Neutrino Factory Target Vessel Concept Update V. Graves Target Studies EVO June 12, 2012 Review – IPAC Paper Concept • Double-wall container for mercury containment • Inner.

Download Report

Transcript Neutrino Factory Target Vessel Concept Update V. Graves Target Studies EVO June 12, 2012 Review – IPAC Paper Concept • Double-wall container for mercury containment • Inner.

Neutrino Factory
Target Vessel
Concept Update
V. Graves
Target Studies EVO
June 12, 2012
Review – IPAC Paper Concept
• Double-wall container for mercury containment
• Inner container is a hollow SS shell filled with He-cooled W beads
– Actually provides triple-wall mercury containment in most areas
• Issue is that it allows Hg to leak into a shielding container that is not part of
the mercury system
• Next step: move outer Hg containment wall inside W, segregate mercury
containment and shielding functions
Tungsten Beads
2
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Inner
Tungsten
Shielding
Helium inlet
Mercury
Vessel Helium
inlet
Prior Concept
Inner
Tungsten
Shielding
Helium outlet
Hg chamber
vent line
Hg jet
inlet
Beam pipe
Mercury
Vessel Helium
outlet
Hg drain
Maintenance
Handle
Hg return
3
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Prior Concept
Hg jet
inlet
Hg chamber
vent line
Beam pipe
Helium inlet
Helium outlet
Hg return
4
Managed by UT-Battelle
for the U.S. Department of Energy
Hg drain
Target Vessel Update 12 June 2012
Updated Concept – Separate Mercury
Containment from Shielding
Downstream
Beam Window
Double wall mercury containment
inside tungsten shielding chambers
5
Managed by UT-Battelle
for the U.S. Department of Energy
Mercury Pool
Target Vessel Update 12 June 2012
Segmented Mercury Interstitial Space
Upstream View Before Hg Pool
Upstream View From Hg Pool
6
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Mercury and Shielding Modules
7
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Double-Wall Supply & Return Piping
• Mercury requires double containment outside the
mercury equipment cell
8
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Double Containment Piping
Mercury Drain Piping
Pin-hole drains
for leaks
Nozzle Inlet
9
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Mercury Module Extraction
10
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Cryostat Modules
• Now have three distinct modules within the first cryostat
• Could combine the shielding modules into one
11
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012
Comments
• Isolating the mercury module from the shielding makes remote
handling simpler
• Still a very complicated geometry and mechanically difficult to
fabricate
• How much heat energy does this new mercury module have to
dissipate?
12
Managed by UT-Battelle
for the U.S. Department of Energy
Target Vessel Update 12 June 2012