UNFCCC MONTREAL WORKSHOP Innovative Options for Financing the Development & Transfer of Technologies PRIVATE SECTOR DEVELOPMENT & FINANCING OF (POWER) PROJECTS & TECHNOLOGY TRANSFER Practical.

Download Report

Transcript UNFCCC MONTREAL WORKSHOP Innovative Options for Financing the Development & Transfer of Technologies PRIVATE SECTOR DEVELOPMENT & FINANCING OF (POWER) PROJECTS & TECHNOLOGY TRANSFER Practical.

UNFCCC MONTREAL WORKSHOP

Innovative Options for Financing the Development & Transfer of Technologies

PRIVATE SECTOR DEVELOPMENT & FINANCING OF (POWER) PROJECTS & TECHNOLOGY TRANSFER

Practical Experiences of Project Pre-Development & Financing in Sub-Saharan Africa

HER I N T E R N A T I O N A L

1

CONTENTS

The Project Development Cycle Pre-Development Phase

Options

Tools & Techniques

 

Example Barriers Development Phase & Financing

Barriers

Tools & Techniques

Cost Issues Integration as a Possible Response

Possibilities of using Integration for financing Wind Power in Africa 2

WHAT IS PRE-DEVELOPMENT?

THE PROJECT DEVELOPMENT CYCLE PRE-DEVELOPMENT DEVELOPMENT IMPLEMENT Project Idea Pre Feasibility Project Dvpt.

Feasibility Project Dvpt.

Imple mentation

• Need • Vision • Can it work?

• What conditions?

• Which Partners?

• Estimated Cost?

• Refinancing Sources?

• Initial Structuring • Business Plan / Bankable Feasibility • Technical Design & Specification • Scope of Work • Project Structure • Investment Consortium • Contractors & Suppliers

3

Pre-Development Phase

PRE-DEVELOPMENT ISSUES

Pre-Development Costs need to be financed

ca. 2% of total project costs

Total Development Costs 5 % – 7 % No Guarantee that Project will be implemented Relatively high risk

Return still uncertain Venture Capital / Development Capital nature of investment Long Term Project Development Horizon

2 – 5 Years 4

Pre-Development Phase

PRE-DEVELOPMENT OPTIONS Sponsor‘s Perspective / i.e. Government

Public Sector Route

Government / Donor funding of studies and initial development

 

Public Procurement Processes (Tender) Time Scale / Efficiency

Alternatives? Private Sector Route

Private Sector Developer Hybrid Routes

In practice most (power sector) projects are hybrids 5

Pre-Development Phase

PRE-DEVELOPMENT TOOLS

Usual Suspects

Development Funds (Multilaterals)

Grants & Subsidies

Facilitators / Networks Development Consortium

Spread & Diversify Risk

Public & Private Sector Partners

Avoid Equipment Suppliers / Contractors if possible Initial Analysis: Identification of strategic / special interests in the Project

Who are the Stakeholders & Benefactors?

What can be done to make project more viable / attractive?

Integration

Linkage

Increased value to Benefactors and Stakeholders 6

Pre-Development Phase

HOW DOES IT LOOK IN PRACTICE?

Zambezi Valley Development Scheme

Multi-faceted Integrated Project

Coal Mining & Export

Railway Rehabilitation for Transport

 

Coal Fired Power Generation at Mine Head Coal Terminal Upgrade What were the Goals?

Private Sector Financed Solution

Participation of MZ Public & Private sectors

Lowest possible burden on MZ PSB

Maximum impact on connected sectors & local economy 7

PRE-DEVELOPMENT PHASE

PUBLIC SECTOR Involved Ministries Authorities & Agencies Parastatals

Collation and Transfer of Deliverables Attendance in Task Force Activities / Meetings Participation in Sectorial Activities -- Coal Mining -- Railway / Port Operations -- Energy and Industrial Outlets -- Forestry & Agriculture HEADS OF AGREEMENT incorporating: Objectives Warranties / Guarantees / Exclusivity Channels of Communications / Task Force Development Programme Deliverables Confidentiality / Non-Disclosure FEASIBILITY REPORT AND IMPLEMENTATION PLAN

DEVELOPMENT CONSORTIUM

Developer / Investors Operators Contractor Preparation of Feasibility Report and Implementation Plan Pursue discussions with IFC / Multi-lateral and Private Funding Agencies

Pre-Development Phase

GETTING OVER THE BARRIERS

Development Consortium

Self Funding of Pre-Development Risk (part / majority)

Project Design & Specification

Commitment to provide equity at implementation phase Partnership with Public Sector Partners

Parastatals as members of Development Consortium (and later also the Implementation Consortia) Equipment Supply & Contracting put out to tender

