Sanitation Study and Wastewater Network System of AL Tayba

Download Report

Transcript Sanitation Study and Wastewater Network System of AL Tayba

Sanitation Study and Wastewater
Network System
AL Tayba Village
Ahlam Mahameed
Submitted to:
Dr. Sameer Shaded
Objectives:
1- Evaluation of the sanitation situation of AlTayba village
2- Design a sewer network system using
SewerCAD
3- Conceptual design of a wastewater
treatment process
Study Area
• Al-Tayba is located in the north of
the West Bank, 18 km northwest of
Jenin city.
• It has a population of 2407 person
• The village is a hilly area, and drain
into two wadis
• The climate is subtropical with
rainfall limited to the winter
months
Household
• All the houses are individual, with
area ranges from 90-200 m²
• The average of household members
is 6 persons per family
• About 66% are in medium
economical situation
Water Supply
The main water Supply is the
municipality water
The average water consumption
ranges from 5-25 m3 / month
Rainfall collection cistern and village
spring
Wastewater System:
There is no wastewater collection
System
Cesspits are used for wastewater
disposal
Solid Waste
• About 15 m3 of solid waste are
generated by AL Tayba village every
day
• The solid waste are transported to
Zahret AL Finjan Sanitary Landfill
• There is no solid waste containers in
the village
Designing the Sewer Network
• Contour map for the village
• Detailed plan of the village, including
houses, main streets
• The population data from the PCBS
• The water consumption from the village
council.
• The collected data through the
questionnaire .
2- Network Design:
Estimate the manhole loads:
1- The area served by each manhole is
labeled
2- Calculating the load for each manhole
3. Determine the manhole locations
The design constraints:
The velocity range 0.6-3 m/sec
The cover range from 0.8-4 m
The slope varies from 1-12%
Wastewater Treatment Plant
The first option:
use the following units:
Screen, Grit Chamber and Primary
Sedimentation Tanks.
The second option:
Use the following units: Screen, Septic tank
and Sand Filter.
WWTP Area:
The required area for WWTP is 550 m²
It is required 320 m² for the treatment
units and 230 m2 for operation units
Conclusions
•
•
•
•
•
•
Total number of manholes: 124 manholes
All pipes are 8“ diameter UPVC
The velocity varies between 0.4-1.51 m/sec
The cover on the manhole varies between
0.83-2.53 m
The maximum distance between manholes
do not exceed 80 m
The total length of the pipes are equal to
3.5 km
According to the designed sewage system
there are two alternatives:
1- Two separate local WWTPs with
preliminary and primary treatment.
2- One pumping station and one WWTP.
Recommendations
it is strongly recommended to establish
a sewage system for Al Taybeh.
It is also recommended to create an
awareness towards the reuse of
wastewater in agriculture .
Thank You