Status of ITER 2nd RCM-FENDL-3 23rd March 2010 Michael Loughlin Office of Central Integration and Engineering ITER 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 1
Download ReportTranscript Status of ITER 2nd RCM-FENDL-3 23rd March 2010 Michael Loughlin Office of Central Integration and Engineering ITER 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 1
Status of ITER 2nd RCM-FENDL-3 23rd March 2010 Michael Loughlin Office of Central Integration and Engineering ITER 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 1 ITER is the Next Step Toward a Solution based on Tokamaks 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 2 Four New Superconducting Tokamaks will Address Steady-State Advanced Tokamak Issues in Non-Burning Plasmas SST-1: R =1.1m, 0.22MA, 2008 EAST: R = 1.7m, 2MA, 2006 KSTAR: R = 1.8m, 2MA, 2008 JT-60SA: R = 3m, 5.5 MA, 2014 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 3 ITER – Key Facts • Mega-Science Project among 7 Members: China, EU, India, Japan, Korea, Russia & US • Designed to produce 500 MW of fusion power for an extended period of time with a Q of 10 • 10 years construction, 20 years operation • Cost: ~5.4 billion Euros approved for construction, and ~5.5 billion for operation and decommissioning • EU 5/11, other six parties 1/11 each. Overall reserve of 10% of total. RF CN European Union KO JP 2nd RCM-FENDL-3, 23 March 2010, Vienna IN US Page 4 Procurement Sharing - A unique feature of ITER is that almost all of the machine will be constructed through in kind procurement from the Members with essentially every member involved in every component. 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 5 Overview of the Major Development of the ITER Project May 2006 ITER Management Structure decided at IPC-8 Meeting in Goa, India 21 November 2006 The ITER Agreements signed in Paris Dec. 2006-Dec. 2007 ITER Design Review 24 October 2007 ITER Organization formally established 7 November 2007 Headquarters Agreement signed between France and the IO 27-28 November 2007 The 1st meeting of the ITER Council (DG, PDDG and DDGs were appointed, etc.) 28 November 2007 First PA with Japan signed on TF Conductor 18 December 2007 First PA with EU signed on TF Conductor End January, 2008 Submission of DAC files including RPrS to Nuclear Safety Authority 12 February 2008 First PA with Russia signed on TF Conductor April 2008 Construction Permit for nuclear buildings was awarded 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 6 17-18 June 2008 The 2nd Meeting of the ITER Council in Aomori, Japan (Project Specification was approved, Reference Schedule was agreed for planning purposes and Briscoe Panel was set up, etc.) October 2008 All DAs were established 19-20 November 2008 The 3rd Meeting of the ITER Council in Cadarache (3 pilot IPTs were agreed, etc.) November 2008 Moving to the HQ Building on-site March 2009 ITER Site Platform completed 17-18 June 2009 The 4th Meeting of the ITER Council in Mito, Japan (Updated Schedule was endorsed as a working basis for further development of ITER Baseline, etc) October 2009 Briscoe Panel Review on the new cost estimates November 2009 5th ITER council could not accept 2018 First Plasma Schedule March 2010 MAC recommends 2019 FP schedule to be used for preparation of baseline and approval in June 2010 by Council 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 7 ITER Organization Structure Tim Watson 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 8 Staffing Status • By 31 December 2009, the ITER Organization had a total of 430 staff members, comprising 291 professional and 139 technical support staff members. In addition, as of end of 2009 there were around 330 external contractors. Professional staff Support staff Total CN 16 1 17 EU 175 106 281 IN 14 14 28 JA 22 6 28 KO 20 4 24 RU 21 2 23 US 23 6 29 Total 291 139 430 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 9 ITER - a multicultural organization 25 nationalities