TT1825 Mix design and field evaluation of foamed bitumen stabilised pavements December 2014 www.arrb.com.au Advancing safety and efficiency in transport through knowledge research | consulting.

Download Report

Transcript TT1825 Mix design and field evaluation of foamed bitumen stabilised pavements December 2014 www.arrb.com.au Advancing safety and efficiency in transport through knowledge research | consulting.

TT1825 Mix design and field evaluation of foamed
bitumen stabilised pavements
December 2014
www.arrb.com.au
Advancing safety and efficiency in transport through knowledge
research | consulting | technology
Need for cost-effective pavement
rehabilitation treatments
2
Increasing use of foamed bitumen to stabilise
unbound granular bases of rural highways
Commonly use
about 3% bitumen
and 1.5% quicklime
3
National procedures for design of FBS
treatments
• mix design
• distress modes
• improved Austroads
thickness design procedures
• project commenced in July 2012
• two progress reports published
• completion June 2016
4
Collaboration is maximising research
outcomes
• research being guided by a Working Group comprising
road agencies and industry
• extensive collaborative of road agencies, industry and
ARRB
• laboratory testing by two experienced labs, Downer and
TMR
• road agencies and industries are contributing through the
construction of under-designed pavts
5
Foamed bitumen (FB) mix design
• Existing mix design process in need of improvement
6
Requirements for untreated material
• requirements for grading and plasticity of the untreated
material, generally accepted
• not the focus of research
7
Amount of bitumen and lime determined from
indirect tensile modulus testing
8
Department of Transport and Main Roads
(TMR) Queensland modulus requirements
• Austroads building on TMR experience over the last 15
years
• TMR lab mixes are compacted into 150 mm diameter
moulds and 10 kg Marshall hammer
9
TMR mix requirements
• initial modulus 3 hours after lab compaction used as a
indicator of early-life rut resistance
• also undertake wheel tracking
10
TMR mix requirements
• bitumen and lime content adjusted to satisfy requirements
for cured dry and wet modulus
11
Issues being addressed in the research project
Need to harmonise test methods throughout Australia
• various compaction methods in use (e.g. gyratory, standard
Marshall, large Marshall)
• recently agreed that the interim Austroads method would
be large Marshall based on TMR experience
• various mixing and compacting moisture contents being
used
– 70% standard Proctor OMC untreated material
– 85% modified Proctor OMC untreated material
• some labs using quicklime other hydrated lime
12
Effect of mixing moisture
13
Research will lead to Austroads test method
and mix design procedure
14
Issues being addressed in the research project
The most challenging issue is validation of usefulness of lab
moduli in materials characterisation/mix design.
Need to link lab moduli to field performance
•usefulness of initial moduli in evaluating early-life rut
resistance
•usefulness in cured dry and wet moduli in predicting long
term field performance
15
Purpose
The purpose of this project is:
•to improve and harmonise national mix design procedures
for bituminous stabilised materials
•to identify distress modes of bituminous stabilised
pavements from the trial sites.
•to improve the Austroads thickness procedures.
16
Field performance
• to address the project objectives data on the field
performance of FBS pavement is required
• to obtain performance data during the research project (4
years), a number of under-designed pavements have been
constructed and are being monitored
• to date we have five trials
–
–
–
–
–
Kwinana Freeway Perth (2010)
Port Wakefield Road South Australia (2011)
Kewdale Road, Welshpool Perth (2011)
Calder Freeway, Woodend Victoria (early 2013)
Newell Highway Bellata, NSW (late 2013)
17
Summary of trials
Site
Surface
FBS
thickness
(mm)
Nominal
bitumen
content
(%)
Nominal
lime content
(%)
Kwinana Freeway
OGA on
DGA
150 mm
3.5%
0.8%
hydrated lime
Port Wakefield
road
seal
150 mm and
200 mm
3%
1%
hydrated lime
Kewdale road
DGA
100 mm and
150 mm
3%
0.8%
quicklime
Calder Freeway
seal
150 mm
3.5%
1.5%
quicklime
Newell Highway
seal
175 mm
3.5%
1.5%
quicklime
18
Kwinana Freeway after FBS placement before
asphalt and GRS placed, 2010
19
Port Wakefield Road 2011
20
Calder Freeway Victoria under construction
March 2013
21
Newell Highway 2013
22
Sites tested during construction and
monitored for performance
23
Proposed trial on Western Highway Victoria
Heavily trafficked road about 1-2 million ESA per year
200 mm depth FBS, anticipate fatigue after 2-3 years
Two binder contents 2.7% and 3.5%
24
25
FINDINGS TO DATE
26
Ravelling of Calder Freeway when pavement
was opened to traffic the day of construction
• ravelling next day
• may have been
affected by adding
additional material
late in construction to
adjust level to match
adjacent lane
27
Cracking has been observed
• at commencement of trial doubts whether fatigue cracking
was a distress mode for FBS
• to date observed cracking at 2 of the 3 trial sites with seal
surfaces
Port Wakefield Road, 18 months
Calder Freeway, 18 months
28
Only one instance of rutting, when an old
asphalt patch was inadvertently stabilised
29
Foamed bitumen and lime stabilisation
produces high modulus in situ
With high temp in
summer construction
enabled rapid water
loss, FBS cores can
be taken 7 days after
construction
30
Modulus varies with markedly depth/density
• in situ modulus can decrease significantly with depth due to
lower densities
31
Back-calculated moduli being monitored to
predict time to fatigue damage
32
Issues being addressed to improve thickness
design
FBS design modulus
• currently values of 2000 – 3000 MPa are commonly used
• need improve process to determine the flexural design
modulus from the lab IDT moduli
33
Data being obtained to improve determination of
design modulus
• relationship between moduli of lab specimens and moduli
of early-life field cores
• relationship to correct the lab moduli to the field densities
• relationship to adjust IDT modulus to a flexural modulus
34
Issues being addressed to improve thickness
design
• currently fatigue relationship used is that for asphalt with a
reduced volume of binder
• given material contains 1-2% lime and the bitumen
distribution is different from asphalt this relationships needs
to be validated
35
Summary
• research is being undertaken to improve Austroads
procedures for foamed bitumen stabilisaton:
– mix design
– thickness
• strong collaboration and involvement of road agencies and
industry will maximise research outcomes
• progress report published in 2014
• project is due for completion in June 2016
36