Transcript Slide 1
Real Options Analysis Office Tower Building Portfolio Presentation Fall 2008 ESD.71 Professor: Richard de Neufville Presented by: Charbel Rizk 1 Introduction • Application of Real Options in construction field • Time between design and completion relatively long • Large Investment, expected long life cycle • Office Building Tower – Based on real projects • 2 types of offices: o For Investor’s Use o For Sale • Project completion around 2000 •Lack of space in 2006 www.manenterprise.com 2 Objective & Procedure Analyze project based on tools and method learned in class: •Identify main uncertainties in design: o Investor’s Office requirement o Market Demand (Offices, Stores) - For simplicity considered only Investor’s office demand • Identify different scenarios: -Low; -Medium; -High • Find possible (feasible) options to be added: o Original: Fixed, deterministic design o Re-buy Option o Option to Add Floors • Evaluate all designs o Evaluation based on expected monetary value o Two stages decision analysis o Lattice decision analysis 3 Summary of Designs • Fixed design: (3 floors for investor’s use) o 7 Floors office tower o 4 Floors for sale • Flexible contract: (2, or 3, or 4 floors for investor’s use) o 7 Floors office tower o 3 Floors for sale o 2 Other floors for sale with option to Re-buy •Flexible design: (2, or 3, or 4 floors for investor’s use) o Start with 6 floors office tower o 4 Floors for sale o Option to add 1 or 2 Floors o Maximum number of floors is higher due to lower risk 4 Assumptions (Simplifying) & Expected Demand • Floors to be sold will be sold upon completion • Time for execution 1 year • Construction cost paid at t=0 • r=10% • i=2% • Assumed Cost of not having when required based on lost opportunities • Benefits are not included (Since using incremental NPV’s) • Area per floor= 220m2 5 General & Particular Costs • General, defined per unit applicable to all designs - Construction Cost - Maintenance - Running & Fees(Power, Ventilating, etc…) - Cost of Lacking space • Particular, unit rate differs or not applicable to all designs - Permit cost - Option Cost a) Allow for Re-buy option in contract b) Allow for adding floors (thicker columns, etc…) - Strike price a) Re-buying floor/s b) Adding floor/s 6 Two Stages Decision Analysis •Probabilities are shown below Year 0 (Actual) 2 Sc Bet Yrs 0&5 Year 5 (Forecast) Prob(0->5) Low 2 0.15 Medium 3 0.4 High 4 0.45 Sc Bet Yrs 5 & 10 Year 10 (Forecast) Prob(5->10) /Year(0->5) Low Medium High Low Medium High Low Medium High 2 2 3 3 4 4 4 4 4 0.6 0.3 0.1 0.15 0.4 0.45 0.05 0.25 0.7 •Flexible contract or design : Add option to change decision Year 5 Year 5 7 Two Stages Decision Analysis (Cont.) Fixed Design Design Type • NPV calculation for each end node •ENPV calculation •Pruning based on maximize ENPV EV At 5 Year 5 High High High Medium Medium Medium Low Low Low Action at year 5 Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Year 10 Low Medium High Low Medium High Low Medium High Status Low - Low Low- Medium Low - High Probability 0.09 0.045 0.015 Best Decision Can't Do antg Can't Do antg Can't Do antg Fixed Design Value -2,227,429 -2,227,429 -1,938,965 Medium - Low Medium - Medium Medium - High 0.06 0.16 0.18 Can't Do antg Can't Do antg Can't Do antg -1,938,965 -2,227,429 -2,227,429 High - Low High - Medium High - High 0.0225 0.1125 0.315 Can't Do antg Can't Do antg Can't Do antg -2,227,429 -2,227,429 -2,227,429 Decide if Possible @5 Options -2,227,429 -2,227,429 -2,227,429 -2,227,429 -1,938,965 -2,227,429 -2,184,159 -2,205,794 -2,227,429 -2,227,429 -2,227,429 -2,198,583 -1,938,965 Expected V. -2,205,794 Best Decision Do Nothing Do Nothing Do Nothing Flexible Contract Value Expected V. -1,067,182 -1,067,182 -1,355,645 Re-Buy 1 Fl Re-Buy 1 Fl Re-Buy 1 Fl -1,337,283 -1,625,747 -1,625,747 Re-Buy 1 Fl Re-Buy 1 Fl Re-Buy 1 Fl -1,625,747 -1,625,747 -1,625,747 -1,528,981 Decsision @ Year 5 If Scenario EV @0 If Design Type Nothing To Chose -2,205,794 Best Decision Do Nothing Do Nothing Do Nothing Flexible Design Value -1,143,182 -1,143,182 -1,431,645 Add 1 Floor Add 1 Floor Add 1 Floor -296,796 -585,260 -585,260 