U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.

Download Report

Transcript U.S. 31 at CR 400 South Roundabout Information Meeting December 18, 2013 Clifty Creek Elementary Columbus, Indiana.

U.S. 31 at CR 400 South
Roundabout
Information Meeting
December 18, 2013
Clifty Creek Elementary
Columbus, Indiana
Meeting Agenda
 Welcome
 Presentations
 Formal Public Statements or
Comments for the Record
 Adjourn
 Please join our project team with
your specific questions in the
Display Area
Project History
Environmental Document released for
public involvement on October 2009


Presented as a Corridor project consisting of
road rehabilitation with bridge
rehab/replacements on US 31 from US 50 to
CR 50 in Jackson and Bartholomew Counties.
INDOT identified areas to address as
independent projects.
Project History continued
 The intersection at US 31 and CR 400 was
identified an important improvement along
the corridor and was identified as one of
those independent projects.
 Initiated an Additional Information (AI) to
determine if any additional impacts as a
result of the new project design.
 Update and inform the public of the
design change.
Project Purpose & Need
The Purpose of the project is to
provide an intersection with improved
safety and improved traffic flow.
 The Need for the
project is due to
safety and traffic
flow concerns.

What is a Roundabout?


A roundabout is a circular intersection
in which traffic enters or exits only
through right turns and proceeds in a
counter-clockwise direction.
When approaching a roundabout –
Slow Down - incoming traffic always
yields to the circulating traffic.
Proposed Right of Way
Environmental Impacts



Existing land use is agricultural
and residential.
Historic farm east of the intersection
and south of CR 400 is eligible for
National Register of Historic Places.
No right-of-way will be cquired from
acquired from this farm.
Environmental Impacts
Why a Roundabout?


Brochure Federal Highway Administration
Conflict Diagram
Roundabout Safety




Reduced conflict points
All vehicles slow to enter roundabout
Reduced number of injury (76%) and
(35%) reduction in all accidents
More than 90% reduction in fatalities
Other Benefits




Provides efficient traffic flow
Reduces noise and air pollution
Less fuel consumption
Lower operation and maintenance
costs
Proposed

Single lane roundabout





18’ Circulatory travel lane
10’ Concrete truck apron
95’ Green center island
Curb and gutter
15 mph Speed
Proposed

Approaches




12’ travel lanes
17’ entry width
Outside curb and gutter
Concrete splitter islands




Visual queue
Separates entering and exiting vehicles
Aligns driver for correct entry
Deters wrong way movements
CR 400 S

East leg



Replace structure just east of US 31
Extend existing structure east of drive
West leg



Driveway relocation in SW Quadrant
Field drive removal in NW Quadrant
Replace structure just west of US 31
Drainage


Will remain basically as the existing
Changes


Curb and gutter on approaches
Curb turnouts draining
back into open ditches
Maintenance of Traffic (MOT)
 Phase 1





One travel lane in each direction
Construct temporary pavement on east side of US 31
Close east leg of CR 400 S
Access will be maintained to all properties
Construction zone speed limit 35 mph
Maintenance of Traffic (MOT)
 Phase 2





One travel lane in each direction
East leg of CR 400 S will remain closed
Close west leg of CR 400 S
Access will be maintained to all properties
Construction zone speed limit 35 mph
Maintenance of Traffic (MOT)
 Phase 3




One shared travel lane controlled by temporary signals
Both east and west legs of CR 400 S will remain closed
Access will be maintained to all properties
Construction zone speed limit 35 mph
Maintenance of Traffic (MOT)
 Phase 4
 One travel lane in each direction
 Both legs of CR 400 S open
 Weekend closures of intersection to complete the center
island and remaining work
 Construction zone speed limit 35 mph
Maintenance of Traffic (MOT)
 Phase 5
 Open new roundabout
 Finish grading of side ditches
 Construction zone speed limit 35 mph
Project Schedule



Public Information Meeting – December 2013
Design Plan Refinement
Real Estate Acquisition Activities






http://www.fhwa.dot.gov/realestate/realprop/index.h
tml
Appraising
Negotiations/Buying
Utilities Coordination/Relocation
Project Let for contractor bidding
Construction – Tentative Spring/Summer 2015
Public Comments
 Indiana Department of Transportation
Seymour District Office
185 Agrico lane
Seymour, IN 47274
 E-mail: [email protected]
 Phone: 1-877-305-7611
 INDOT respectfully requests comments
postmarked by Friday, January 10, 2014
All comments will be reviewed and evaluated and
given full consideration during the final design
process.