Energy Performance Contracting –
The Example of Berlin and
EU-wide Experiences
Michael Geissler
CEO Berliner Energieagentur GmbH
26 November 2013
EPC – The Example of Berlin and
EU-wide Experiences
Contents
Berlin Energy Agency (BEA)
Energy Saving Partnership Berlin
© Berliner Energieagentur GmbH
EU-wide Experiences with EPC
Lessons Learned and Outlook
EPC – The Example of Berlin and
EU-wide Experiences
© Berliner Energieagentur GmbH
Berlin Energy Agency (BEA)
EPC – The Example of Berlin and
EU-wide Experiences
Berlin Energy Agency (BEA) – Facts and Figures
Established
in 1992 as Public Private Partnership
Shareholders
Federal State of Berlin
Vattenfall Europe
GASAG
KfW Banking Group
Equity
2.5 million €
Annual total turnover
12.9 million €
Energy Services
Contracting
Consulting
International Know-How Transfer
Based in
Französische Straße 23
10117 Berlin
Phone:
(030) 29 33 30 - 0
e-mail:
[email protected]
Internet: www.berliner-e-agentur.de
Company earnings (EBIT)
905 k €
Know-how
53 members of staff
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
© Berliner Energieagentur GmbH
Energy Saving Partnership Berlin
EPC – The Example of Berlin and
EU-wide Experiences
Energy Saving Partnership Berlin – BEA as Facilitator of EPC
Assignment
Client
(State, hospital, etc.)
Technical-economic requirements,
Negotiations
Consultancy
Berlin Energy Agency
(BEA)
Project Manager
Energy Saving Guarantee Contract
Energy Saving Partner
ESCO
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Energy Saving Partnership Berlin – Main Clients
Schools, Universities
Cultural centres
Trade and
commerce,
housing
associations 5%
Administrative buildings
Hospitals 20%
Sports
facilities
Public
authorities 75%
© Berliner Energieagentur GmbH
Prisons
Hospitals
EPC – The Example of Berlin and
EU-wide Experiences
Energy Saving Partnership Berlin – A Role Model for EPC
Total number of Pools:
26
more than 1,400 buildings
Guaranteed savings in total:
Annual plus to the public household:
€ 11.9 million (26%)
€ 2.7 million
Total CO2 reduction (1996-2012) :
approx. 600,000 t
Total net Investment:
€ 53 million
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Energy Saving Partnership Berlin – General Project Scheme
Public
Authority/
Building owner
remuneration
ESCO
saving guarantee
Facilities/sites
remuneration
natural gas district heat
electricity
oil
Co-ordination
Supply
Technical issues
Utilities
Gas, electricity and/or fuel supply
companies
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – Wenckebach Hospital Berlin
Building:
public-owned hospital with 438 beds
Baseline:
808,359 €/a
Guaranteed savings:
39.6% = 320,000 €/a
Invest:
2.44 m €
CO2 reduction:
1,789 t/a
Duration of contract:
12 years (start in 2011)
Measures:
modernisation of heat distribution, cooling and
ventilation system, installation of CHP unit, webbased energy management system, user trainings
Special feature:
insulation of top storey ceilings
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – Deutsche Oper Berlin (German Opera house)
Building:
building complex with playhouse, studios,
administration etc. (approx. 60,000 sqm GFA)
Baseline 2005/06:
651 K€/a
Guaranteed savings:
35.8% = 233,155 €/a
Invest (hardware):
1.48 m €
CO2 reduction:
1,085 t/a
Contract duration:
12 years
Obligatory measures: refurbishment of VAC installations, optimization of
cooling plant, hot water generation and CBCS
Special features:
contribution of 1 m € to construction costs by DOB,
resulting in increase of budget relief from
14,992 €/a to 126,021 €/a
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – Berliner Bäder-Betriebe (public swimming pools)
Pool 12:
11 buildings/swimming pools
Baseline:
4.9 m €/a (incl. water costs)
Guaranteed savings:
33.5% = 1.6 Mio. €/a
Invest:
7.9 m €
CO2 reduction:
4,938 t/a
Duration of contract:
10 years (start in 2001)
Measures:
water saving technology, optimizing filter flushes,
separating water circulations, modernisation of hot
water generation renovation of air conditioning and
lighting
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – Berliner Immobilienmanagement GmbH (1)
Pool: 18 office buildings (about 300,000 sqm GFA)
Costs [€/ a]
Share of customer
Share of customer
Energy
before EPC
EPC
Energy costs
costs before
2.755 m €
Contracting rate
Contracting rate
1st
Savings
contract
Reduced costs
1. EPC
25 %
nd contract
Savings
Reduced2 costs
2. EPC
21 %
Reduced
energy costs
after EPC
1996
Start of 1 contract
Start of 1. contract
st