Development Consortium retains operating responsibility, and control

Vital self-interest to ensure value for money

Bears economic risk and takes return Benchmarking 9

Pre-Development Phase

GETTING OVER THE BARRIERS

(2) Independent Integrator / Developer

No vested interests - neither supplier, nor contractor nor investor

Only interest / goal is that the Project gets done

Mediates and co-ordinates

Brokers (forces) the compromises & the issues

Economic Logic & Project Success are sole drivers 10

Pre-Development Phase

THE BARRIERS

Developer(s) / Consortium required comfort that they would take benefit out of the Project assuming positive feasibility

Return on investment in development costs & risks Pressure for an early decision Conflict with established procurement procedures Political Unease & Resistance because of Issues of

Control

Value for Money

Transparency All of which were however addressed by the Structure Project now being implemented in its constituent parts

No integration

Financed by PSB 11

Development / Implementation Phase

MAIN BARRIERS TO FINANCING

Legislative & Regulatory Environment Economic & Commercial Risks Standard Tools are indispensable

Multilaterals

ECAs / Commercial Political Insurance

Hedging Identifying & Generating Secure Refinancing Streams

Off-takers

Integration 12

PARASTATALS

CONCESSIONS & ASSETS

IMPLEMENTATION PHASE

Debt Financing - IFC - ECAs - Commercial banks

SECTOR: MINING

Developer: Coal Miner (Commodities Trader) 

$

SPECIAL PURPOSE COMPANY

SECTOR: TRANSPORTATION

Developer: Railway Operator Rehabilitation: Contractor 

$ IMPLEMENTATION CONSORTIUM

Developer Investors Operators Contractors EQUITY FUNDING

MOZ. COMPANIES SECTOR: POWER

Development: Utility Operator & Parastatal 

$ GENERATED OPERATING INCOME

Interest Principal Repayment of Debt On-going Maintenance Costs Dividends

Global Scheme up to full Repayment of Debts and Return on Capital

Development / Implementation Phase

REVENUES ARE THE KEY

Export of High Quality Coking Coal

Arms length long term off-taking contract with independent commodity trader

Indexed to market prices: Security of Revenues

Offshore Hard Currency Payments

 

PPA / Off-taking Agreements

Industrial Users for base load

Local Utility and International Utility Price was key (<2 cts / KWhr.) Export into SAPP Operator Experience & Know-how

Guarantee of operating targets Equity Component 14

16 14 12 10 8 6 4 2 0

Price Considerations in the Development Process

PRICE ISSUES IN RELATION TO CHOICE OF TECHNOLOGY

(1) Ranges of Energy Production Costs €-cent / KWh

Wind Hydro Gas Coal Nuclear Biomass

15

Price Considerations in the Development Process

PRICE ISSUES IN RELATION TO CHOICE OF TECHNOLOGY

(2) COMPARISON OF CAPITAL COST OF NOMINAL PEAK CAPACITY USD / MW

1.750.000

1.500.000

1.250.000

1.000.000

750.000

500.000

CCGT Thermal Wind Hydro

16

Development / Implementation Phase

INTEGRATION AS A TOOL TO ADDRESS PRICE ISSUES Wind Energy in RIM / MZ / ANG / TNZ

€ cents 5 - 9 / KWhr make Wind Energy an apparently unattractive commercial proposition in Africa Thermal Production Costs much lower (subsidy) Ideas for Integration:

Decentralised Locations (reduction of transmission costs)

Combination with Desalination

Combination with establishment of refrigerated processing & storage facilities for local fishing industries

Cooperation with white goods manufacturers for production of appliances with low voltage ratings 17

Development / Implementation Phase

EFFECTS OF INTEGRATION

Diversification & Increase of Revenue Streams for Repayment of Financing Risk diversification (although increased in absolute terms)

Reduction of pure economic risks

  

Increased Revenue Earnings diversification Foreign Currency Potential Higher Added Value

Increased benefits to a wider community of stakeholders

Nominal high price is made more acceptable

Linkage Increased Complexity 18

Conclusions

CONCLUSIONS

Price of (new) Renewables Technology is the chief barrier

No need to buy a Rolls Royce if a 2 CV also gets you there

External cost argument is only partially accepted in Africa Private Finance, Developers & Tools are available for pre-development phases of New Technology Projects

Combination with existing tools and financing instruments Need for increased flexibility for dealing with parties

 

able & willing to take development risk

Development of appropriate control mechanism Transparent criteria for calculation of return Further third party funding sources / funds Potential of Project Integration to create Linkage and increase Stakeholder benefits

Can be used to raise finance for a VW-Golf 19