Magnet design and optimization

Download Report

Transcript Magnet design and optimization

CIEMAT technological
contributions to linear colliders
Fernando Toral
Gandía, 3/12/2005
Outline






Accelerator capabilities
TESLA500
XFEL
ILC
CLIC
Conclusions
Fernando Toral - Gandía, 3/12/2005
2
Accelerator capabilities

Particle superconducting magnets:






Conduction-cooled superconducting magnets.
High frequency electromagnetic devices:



Magnetic and mechanical design.
Prototype fabrication.
Testing of magnets up to 400 mm long.
Associated components: current leads, power supplies.
Kicker magnets: design and fabrication of prototypes.
RF cavities (PETS for CLIC): design and fabrication of
prototypes.
Other CIEMAT capabilities:



Detectors.
Electronics & instrumentation
IFMIF
Fernando Toral - Gandía, 3/12/2005
3
TESLA500 contribution (I)
Design and cost estimation of the superconducting magnet package for
the TESLA 500 Technical Design Report (2000).
Design and fabrication of a pair of 100 A HTS current leads (2001).
Design and fabrication of a machine to glue ribbons of superconducting
wires (2001): thickness accuracy better than 5 microns for a 130 m
long ribbon of 8 wires (0.46 mm x 0.69 mm).
Fernando Toral - Gandía, 3/12/2005
4
TESLA500 contribution (II)
Calculation and detailed design of a combined superconducting prototype
magnet for TESLA500: a quadrupole and two dipoles. (2002-04)
Parameter
Quadrupole
Nominal current
Bore diameter
Number of turns
Bare wire
Insulated wire
Cu/Sc ratio
Main field
Magnetic length
First multipole**
Second multipole**
Third multipole**
2-D peak field
3-D peak field
Working point@2K
Self inductance
100
90
50x16
0.42x0.63
0.46x0.69
1.84
60
588
0.4348
35.845
1.056
3.20
3.62
49.5
2.35
3- D magnetic calculation for XFEL
** Reference radius is 30 mm.
Inner
dipole
40
114.56
111x1
0.42x0.63
0.46x0.69
1.84
0.140
588
-0.23
-146.32
-0.160
-15.5*
0.0332
Outer
dipole
40
118.02
114x1
0.42x0.63
0.46x0.69
1.84
0.144
588
1.34
-143.42
-0.175
-14.8*
0.0364
Fernando Toral - Gandía, 3/12/2005
Units
A
mm
mm
mm
T/m - T
mm
unit
unit
unit
T
T
%
H
5
TESLA500 contribution (III)
Calculations
Double-pancake winding
Quad coil X-section
Vacuum impregnation mould
Fernando Toral - Gandía, 3/12/2005
6
TESLA500 contribution (IV)
Assembly mandrel
Vacuum impregnation
Connection plate
Finished magnet
Fernando Toral - Gandía, 3/12/2005
7
TESLA500 contribution (V)
Training tests (2005)
140
130
CURRENT (A)
120
110
100
90
80
training 4K quad
training 4K combined
training 4K quad
training 2K quad
retraining 4K quad
first campaign 4K
70
60
50
0
5
10
15
20
25
30
35
QUENCH NUMBER
3- D magnetic calculation for XFEL
Fernando Toral - Gandía, 3/12/2005
8
TESLA500 contribution (VI)
Field quality (2005)
Normalized Multipoles at 30mm
Normalized Multipoles at 30mm
1
1
0.1
0.1
0.01
0.01
1 10
3
1 10
4
1 10
5
5
10
15
1 10
3
1 10
4
0
Multipole Order
Quadrupole 100A
Quadrupole 10A
Detection level at 10A
3- D magnetic calculation for XFEL
Fernando Toral - Gandía, 3/12/2005
5
10
15
Multipole Order
Dipole 2 at 40A
Dipole 2 at 5A
Detection level at 5A
9
XFEL contribution
Design of a combined superferric magnet (2005).
Fabrication of four prototypes (2006).
Series production (120 units, 2007-08).
Strength
Operating current
Gradient / field
Quadrupole
5.6T
50 A
35 T/m
3- D magnetic calculation for XFEL
Inner dipole
0.006 Tm
50 A
0.04 T
Outer dipole
0.006 Tm
50 A
0.04 T
Fernando Toral - Gandía, 3/12/2005
10
ILC contribution
The TESLA500 prototype magnet will be tested
in SLAC (2006) to carefully measure:
 The stability of the magnetic axis (better than
5 microns).
 The field quality at low currents (persistent
currents effect).
3- D magnetic calculation for XFEL
Fernando Toral - Gandía, 3/12/2005
11
CLIC contribution
