CTIO STATUS & PLANS Malcolm G. Smith, Alistair Walker October 23 2003 11/7/2015 NOAO Users Committee.

Download Report

Transcript CTIO STATUS & PLANS Malcolm G. Smith, Alistair Walker October 23 2003 11/7/2015 NOAO Users Committee.

CTIO STATUS & PLANS
Malcolm G. Smith, Alistair Walker
October 23 2003
11/7/2015
NOAO Users Committee
1
Facilities
• Blanco 4m Telescope (90%)
• SMARTS 1-5-m + 1.3-m + 0.9-m (33% 2003, 25%
2004)
• SOAR 4.1-m (30%, first light April 2004)
Not available to NOAO Users
• Schmidt 0.6/0.9m (U. Michigan only - satellite debris program)
• Yale 1.0-m (closed 2003)
• Lowell 0.6-m (closed)
11/7/2015
NOAO Users Committee
2
Blanco 4-m
• Instruments (Mosaic, ISPI, Hydra, RC Spec,
Echelle) block-scheduled, all classical mode
• Mixture of multi-semester Survey (~20%) and short
(~80%) allocations
• La Serena Operations Room - Super Macho &
Essence Programs; Instrument support via VNC
• Mosaic super-popular; ISPI a slow start but 2004A
looks good; continuing steady demand for the
spectrographs
11/7/2015
NOAO Users Committee
3
Site statistics
Data for ONE YEAR:
October 1 2002 - September 30 2003
4m
1.5m
1.3m
0.9m
% observing
76.1
86.0
90.8
84.8
% failure
3.2
2.4
0.6
1.1
% weather total loss
10.9
10.6
8.6
13.6
% engineering
9.8
1.0
0.0
0.5
HOURS TOTAL
3998
3490
2452
3793
HOURS OBSERVING
3042
3002
2226
3216
HOURS NOAO OBS
2728
1640
741
1798
HOURS SMARTS OBS
0
1179
1262
1218
HOURS CHILE OBS
304
182
223
200
11/7/2015
NOAO Users Committee
4
Blanco statistics I - Mosaic & ISPI “nights”
2001B 2002A 2002B 2003A 2003B 2004A
Mosaic Surveys etc. 27
23
38
34
40
21
Mosaic Requested
178
64
188
86
105
48
Mosaic Scheduled
78
49
82
71
105
-
ISPI requested
64
39
28
93
ISPI scheduled
12
18
13
-
(N.B. “scheduled” includes Chile time)
11/7/2015
NOAO Users Committee
5
Blanco Nights scheduled, by instrument
120
100
Echelle
Hydra
ISPI
Mosaic
Osiris
RCSP
IRS
VIS
80
60
40
20
0
2001A
11/7/2015
2001B
2002A
2002B
2003A
NOAO Users Committee
2003B
6
Blanco statistics II - Pre-assigned nights, per
semester (surveys, HST, Chanda, SIRTF)
1B
2A
2B
3A
3B
4A
4B
5A
5B
6B
34
31
44
22
40
21
34
4
30
15
Some large programs 2001B-2006B
• Essence (Suntzeff): 65 nights
• Microlensing (Stuubbs): 65 nights
• Deep lens survey (Tyson): 39 nights
Over 2001A-2003B: 21% of available nights (after engineering and Chile time
removed) are pre-assigned.
11/7/2015
NOAO Users Committee
7
Blanco Instrumentation 2003-2005
• Mosaic Imager, ISPI and Hydra can be a set of permanently
mounted instruments
• RC Spec still a popular workhorse - Goodman spectrograph
on SOAR will be superior
• Echelle also has a steady demand - users will migrate to
Gemini HROS? Or to the Brazilian Echelle (STELES) on
SOAR?
POLICY
• Minimize instrument changes
• Retire uncompetitive instruments
• Plan maintenance and upgrades
11/7/2015
NOAO Users Committee
8
Blanco Issues
• Instrumentation
- Mosaic CCDs - vulnerable to failure
- Fixed instrument complement situation not reached
- Available scientist time not consistent with
instrumentation offered: Blanco 1.5 FTE,
SOAR 0.5 FTE, SMARTS 0.1 FTE
• Telescope
- Dedicated telescope scientist (Abbott)
- Large list of fixes and upgrades needed, e.g. primary
mirror edge supports - will prioritize and work
our way through them
- New TCS - copy SOAR?
