LAGOS BRT SYSTEM BY Dr. Dayo Mobereola Managing Director/CEO LAMATA Presentation at the Asia BRTS conference 2012 Ahmedabad, India September 2012 Presentation contents      -     Background Public Transport Operations in Lagos Existing and Proposed.

Download Report

Transcript LAGOS BRT SYSTEM BY Dr. Dayo Mobereola Managing Director/CEO LAMATA Presentation at the Asia BRTS conference 2012 Ahmedabad, India September 2012 Presentation contents      -     Background Public Transport Operations in Lagos Existing and Proposed.

Slide 1

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 2

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 3

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 4

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 5

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 6

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 7

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 8

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 9

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 10

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 11

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 12

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 13

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 14

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15


Slide 15

LAGOS BRT SYSTEM

BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012

Presentation contents






-






Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations

Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2

BACKGROUND


18 million inhabitants



Smallest state in Nigeria with total
area of 357,700 Hectares.

LAGOS STATE GOVERNMEN T



Most populous city in Africa.



Current estimated growth rate is 6%,

LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY

LAGOS LOCAL GOVERNMEN T AREAS

hence by 2020, population is

LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies

If ako/ Ijaye

Epe

Agege
Ikorodu
Ikeja

expected to be 35 million.

Kosofe

Mushi n

Alim osho

Shomol u

Oshodi/ Isolo

Lagos M ainland

Lagoon(Comm on)

Surulere
Ibeju Lekki

Badagry

Ojo

Ajeromi /
If elodun
Amuwo Odofin

Lagos I sland
Apapa

Et i Osa



Hub of nation’s economic,
commercial and industrial activities.


7

0

7

45% of nation’s skilled manpower
reside in the city.

14 Kilometers



3

Houses the nation’s principal

commercial sea and airports.

PUBLIC TRANSPORT OPERATIONS
IN LAGOS

4

Existing and proposed BRT corridors in
Lagos

5

Design and Procurement Strategies


Route selected based on
the following Criteria:
 Gateway corridor
 High traffic demand
 Less resettlement action
plan

6

Design and Procurement Strategies







-

Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model

-

Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet



Study tours organized with union executives

7

Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration

STATIONS
28 bus shelters

TERMINALS
3 Terminals

DEPOT/GARAGE
1 Depot

OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system

8

Achievement /Performance


Capacity development of the informal sector



Daily ridership well exceeds 140,000



Average trip per bus per day is 5



Average waiting time of 15mins



Average speed of 30km/h



Average journey time of 55mins



Over 211 million ridership since inception



Stability in fare

BRT IN OPERATION

10

Issues and Challenges
Internal
 Ownership
-

Monopolistic in nature

 Management
-

Lack of corporate governance

 Inefficient Service
delivery

External
 Frequent damage
infrastructure
 Violation of BRT lane
by other road users
 Safety and security
issues
 Overriding

11

Lesson Learnt


Adequate preparation and planning are required for any
successful transport initiative



Union resistance to change



There is reward in investing in high capacity buses



Financial institutions are now showing interest in public
transport investment



Involvement of politician is imperative in the re-organisation
of the informal sector



We need to look beyond the union in future BRT expansion to
ensure high standard is maintained

Next steps









Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators

3D image of the proposed Mile 12 –
Ikorodu BRT corridor

14

15