LAGOS BRT SYSTEM BY Dr. Dayo Mobereola Managing Director/CEO LAMATA Presentation at the Asia BRTS conference 2012 Ahmedabad, India September 2012 Presentation contents - Background Public Transport Operations in Lagos Existing and Proposed.
Download ReportTranscript LAGOS BRT SYSTEM BY Dr. Dayo Mobereola Managing Director/CEO LAMATA Presentation at the Asia BRTS conference 2012 Ahmedabad, India September 2012 Presentation contents - Background Public Transport Operations in Lagos Existing and Proposed.
Slide 1
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 2
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 3
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 4
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 5
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 6
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 7
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 8
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 9
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 10
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 11
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 12
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 13
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 14
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 15
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 2
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 3
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 4
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 5
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 6
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 7
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 8
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 9
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 10
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 11
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 12
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 13
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 14
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15
Slide 15
LAGOS BRT SYSTEM
BY
Dr. Dayo Mobereola
Managing Director/CEO
LAMATA
Presentation at the
Asia BRTS conference 2012
Ahmedabad, India
September 2012
Presentation contents
-
Background
Public Transport Operations in Lagos
Existing and Proposed BRT corridors in Lagos
Design/ Procurement Strategies
Implementation
Infrastructure
Operations
Achievement/Performance
Issues and Challenges
Lesson Learnt
Next Steps
2
BACKGROUND
18 million inhabitants
Smallest state in Nigeria with total
area of 357,700 Hectares.
LAGOS STATE GOVERNMEN T
Most populous city in Africa.
Current estimated growth rate is 6%,
LA G OS M E TRO P O LITA N A RE A TRA NS P O RT A UTH OR ITY
LAGOS LOCAL GOVERNMEN T AREAS
hence by 2020, population is
LEGEND
Local G o vernm en t B oun da ries
Lag os wa ter b od ies
If ako/ Ijaye
Epe
Agege
Ikorodu
Ikeja
expected to be 35 million.
Kosofe
Mushi n
Alim osho
Shomol u
Oshodi/ Isolo
Lagos M ainland
Lagoon(Comm on)
Surulere
Ibeju Lekki
Badagry
Ojo
Ajeromi /
If elodun
Amuwo Odofin
Lagos I sland
Apapa
Et i Osa
Hub of nation’s economic,
commercial and industrial activities.
7
0
7
45% of nation’s skilled manpower
reside in the city.
14 Kilometers
3
Houses the nation’s principal
commercial sea and airports.
PUBLIC TRANSPORT OPERATIONS
IN LAGOS
4
Existing and proposed BRT corridors in
Lagos
5
Design and Procurement Strategies
Route selected based on
the following Criteria:
Gateway corridor
High traffic demand
Less resettlement action
plan
6
Design and Procurement Strategies
-
Feasibility study was conducted by an international consultant
(ITP)
Contractor was engaged to design and construct
Bilateral configuration
Construction was done over a period of 18 months
Scheme was implemented as a PPP model
-
Government provided the infrastructure
Union provided the fleet
Formation of NURTW 1st BRT cooperative to operate the fleet
Study tours organized with union executives
7
Implementation: Infrastructure
and Operations
RUNNING WAYS
65% of 22km segregated
lane
Bilateral configuration
STATIONS
28 bus shelters
TERMINALS
3 Terminals
DEPOT/GARAGE
1 Depot
OPERATIONS
Scheme launched in March 2008
220 buses in operations
16hrs of operations
Headway – 10mins max
Over 900 bus pilots& bus officers
57 Inspectors
LASTMA’S role – Traffic management,
Breakdowns& Enforcement
Fares – 2 zone system
8
Achievement /Performance
Capacity development of the informal sector
Daily ridership well exceeds 140,000
Average trip per bus per day is 5
Average waiting time of 15mins
Average speed of 30km/h
Average journey time of 55mins
Over 211 million ridership since inception
Stability in fare
BRT IN OPERATION
10
Issues and Challenges
Internal
Ownership
-
Monopolistic in nature
Management
-
Lack of corporate governance
Inefficient Service
delivery
External
Frequent damage
infrastructure
Violation of BRT lane
by other road users
Safety and security
issues
Overriding
11
Lesson Learnt
Adequate preparation and planning are required for any
successful transport initiative
Union resistance to change
There is reward in investing in high capacity buses
Financial institutions are now showing interest in public
transport investment
Involvement of politician is imperative in the re-organisation
of the informal sector
We need to look beyond the union in future BRT expansion to
ensure high standard is maintained
Next steps
Extension and expansion of BRT network to Ikorodu
Integration with the proposed Rail mass transit (Blue
line at Marina) and other modes of transportation i.e.
water transport
Migration to electronic ticketing
Introduction of feeder routes along the BRT corridors
to enhance capacity utilization
Consolidation of bus operations within the BRT
routes is necessary to further improve efficiency and
performance level of BRT services
A model that involves professional private operators
3D image of the proposed Mile 12 –
Ikorodu BRT corridor
14
15