Add 2 Floors Add 2 Floors Add 2 Floors -550,411 -550,411 -550,411 Expected V. -640,285 8 Two Stages Decision Analysis (Cont.) Best Strategy & VARG: At t=0 choose flexible design a) If demand during first period Was high => Add 2 Floors b) If demand during first period was Medium => Add 2 Floors c) If demand during first period was Low => Don’t Add Floors VARG Chart 1.2 1 Probabilities 0.8 Fixed Design Flexible Contract 0.6 Flexible Design EV Fixed Design 0.4 EV Flexible Contract EV Flexible Design 0.2 0 -2,500.00 -2,000.00 -1,500.00 -1,000.00 -500.00 0.00 Values in 1,000$ 9 Lattice Decision Analysis • Determine: u, d, & p using: - Maximum Value= S u u => u= Sqrt(Max/S) - Minimum Value= S d d => d= Sqrt(Min/S) - Most Likely= p2 * (S u u ) + 2*p*(1-p)*(S u d) + (1-p)2 * (S d d) • Results: -u= 1.4142 - d= 1.0000 - p= 0.8494 10 Lattice Decision Analysis (Cont.) • Resulting outcome & probability lattice: P=0 2.00 Outcome Lattice P=1(5 Yrs) P=2 (10 Yrs) P=3(15 Yrs) P=4(20 Yrs) P=5(25Yrs) 2.83 4.00 5.66 8.00 11.31 2.00 2.83 4.00 5.66 8.00 2.00 2.83 4.00 5.66 2.00 2.83 4.00 2.00 2.83 2.00 P=0 1.00 Probability Lattice P=1(5 Yrs) P=2 (10 Yrs) P=3(15 Yrs) P=4(20 Yrs) P=5(25Yrs) 0.85 0.72 0.61 0.52 0.44 0.15 0.26 0.33 0.37 0.39 0.02 0.06 0.10 0.14 0.00 0.01 0.02 0.00 0.00 0.00 • Probability distribution function: PDF for Lattice c-1 c-2 c-3 c-4 c-5 c-6 Outcome Prob 11.31 8.00 5.66 4.00 2.83 2.00 0.44 0.39 0.14 0.02 0.00 0.00 Rank 5.00 4.00 3.00 2.00 1.00 0.00 0.45 0.40 0.35 0.30 0.25 0.20 0.15 0.10 0.05 0.00 -0.050.00 Probability Data for PDF: 5.00 10.00 15.00 20.00 Outcome 11 Lattice Decision Analysis (Cont.) • Option evaluation: - Prepare cash flow per state & stage for each design - Find ENPV for each design: ENPV = Cash Flow Lattice * Probability Lattice Flexible Design Cash Flow in 1,000 of $ Expanded (Taking All 4 Floors) P=0 Cash Flow (566.00) Flexibility 2 Floors Added Dynamic programming approach P=1 P=2 P=3 (4469.67) (4687.05) (7689.60) (6082.43) (7332.96) (7689.60) (9978.88) (12030.50) (16371.40) P=4 (7689.60) (7689.60) (7689.60) (12030.50) (16371.40) P=5 (7689.60) (7689.60) (7689.60) (7689.60) (12030.50) (16371.40) Flexible Design ENPV in 1,000 of $ Expanded (Taking All 4 Floors) P=0 P=1 P=2 P=3 P=4 ENPV (Cash Flow) (9376.07) (13617.63) (14267.18) (15428.91) (12464.23) Flexibility (17410.70) (17360.39) (15428.91) (12464.23) 2 Floors Added (23231.25) (20213.55) (12464.23) Dynamic programming (27715.82) (17210.94) approach (24247.20) P=5 (7689.60) (7689.60) (7689.60) (7689.60) (12030.50) (16371.40) - Decison Lattice (Strategy): Excercise CALL OPTION ? P=0 Add 2 Fl. P=1 Add 2 Fl. Don't Add P=2 Add 2 Fl. Add 2 Fl. Don't Add P=3 Add 2 Fl. Add 2 Fl. Add 2 Fl. Don't Add P=4 Add 2 Fl. Add 2 Fl. Add 2 Fl. Don't Add Don't Add P=5 12 Lattice Decision Analysis (Cont.) • VARG For Lattice: - Enumeration of all paths (5 periods 2 decisions => 32 Paths) - Calculate PV for each path - Find probabilities and prepare cumulative distribution 5 up 4 up 1 Down 3 up 2 Down 2 up 3 Down 1 up 4 Down 5 Down EPV P P(PATH) -621.1716915 -619.4651603 -283.0459493 -59.32895678 -6.114694908 -0.252082597 0.39177081 0.40377568 0.16645936 0.03431202 0.00353634 0.00014579 0.39177081 0.08075514 0.01664594 0.0034312 0.00070727 0.00014579 ENUMERATION OF PATHS WITHOUT CLOSING OPTION (1585.55) (1585.55) (1585.55) (1729.10) (1729.10) (1729.10) (1585.55) (1585.55) (1729.10) (1729.10) (1585.55) (1729.10) (1729.10) (1729.10) (1457.13) (1729.10) (1729.10) (1729.10) (1457.13) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) (1729.10) 13 Conclusions • Demand variance was small and still: - Based on decision trees: Flexible design was best alternative - Based on lattice analysis: Option value above $ 1 M • All values are not accurate, they are upper & lower bounds only • Designers should take uncertainty into consideration, especially with the availability of all new tools • Discussion in this paper is based on NPV analysis only • Other tools metrics can also be taken into consideration for example: - Benefit to cost ratio - Payback period - Risks - Range of outcomes (maximum, minimum) 14 Thank you For Your Time Comments? Questions? 15