• Renewal of heating pumps and heating circuit
• Use of electronic regulation and building
automation systems for heating and
ventilation
2008
End of 1. contract
End of 1st contract
== Sart
of 2. contract
Start of 2nd contract
• Use of highly efficient heating pumps
• Hydraulic compensation of heating system
• Use of CHP
2018
End of 2nd contract
Time
Time
[years]
[years]
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – Berliner Immobilienmanagement GmbH (2)
Re-tender after expiration of first ESP contracts (Pools 1 + 2)
Pool 24:
18 office buildings (approx. 300,000 m² GFA)
Baseline 2007:
2.07 million €/a
Guaranteed savings:
21% = 433,757 €/a
Invest:
approx. 2.4 million €
CO2 reduction:
2,208 t/a
Duration:
10 years
Measures (selected):
boiler replacement, CHP-unit, optimizing of
ventilation systems, renewal of CBCS special
feature: obligation of maintenance of all old
systems
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Energy Saving Partnership Berlin – Proven Project Schedule
Project preparation
and development
Involvement of decision-makers: information and training
workshops for public authorities concerned
Research of building data (energy cost baseline, user
requirements) and framework conditions (e.g. ESCO market)
Pre-selection of buildings → on-site visits and energy audits
Adaptation of EPC model contract to national legislation
Competitive Tendering
(Pre-tender) ESCO workshop for potential bidders on project
(tender documents, model contract, assessment criteria)
Call for tender with pre-selected ESCOs
Evaluation of offers (cost-benefit analysis and evaluation of
technical concept), pre-selection of best offers
2 rounds of negotiations and determination of best offer
Project
implementation
→ Technical and procedural advice throughout the process
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Energy Saving Partnership Berlin – Experiences and Results
guaranteed energy savings achieved in most contracts, high savings up to
35 % feasible
26 contracts operated by 15 different ESCOs, around 100 subcontractors
(regional SMEs) involved in implementation and maintenance
good quality of saving measures because of expertise of ESCOs,
rising experience and improvement of cost-effectiveness
additional improvement of maintenance situation by central coordination
through ESCO
no legal proceedings or need to use bank guarantees so far
re-tendering after end of contract leads to new investments and additional
savings
→ Success thanks to reliable legal framework, standardized procedures
and contracts together with professional process management
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Additional Challenges for EPC
Experiences with EPC projects have shown the need for a focus on
integration of building refurbishment measures
involving the building envelope
energy management systems
as low-cost investment measure
use of Renewable Energy Sources
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Additional Types of EPC
EPC plus
Integration of (comprehensive) building refurbishment
measures
Shared financing instruments
First EPC with (small) share of construction measures
EPC light
Operation and energy management of buildings with saving
guarantee
Green EPC
Focus on renewable energy technologies
Specific tender objectives and link to subsidy programs
Primary energy consumption as guaranteed element
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice EPC light – Building pool in Berlin district Pankow
Buildings:
12 schools, 1 art centre,
1 youth facility,
1 office building
Baseline 2009:
€ 883,000 €/a
Guaranteed savings:
10.2% = € 90,037/a
Share/payment to ESCO: 5.00% = € 44,118/a
„Tesla“ secondary school
CO2 reduction:
3,973 t/a
Contract duration:
2 years
Service of the ESCO:
active optimization of heating and ventilation by
building control systems; analysis of
consumption, monitoring of meters; control of
the invoices of supply companies; energy
reporting every 6 months, weak-point analysis
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
© Berliner Energieagentur GmbH
EU-wide Experiences with EPC
EPC – The Example of Berlin and
EU-wide Experiences
EU-wide Capacity Building in Energy Services
Clearcontract – Clearinghouse for Energy Contracting in CEE
• Project duration: 2003-2004
• Model contracts and tender documents (LV, LT, PL, CZ, SLO, SK, BG, H)
• Results: > 10 contracts signed
• Project duration: 2005-2007
• Model contracts and tender documents (A, D, F, FIN, GR, I, N, S)