Spanish Contribution as stated in the 2004 Coll. Meeting
2004
TASKS
N
ITEM
2005
J
M
M
J
S
N
J
M
M
0.1 “ COMPL. ACTION” REQUEST
0.2 “ COMPL. ACTION” APPROVAL
1.2 FABRICATION
J
S
N
J
DEADLINE
2007
M
M
J
Correctors
33 H/V Orbit Correct Magnets for
the Combiner Ring and Transfer
Lines. (Existing design)
July -2005
Septa
2 Double Septa Magnets for the
Combiner Ring (Only a reference
design)
Dec-2005
Kickers
1 “Stripline” Extraction Kicker (Only
a reference design)
Oct-2006 ???
TBL Quads
15 Quadrupole Magnets with
motorised support structure for the
Test Beam Line
Mid-2007
PETS
1 Power Extraction Transfer
System Prototype
Dec-2006
CORRECTORS
1.1 DRAWINGS & TOOLING
DESCRIPTION
2006
SEPTA
2.1 DESIGN
2.2 DRAWINGS & TOOLING
2.3 FABRICATION
KICKERS
3.1 CALCULATION
3.2 DESIGN
3.3 DRAWINGS & TOOLING
3.4 FABRICATION & TESTS
TBL QUADS.
4.1 MAGNET DESIGN
4.2 STRUCTURE DESIGN
4.3 MAGNET DRAWINGS
4.4 STRUCTURE DRAWINGS
4..5 MAGNET FABRICATION
4.6 STRUCTURE FABRICATION
4.7 ASSEMBLY & TESTS
PETS
5.1 CALCULATION & DESIGN
5.2 DRAWINGS
5.3 FABRICATION OF ONE OCTANCT
5.4 FABRICATION OF A PROTOTY PE
3- D magnetic calculation for XFEL
Fernando Toral - Gandía, 3/12/2005
12
CLIC CONTRIBUTION:
1. Orbit Corrector Magnets (I)
2004
TASKS
N
2005
J
M
M
J
2006
S
N
J
M
M
J
2007
S
N
J
M
M
J
CORRECTORS
1.1 DRAWINGS & TOOLING
1.2 FABRICATION
MAIN ACTIVITIES DURING THE PAST YEAR:
• Placement of the Order (December 04)
• Drawings Approved by CERN (April 05)
• Tooling development (May 05)
• Laminations fabrication (June 05)
• Pre-Series delivery to CERN (2 Magnets) (September 05)
• Final Approval by CERN (Magnetic Measurements) ( Pending)
PRESENT STATUS:
• All the magnet components are under fabrication
• Pole fabrication is almost finished (100% stacked & cured, 100% machined, 25% wound & tested)
SHORT TERM ACTIVITIES:
• All the coils will be wound in 3 weeks
• Magnets will be mounted 4 weeks later : All the units should be finished by the end of the year
CONCLUSION: An overall delay of 5 months, but still on time for CTF3
Fernando Toral - Gandía, 3/12/2005
13
CLIC CONTRIBUTION:
1. Orbit Corrector Magnets (II)
STATUS OF THE FABRICATION PROCESS
1.- POLE STACKING
3.- WINDING
2.- POLE INSULATION
4.- COIL ELEC. TESTS
5.- FINAL ASSEMBLY (PRE-SERIES)
Fernando Toral - Gandía, 3/12/2005
14
CLIC CONTRIBUTION:
2. Septa Magnets (I)
2004
TASKS
N
2005
J
M
M
J
2006
S
N
J
M
M
J
2007
S
N
J
M
M
J
SEPTA
2.1 DESIGN
2.2 DRAWINGS & TOOLING
2.3 FABRICATION
MAIN ACTIVITIES DURING THE PAST YEAR:
•
•
•
•
•
Start of the Conceptual design ( March 05)
Placement of the Order for the Conceptual Design ( June 05)
Technical Design Review of the Conceptual Design at CERN ( July 05).
Final Report on the Conceptual Design ( July 05)
Placement of the Order for the Fabrication ( October 05)
SHORT TERM ACTIVITIES:
•
•
•
•
Fabrication Drawings (December 05)
Tooling and Components Fabrication (excl. Coils) (January 06).
Coil Fabrication (February 06)
Magnet Assembly: Septa Finished (15-March-2006).
CONCLUSION: An overall delay of 2
CTF3 ( IN THE LIMIT)
1/2
months, but still on time for
Fernando Toral - Gandía, 3/12/2005
15
CLIC CONTRIBUTION:
2. Septa Magnets (II)
CONCEPTUAL DESIGN
Thin Septum
CONCEPTUAL DESIGN
Thick Septum
MAGNETIC CALCULATIONS
MAGNETIC MODELLING
Fernando Toral - Gandía, 3/12/2005
16
CLIC CONTRIBUTION:
3. Kicker magnet (I)
2004
TASKS
N
2005
J
M
M
J
2006
S
N
J
M
M
J
2007
S
N
J
M
M
J
KICKER
3.1 CALCULATION
3.2 DESIGN
3.3 DRAWINGS & TOOL ING
3.4 FABRICATION & TESTS
MAIN ACTIVITIES DURING THE PAST YEAR:
• Visit to Frascati to start contacts with INFN about the kicker design. (February 05)
• Placement of the order to purchase HFSS (April 2005)
• A new engineer joints the team, devoted specifically for this development (August 05)