Grèce 0.3% Inde Irlande 5.9% 0.5% Italie 6.7% France Japon 6.7% 5.1% 29.6% Espagne Corée Pays-Bas Finlande 1.8% 0.8% Royaume-Uni 3.3% 10.8% Danemark Russie 0% 5.9% S uède Chine S uisse 3.9% 0.5% 0.5% Canada Ukraine 0.3% Bulgarie 0.3% Belgique 2.3% Autriche Australie 0.5% 0.3% Allemagne US A 6.7% 6.9% 2nd RCM-FENDL-3, 23 March 2010, Vienna 0.3% Page 10 • The ITER Organization and the ITER Domestic Agencies 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 11 Integration between IO and DAs - Basic Roles and Responsibilities - ITER Organization – Planning / Design* – Integration / QA / Safety / Licensing / Schedule – Installation – Testing + Commissioning – Operation Seven Members (Domestic Agencies, DA) – – – – – Detailing / Designing* Procuring / Manufacturing Delivering Supporting installation Conformance * Depending on type of specification - Functional: Functional requirements by IO and design by DAs - Detail design: Conceptual design by IO and detailed design by DAs - Build-to-print: Detailed design by IO and fabrication/shop design by DAs 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 12 Main Buildings on the ITER Site A facility licensed under the French Nuclear Regulatory Authority (ASN) Tokamak PF Coils winding Cryoplant Tritium Magnet power convertor Cooling towers Hot cell • Will cover an area of about 60 ha • Large buildings up to 250m long • Large number of systems Control 2nd RCM-FENDL-3, 23 March 2010, Vienna Main Office Page 13 Status of ITER’s technical progress (highlights) Fusion gain Q = 10, Fusion Power: ~500MW, Ohmic burn 300 to 500 sec Goal Q=5 for 3000 sec Central Solenoid (6) Cryostat (Nb3Sn) (29 m high x 28 m dia.) Toroidal Field Coils (18) (Nb3Sn) Poloidal Field Coils (6) (NbTi) Thermal Shield (4 sub-assemblies) Vacuum Vessel (9 sectors) In-Vessel Coils (2-VS & 27-ELM) Correction Coils (18) (NbTi) Feeders (31) (NbTi) Blanket (440 modules) Divertor (54 cassettes) Machine mass: 23350 t (cryostat + VV + magnets) - shielding, divertor and manifolds: 7945 t + 1060 port plugs 2nd RCM-FENDL-3, March 2010, Vienna - magnet 23 systems: 10150 t; cryostat: 820 t Page 14 Magnet Energy Comparison Superconducting Magnet Energy: Charles de Gaulle Energy: ~38000 t at ~150 km/hr ~51 GJ 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 15 TF Coil – Mass Comparison Mass of (1) TF Coil: ~360 t 16 m Tall x 9 m Wide Boeing 747-300 (Maximum Takeoff Weight) ~377 t 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 16 TF and PF Jacketing in: CN JA RF US 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 17 ITER Procurement - a Worldwide Collaboration Example: TF Coils 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 18 Overview of Schedule for 2019 First Plasma First Plasma ITER Construction 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 TF Coils (EU) Case Winding Mockups Complete TF10 TF15 CS Coil CS Final Design Approved CS3L CS3U CS Ready for Machine Assembly Vacuum Vessel (EU) VV Fabrication Contract Award VV 05 VV09 VV07 Buildings & Site Construction Contract Award Tokamak Bldg 11 RFE Tokamak Assembly Start Machine Assembly Tokamak Basic Machine Assembly Start Install CS Start Cryostat Closure Ex Vessel Assembly In Vessel Assembly Assembly Phase 2 Assembly Phase 3 ITER Operations Pump Down & Integrated Commissioning Plasma Operations 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 19 34 signed Procurement Arrangements as of 16 March 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 REFERENCE Signature date 1.1.P6A.JA.01 TF Conductors 28 November 2007 1.1.P6A.EU.01 TF Conductors 18 December 2007 1.1.P6A.RF.01 TF Conductors 12 February 2008 1.1.P6A.KO.01 TF Conductors 07 May 2008 1.1.P6A.CN.01 TF Conductors 16 June 2008 1.1.P1A.EU.01 TF Magnet Windings 20 June 2008 1.1.P6C.CN.01 PF Conductors 10 October 2008 1.1.P1B.JA.01 TF Magnet Windings 19 November 2008 1.1.P2B.JA.01 TF Magnet Structures 19 November 2008 6.2.P2.EU.01 PF Coil Winding Facility 19 November 2008 