Warm-up
Warm-up
Warm-up
Feb. 8th 2012
Delay Cool-down of 56 (1st sector)
Splices
Delay Powering tests of 56
Splices
But 1 month
marginw.r.t
s45
Splices
Cool-down
Cool-down
Powering
Tests
Splices
Cool-down
Powering
Tests
P8
S81
PT
PT
Warm-up
Warm-up
Splices
Cool-down
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
Splices
S78
Splices
Cool-down
Splices
Powering
Tests
P7
R2E
P2
P7 to be finalized
S12
R2E
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
R2E
2013
P1
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering Tests
Splices
Cool-down
Warm-up
Preparation for cool-down
R2E
K. Foraz - LHC Performance Workshop 2012
19
EN
Skeleton schedule – Physics to physics
2014
Feb. 8th 2012
PT
Warm-up
Warm-up
P3
S34
P4
PT
S45
PT
-> 10K
CSCM preparation
CSCM
P5
S56
PT
Warm-up
Warm-up
Warm-up
Splices
P7
S78
Splices
Splices
Splices
Cool-down
PT
Warm-up
Warm-up
Splices
Powering
Tests
Cool-down
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
S81
Splices
Cool-down
Cool-down
Powering
Tests
P8
PT
Splices
Cool-down
Powering
Tests
S67
PT
Warm-up
Splices
P6
Cryo Maint.
PT
S23
Cryo Maint.
P2
Cryo Maint.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
S12
Cryo Maint.
2013
P1
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Cold check-out & Beam Commissioning
Ezio : What is the maximum
reasonable energy
Physics
1 week stand-by 2014-2015
K. Foraz - LHC Performance Workshop 2012
20
EN
Risks (possible changes in schedule): IC trains
From installation experience, first 2 sectors took ~ 20% longer
2014
2013
P1
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
S12
P2
S23
P3
34
P4
S45
S56
P6
S67
P7
S78
But leak
detection
and Selectrical
testsP5at the
end
can
reserve
bad P8
surprises in the last sectors…
Warm-up
Warm-up
-> 10K
Warm-up
Feb. 8th 2012
PT
Warm-up
PT
Warm-up
PT
PT
PT
CSCM preparation
CSCM
Warm-up
Warm-up
+
20%
Splices
PT
PT
S81
PT
Warm-up
+
20%
Splices
Splices
Splices
Splices
Splices
Cool-down
Splices
Splices
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
Cool-down
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering Tests
Splices
Warm-up
Preparation for cool-down
K. Foraz - LHC Performance Workshop 2012
Cool-down
21
EN
Risks (possible changes in schedule): R2E mitigation measures
P1 & P5 are tight in schedule : Effect of 6 weeks delay
No direct impact on end dates but will delay the powering tests of 3rd and
S12
P2
S23
P3
S34
P4
S45
P5
S56
P6
S67
P7
S78
P8
following sectors.
2014
Harwdware
Warm-up
Warm-up
PT
-> 10K
commissioning
workload
7
PT
PT
Warm-up
Warm-up
Warm-up
Warm-up
6
Feb. 8th 2012
CSCM preparation
CSCM
PT
5
4
R2E
3
2
Splices
Splices
1
0Splices
Nov
Dec
Jan
SplicesFeb
6 weeks delay
Mar
Apr
Splices
May
no delay
Jun
Splices
Cool-down
Powering
Tests
Powering
Tests
Cool-down
Powering
Tests
PT
PT
Warm-up
Warm-up
Splices
Splices
Cool-down
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering
Tests
Cool-down
S81
R2E
PT
P7 to be finalized
PT
Nb of sectors
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
R2E
2013
P1
Cool-down
Powering
Tests
Cool-down
Powering
Tests
Powering Tests
Splices
Cool-down
Warm-up
Preparation for cool-down
R2E
K. Foraz - LHC Performance Workshop 2012
22
EN
Risk (possible changes in schedule): additional activities
Additional activities, especially those requiring supports from other
S12
P2
S23
P3
S34
P4
S45
P5
S56
P6
S67
P7
S78
P8
groups can disorganize the global schedule, and induce delays.
2014
PT
Warm-up
Warm-up
PT
PT
-> 10K
CSCM preparation
CSCM
PT
PT
Warm-up
Warm-up
Warm-up
Feb. 8th 2012
Splices
Splices
PT
Warm-up
Warm-up
Splices
Splices
Splices
Splices
Splices
Cool-down
Splices
Cool-down
Cool-down
CSCM
Powering
Tests
PT
Cryo Maint.
CSCM tests in all sectors
will cost around 4 weeks
Warm-up
S81
Cryo Maint.
PT
Cryo Maint.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Cryo Maint.
2013
P1
Powering
Tests
CSCM
Cool-down
CSCM
Cool-down
CSCM
Powering
Tests
Powering
Tests
CSCM
Cool-down
CSCM
Cool-down
CSCM
Powering
Tests
Powering
Tests
Cool-down
CSCM
Powering
Tests
Powering
Tests
Cold check-out & Beam Commissioning
Physics
K. Foraz - LHC Performance Workshop 2012
23
EN
Outline
• General frame
• Injectors
• LHC machine : Main activities and risks
• Organization
• Conclusion
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
24
EN
Organization
• Schedule & logistics
– Lots’of work still to be done in matter of schedule &
logistics for all the other activities w.r.t. skeleton
Reiner : “QPS upgrade and machine
schedule
protection during LS1 ”
Miguel : “Vacuum upgrade”
Laurent: “Cryogenics system: strategy
to achieve nominal performance and
reliable operation “
• Preparation
–
–
–
–
ECR have to be written prior to works
Modification of the envelope of your equipment  ICL
DIMR
Materials have to be ready in due time…..This has often induced
delays !!!
• Follow-up
– Weekly coordination and scheduling meeting
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
25
EN
Conclusions
• Analysis of requests well advanced (LHC & experiments, injectors)
– w.r.t. priorities & resources & time & interaction between groups
– New requests will be scrutinized, especially the support form
overloaded groups (VSC, EL, CV)
• “Skeleton” schedules for LHC machine & injectors ready
• Workload is huge and the schedule is tight
• Worksites have to be well prepared.
Please do not forget layout, integration & safety
Feb. 8th 2012
K. Foraz - LHC Performance Workshop 2012
26