11/7/2015
NOAO Users Committee
9
SOAR EXISTS!
Dedication 17 April 2004
11/7/2015
NOAO Users Committee
10
Primary Mirror – Status
(Control system is highly
accurate).
SOAR 11/7/2015
Board Meeting
12 September 2003
NOAO Users Committee
11
Instrument Arrival Schedule
• Delivery of M1 in Chile
• SOAR 1st Light
12/03
• OSIRIS
09/03
• Optical Imager
• Goodman Spectrograph
10/03
– Begin Integration in Chile
– Ready For Installation
04/04
01/04
03/04
• Spartan 2K IR Imager
03/04
• Phoenix - shared with Gemini (2005?)
• SIFS
>10/04
11/7/2015
NOAO Users Committee
Integration with SOAR
system & debug
will be performed before
1st light
Integrated &
commissioned as quickly
as possible following
delivery
12
OSIRIS
(IR Imaging Spectrometer)
11/7/2015
NOAO Users Committee
OSIRIS (cold and ready with new data acquisition system).
13
SOAR Optical Imager
11/7/2015
NOAO Users Committee
14
SOAR Optical Imager
11/7/2015
NOAO Users Committee
15
Goodman Spectrograph
Final Integration and Testing Underway
Grating Rotation
(100% complete and
tested)
Collimator Focus
Stage
(100% complete and
tested)
Grating Translation
(100% complete and
tested)
Mechanical Frame
(100% complete and
tested)
2 Filter Wheels
(100% complete and
tested)
Not shown:
Camera Focus Stage
(90% complete)
11/7/2015
Camera Rotator
(100% complete and
tested)
NOAO Users Committee
16
Spartan
What Goes Inside the
Cryo-optical Box
Preparation for Cold Test
In Clean Room
Cryo-optical Box
Wrapped in
Insulating Blanket
Cryo-optical Box (Inside Out)
After Final Machining
Bathtub of Vacuum Enclosure
11/7/2015
NOAO Users Committee
17
SOAR Integral Field
Spectrograph (SIFS)
• Major Funding Log Jam Has Finally
Cleared - Procurement of Imported Items Now
Getting underway At Last
11/7/2015
NOAO Users Committee
18
SOAR Issues
• Need to commission instruments and telescope
together (not a usual problem!)
• Overly-ambitious instrumentation program
But
• Lots of preparation
• Experienced instrument builders and teams
11/7/2015
NOAO Users Committee
19
New Instruments
4K CCD IMAGER -> 1.0m (2004)
2K IR IMAGER (CPAPIR) -> 1.5m (2004)
NEWFIRM -> BLANCO (2006)
STELES -> SOAR (2006?)
SOAR Adaptive Optics -> SOAR (2005-2006)
New Telescopes
SMARTS to include 1.0-m (2004)
Bochum 1.5-m (2004-2005)
PROMPT 4 x 0.5m (?)
11/7/2015
NOAO Users Committee
20
NEWFIRM
4K IR
Imager
Share
between
Mayall &
Blanco
telescopes
11/7/2015
NOAO Users Committee
21
SOAR AO
•
Ground Layer Corrected Image Quality
– “Realistic”model of SOAR AO Performance
– Tied to Real MASS Data Obtained on CP
• Jan 8-31 2003
• 4234 Profiles, 1 Minute Average
25%
50%
75%
Natural 0.94
1.11
1.33
DIMM
on
Ground
0.5μm
11/7/2015
0.5μm
0.38
0.53
0.71
0.7μm
0.22
0.31
0.49
1μm
0.17
0.22
0.30
NOAO Users Committee
[arcseconds]]
22
SOAR ADAPTIVE OPTICS 2005-2006
GLAO Simulation
AO “on”
11/7/2015
NOAO Users Committee
AO “off”
23
STELES
CoDR scheduled to November 20/21
• Optical Design - finished
– Optimization waiting for concept
approval at CoDR
• Mechanical Design - started
• VPH gratings - prototyping started
– Wasatch Photonics (Richard Rallison)
• Software - control, reduction - started
• Funding search - started
• Preparing documentation for CoDR
11/7/2015
NOAO Users Committee
24
Bochum 1.5m
“hexapod”
telescope
11/7/2015
NOAO Users Committee
25