1.5.P1A.KO.01 Main Vessel 19 November 2008 1.5.P2A.KO.01 Equatorial and Lower Ports 19 November 2008 4 May 2009 6.2.P2.EU.02 Architect Engineering Services 6.2.P2.EU.03 Tokamak Pit Excavation and 4 May 2009 Drainage 6.2.P2.EU.04 Seismic Isolation Pads 4 May 2009 5.3.P7A.IN.01 Diagnostic neutral Beam Power 19 April 2009 Supply 1.1.P6C.EU.01 PF Conductors 4 May 2009 2nd RCM-FENDL-3, 23 March 2010, Vienna 1.7.P2C.RF.01 Divertor Dome 9 June 2009 Page 20 REFERENCE Signature date 19 1.5.P2B.RF.01 Upper Ports 9 June 2009 20 1.1.P6A.US.01 TF Conductors 18 June 2009 21 22 23 2.6.P1A-1B.US.01 Tokamak Cooling Water System 1.7.P2A. JA.01 Divertor Outer Vertical Target 1.1.P3A-B.EU.01 PF Magnets 2,3,4,5,6 (EU) 5.3.P6.EU.01 Power Supply for Heating Neutral Beam ( Low Voltage) 2.2.P2A.KO.01 Machine Assembly Tooling 1.5.P1B.IN.01.0 VV In-Wall Shielding Block Assemblies 1.1.P6C.RF.01 PF Conductors 4.1.P1A-P8B.EU.01 SSEPN and PPEN Detailed System Engineering Design 1.5.P1A.EU.01.0 VV Main Vessel 7 sectors 1.1.P6B.JA.01 Central Solenoid Conductor 5.1.P3.IN.01.0 IC H&CD RF Power Sources 1.7. P2D.RF.01 PFC HHF Tests 1.7.P2B.EU.01 Inner Vertical Targets 1.1.P4A-B.US.01 CS Magnet 18 June 2009 17 June 2009 19 June 2009 24 25 26 27 28 29 30 31 32 33 34 kIUA 13 July 2009 3 August 2009 24 September 09 2 October 09 26 October 09 19 November 09 8 December 09 4 February 2010 23 February 2010 12 March 2010 12 March 2010 1243.37844 kIUA Total Signed Value 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 21 (about 41% of the total in-kind PA value) ( EUR 1,900 million) Procurement Arrangements (PAs) • As of 18 March 2010, there are a total of 34 signed PAs, amounting to 1243.37844 kIUA (approximately EUR 1,900 million), about 41% of the total in-kind PA value; • 19 PAs are scheduled to be signed by August 2010 for a total of 776.453 kIUA (an estimated EUR 1,186 million). 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 22 PAs to be signed by August 2010 according to the IPS PA REFERENCE 2019 IPS DATE PROJECTION DATE 1 1.7.P2B.EU.01 Inner Vertical Targets 5-Jan-10 12-Mar-10 2 5.3.P7B.IN.01 Diagnostic Neutral Beam Line 14-Jan-10 22-Mar-10 3 5.1.P2.US.01 IC Transmission Lines 22-Jan-10 March 2010 4 6.2.P2.EU.05 Building Construction 29-Jan-10 April 2010 5 1.1.P4A-B.US.01 CS Magnet 6 5.3.P6.JA.01 NB H&CD Power Supply for Heating Neutral Beam 7 1.1.P2C.CN.01 Magnet Supports 8 5.1.P4.IN.01 IC H&CD Radio Frequency Power Supply 9 1.1.P3C.CN.01 Correction Coils 19-Feb10 22-Feb10 26-Feb10 31-Mar10 31-Mar10 2nd RCM-FENDL-3, 23 March 2010, Vienna 12-Mar-10 March 2010 March 2010 March 2010 March 2010 Page 23 PAs to be signed by August 2010 according to the IPS PA REFERENCE 2019 IPS DATE PROJECTION DATE 10 2.7.P1.KO.01 Thermal Shield 12-Mar-10 April 2010 11 1.1.P6C.CN.02 Conductors for Correction Coils and Feeders 31-Mar-10 March 2010 12 1.1.P2A.EU.01 Pre Compression Rings 31-Mar-10 April 2010 13 1.1.P3A.RF.01 PF Magnet 1 31-Mar-10 April 2010 14 5.2.P2.US.01 EC Main Transmission 13-Apr-10 April 2010 15 2.6.P2A.IN.01 Component Cooling Water System (CCWS) Chilled Water System (CHWS) and Heat Rejection System (HRS) 16-Apr-10 22-Mar-10 16 1.1.P5A.CN.01 Magnet Feeders 16-Apr-10 September 2010 17 3.4.P2.IN.01 Lower Pipe Chase Cryolines 23-Apr-10 April 2010 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 24 PAs to be signed by August 2010 according to the IPS PA REFERENCE 2019 IPS DATE PROJECTIO N DATE 25-Jun10 October 2010 18 2.4.P1A.IN.01 Cryostat 19 4.1.P2.CN.01 AC/DC Convertors 13-Jul-10 July 2010 20 4.1.P2.KO.01 AC/DC Convertors 13-Jul-10 July 2010 21 4.1.P3.RF.01 Switching Network, Fast Discharge Units, DC Busbar & Instrumentation 19-Jul-10 July 2010 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 25 ITER Schedule Following First Plasma: Path to DT in 2026 First Plasma ITER Commissioning and Operations 2019 2020 2021 2022 2023 2024 2025 2026 2027 Hydrogen Operations & Coil Commissioning First Plasma Install InVessel Equipment, ECRH & ⅓ Diagnostics Install Blanket, Divertors,1st NBI, ICRH? & ⅓ Diagnostics Shutdown Commission Hydrogen Operations Tritium Plant Full DT Throughput Shutdown Install 2ndNBI, & ⅓ Diagnostics Commission H & He Operations Tritium Plant Ready for Nuclear Operation All H&CD Fully Commissioned Pre-Nuclear Shutdown Neutron Diagnostic Calibration Hydrogen Operations DD & Trace DT Operations Full DT 500 MW Fusion Attempt 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 26 What is Next? • The IO works towards finalizing a full set of baseline documents by the end April (scope, schedule, cost); • Scope is set in 2008. Schedule agreed as working basis in March 2010; • Resource loading of IPS for the IO is ongoing; • The acceptance of the ITER baseline towards a commonly agreed upon schedule is a huge step forward, since every party is committed to a common plan. 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 27 Present ITER Construction Site Future Tokamak Complex JWS 2 JWS 3 The creation and improvement of 106 kilometres of access roads from Fos harbour to Cadarache will be finished by February 2010. 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 28 1 Itinerary of ITER Components ITER Site = Itinerary of ITER Components 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 29 The Roadmap Beyond ITER Today’s expts. upgrade, construction Operation H ITER Des. D DT Construction 2nd DT Op. Phase Test/Optimise Blanket IFMIF Design Construction Qualify DEMO Materials DEMO Design Optimise Materials Construction Initial Operation Alternative Commercial Concept Confinement Power Plants Schemes 2nd RCM-FENDL-3, 23 March 2010, Vienna Design Reliability demo Construction Op. Page 30 Summary • It took almost four years to re-baseline ITER and have a common understanding of the real cost of ITER. In the parties and for the IO. • The baseline decision by Council in June 2010 will set the real trigger for all countries to now move at the same pace. • We still have lots of things to improve, technically, managerially and also in interfacing with industry partners. 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 31 ITER Licensing Process • Accordance with French regulations ITER is a “basic nuclear facility” (Installation Nucléaire de Base, INB) e.g. labs, fuel plants, not fission reactors. Compliance with international standards of safety (IAEA) • Licensing process: – Safety options report submitted and reviewed 2002 – Series of informal technical meetings with the authorities (ASN) and their technical advisors (IRSN), 2006 – 2008. – License application documents were submitted January 2008 • Request for authorisation (Demande d’Autorisation de Création, DAC), including Impact Study • Preliminary Safety Report (Rapport Préliminaire de Sûreté, RPrS) • Examination of files submitted in January 2008 – Authorities (ASN & IRSN) reviewed our files for acceptability – In July 2008, they requested detailed additional information in the files – DAC and RPrS are now being updated, for re-submission in 2010 • Next: Public Enquiry. Then examination by panel of independent experts (Groupe Permanent) to advise ASN. 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 32 Current status (October 2009) • All RPrS chapters and Impact Study are in first draft – Some require completion with the outcome of safety analyses in progress, or design information from baseline documents to be fixed • Many annexe documents completed – Translation into French under way • Reviews of RPrS to be held October – December, by technical ROs, Safety Control Division (“second level” check), and in review including external experts - English version to be finalized by end of 2009 • Translation in French and final checking – Submission expected end of February 2010 • Should lead to issue of decree allowing “creation” of facility. – Further processes will follow to obtain authorisation for commissioning and start-up. 2nd RCM-FENDL-3, 23 March 2010, Vienna Page 33