• Arrival of the HFSS license to CIEMAT & Installation on a specific PC (3GHz,2Gb RAM) (August 05)
• First simulation of a Stripline Kicker based on INFN previous designs (September 05)
• New visit to Frascati. Discussion about specifications, model geometries and kicker optimization parameters. (October 05).
• Starting of calculations & simulations of a real magnet (November 05)
SHORT TERM ACTIVITIES:
• Conceptual Design of the Kicker Magnet ( March 05)
• Drawings for Fabrication ( April 05)
CONCLUSION: An overall delay of about 4 months, but correction actions
can be taken to have the magnet finished by the end of 2006
Fernando Toral - Gandía, 3/12/2005
17
CLIC CONTRIBUTION:
3. Kicker Magnet (II)
STUDY OF DIFFERENT CROSS-SECTIONS: IMPEDANCE CALCULATION
MAGNETIC & ELECTRIC FIELD CALCULATIONS FROM THE COMPLETE GEOMETRY
Fernando Toral - Gandía, 3/12/2005
18
CLIC CONTRIBUTION:
3bis. Kicker Power Supply
MAIN ACTIVITIES DURING THE PAST YEAR:
• First meeting with SLAC to discuss a possible collaboration with LLNL
for the development of the kicker pulser. (Very Unlikely). (May 05)
• Contact with Spanish Industry to develop this pulser which has other
potential applications (Feb-Nov 2005)
SHORT TERM ACTIVITIES:
• To be defined
CONCLUSION: A decision must be taken on how to continue with this
development. Spanish participation on her own seems very difficult
Fernando Toral - Gandía, 3/12/2005
19
CLIC CONTRIBUTION:
4. TBL QUADS (I)
2004
TASKS
N
2005
J
M
M
J
2006
S
N
J
M
M
J
2007
S
N
J
M
M
J
TBL QUADS.
4.1 MAGNET DESIGN
4.2 STRUCTURE DESIGN
4.3 MAGNET DRAWINGS
4.4 STRUCTURE DRAWINGS
4..5 MAGNET FABRICATION
4.6 STRUCTURE FABRICATION
4.7 ASSEMBLY & TESTS
MAIN ACTIVITIES DURING THE PAST YEAR:
• Analysis of solutions for the Moving Table ( March 05)
• Moving Table Conceptual Design (October 05)
• Moving Table Component Selection (October 05)
• Moving Table Technical Design presentation at CERN (November 05)
SHORT TERM ACTIVITIES:
• Validation of Design and Components ( December 05)
• Drawings of the MT Prototype ( February 05)
• Fabrication of the MT Prototype (June 05)
CONCLUSION: Initial planning has been changed significantly to stress the work
on the Moving Table as Magnet Design and Fabrication seems a more
conventional activity.
Fernando Toral - Gandía, 3/12/2005
20
CLIC CONTRIBUTION:
4. TBL QUADS (II)
TBL QUADS MOVING TABLE
Section at the Horizontal
Actuator
Section at the Vertical
Actuator
Fernando Toral - Gandía, 3/12/2005
21
CLIC CONTRIBUTION:
5. PETS
2004
TASKS
N
2005
J
M
M
J
2006
S
N
J
M
M
J
2007
S
N
J
M
M
J
PETS
5.1 CALCULATION & DESIGN
5.2 DRAWINGS
5.3 FABRICATION OF ONE OCTANCT
5.4 FABRICATION OF A PROTOTY PE
MAIN ACTIVITIES DURING THE PAST YEAR:
• Market survey for PETS fabrication in Spain (Jan-Sep 05)
• Purchasing of the HFSS software (August 05)
• A new engineer joints the team, devoted specifically for this development (Nov 05)
• First trials to machine one small PET octant at CIEMAT (Sep-Dec 05)
• Placement of the order to manufacture a 400 mm PET Octant at the Industry (Oct 05)
SHORT TERM ACTIVITIES:
• Reception of the first industrial prototype of PETS octant (January 06)
• Verification of CIEMAT PETS Octant ( February 06)
• Stay at CERN of the CIEMAT engineer for the full PETS design (Nov-?? 06)
CONCLUSION: Relevant modifications have been made in
the planning due to the delay in the starting of the new
engineer (design has been substituted by fabrication)
Fernando Toral - Gandía, 3/12/2005
22
Conclusions


The Superconductivity Laboratory CIEMATCEDEX has been collaborating with different
linear accelerators since 2000: TESLA500, XFEL,
ILC, CLIC.
Former contributions were superconducting
magnets, now we are also including HF
electromagnetic devices.
Fernando Toral - Gandía, 3/12/2005
23