• Results: 17 new EPC projects kick-started
Clearcontract –
European Energy Service Initiative (EESI)
• Project duration: 2009-2012
• Improving EPC and energy efficiency standards (B, SE, NO, CZ, SK, SI, RO, A, F)
• Results: assistance of 24 EPC pilot projects (incl. 6 advanced EPC), 57 trainings/workshops
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – clearcontract
Municipality of Kranj, Slovenia
Pool:
14 buildings
(office, schools, sport centres)
Baseline:
€ 350,000/a
Guaranteed savings:
15%
Invest:
€ 340,000
CO2 reduction:
60 t/a
Contract duration:
15 years (from 2001)
Measures:
Replacement of boilers and thermostats, installation
of new control centers, adjustment of heating
system, renovation of heat distribution systems,
fitting of thermostats to radiators
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – EUROCONTRACT
Municipality of Nyköping, Sweden
Pool:
130 buildings,
all public remises
Baseline:
about € 4.7 m/a
Guaranteed savings:
17% = € 800,000/a
25% = € 1.2 m/a
Achieved savings:
Invest:
€ 5.5 m
Contract duration:
6.5 years (from 2003)
Measures:
Renovation of heating systems, optimization and
retrofit of HVAC system, building control,
operation and maintenance system, targeted
training for the operational staff
Source: Schneider Electric
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – EESI (EPC plus)
Characteristics:
9-storey buildings with single
staircase (36 apartments), built in 1980
Guaranteed savings:
56.9% = 245.9 MWh/a
CO2 reduction:
64.9 t/a
Measures: comprehensive renovation (general insulation of
building, replacement of windows, renovation of
heating and hot water system, reconstruction of
roof, energy monitoring system)
Renovation of 7 buildings by the end of 2012
with consortium of financial partners and
EU structural funding (23 by the end of 2014)
Source: Ekodoma
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Best Practice – EESI (Green EPC)
Pool:
14 buildings,
high schools
Baseline:
about € 2.4 m/a
Guaranteed savings:
35% = € 606,000/a
Invest:
€ 36 m
CO2 reduction:
2,300 t/a
Contract duration:
20 years (PPP contract, start 2009)
Measures:
6 wood boilers, 1 heat pump, other new boilers,
district heating connection, insulation of
windows, photovoltaic plants (5,000 m²)
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Lessons Learned – Criteria and Conditions of Success
Driving force:
Political decision makers and public authorities who take on responsibility
© Berliner Energieagentur GmbH
Reliable legal framework:
Clear information that EPC is possible
Favourable public procurement rules, tender procedure and accounting
treatment
Standardized procedures and contracts (while adaptable):
Time and cost-effectiveness for implementation → reliability
Competition and transparency
Promotion and capacity building
Information and assistance through independent EPC market facilitators
EPC – The Example of Berlin and
EU-wide Experiences
Market Development for Energy Services – Principality of Monaco
Objectives
Support the Principality of Monaco in introducing
a suitable EPC model
Call for tenders for a pilot project with contract award
Role of BEA: Consultant
Develop and adapt the EPC model to Monaco
Select public buildings
Train administration officials
Prepare tendering documents
Support the call for tenders and the award of contract for a pilot project
→ establish a framework for EPC projects in Monaco
Result:
EPC contract (12 years) for 5 public buildings
Guarantee on 27% annual energy cost savings (35% in CO2 emissions)
total project cost: € 2+ million
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
Outlook
European Energy Service Initiative towards
the EU 2020 energy saving targets (EESI 2020)
Objective: Europe-wide dissemination of EPC as contribution to EU 2020 targets
Target group: demand side = public institutions (as potential EPC clients) and
project developers in 9 European cities/metropolitan regions –
with EU project „Transparense“ focusing in parallel on supply side (ESCOs)
Consortium: BEA as coordinator; partners from Antwerp, Barcelona, Dublin,
Graz, Oslo, Prague, Sofia, Zagreb
Contents: best-practice database, marketing tools for EPC project developers,
implementation of at least 20 EPC projects, European Energy Service Awards
Duration: 36 months (4/2013 – 4/2016)
© Berliner Energieagentur GmbH
EPC – The Example of Berlin and
EU-wide Experiences
For more information please visit:
© Berliner Energieagentur GmbH
www.berliner-e-agentur.de