Extent of the radioactive cloud

Download Report

Transcript Extent of the radioactive cloud

Extent of the radioactive cloud
Fukushima Nuclear plant accident
• 11 March 2011 –9.0 magnitude undersea Earthquake and
Tsunami hit northern Japan
• Plant contains 6 boiling water reactors, 3 of which were
offline at the time of the earthquake(4,5,6).
• Reactors 1,2,3 were shut down after the earthquake, but
the tsunami flooding caused electrical failure which
knocked out the emergency pumps needed to cool and
control water flowing into the reactors.
• Initial concern is over the damaged storage pool for
spent fuel from reactor 2
• Pressure is seen to rise in Unit 1, as cooling system fails
Fukashima Timeline
• March 12
– Battery power for reactor 3 cooling system runs out and its
fuel rods are exposed.
– Unit 1 and 2 vent radioactive steam to relive the pressure
building up
– H explosion occurs in Unit 1
• March 14
– H explosion at Unit 3
– Unit 2 fuel rods are fully exposed to air, and seawater is
pumped in to cool them
Fukushima Timeline
• March 15
– Fire breaks out in Unit 4
– Unit 2 experiences another explosion. Fuel rods
may be melting
– Explosion occurs at Unit 4
– Fire in the spent fuel pond at Unit 4 is releasing
radioactivity into the air and water may be boiling
off in the pond
– Unit 5 water level is falling
– Unit 3 spent fuel pond has decreasing water levels
Fukushima Timeline
• March 17
– Radiation levels are rising in cities within 75KM of the
plant
• March 19
– Power becomes available to Unit 5 and 6.Cooling of Unit 5
spent fuel pond begins.
– Milk and spinach in areas near the power station are found
to have increased levels of radioactivity.
– Unit 6 spent fuel pond begins to be cooled
• March 21
– Full cooling to reactor 5 is resumed
Fukushima Timeline
• March 22
– Seawater near the plant shows elevated levels of
radioactivity
• March 23
– Power restored to Unit 3
• March 24
– 3 workers exposed to radiation in Unit 3 turbine
building. 2 received radiation burns after standing
in contaminated water for2 hours without
protective boots.
Fukushima Timeline
• March 25
– Possible breaches in the containment buildings of Units 1,2,3
reported.
• March 26
– Radiation levels of 10 million times normal in the Unit 2 turbine
room were reported, but later found to be inaccurate. It was
only 100,000 times higher than normal.
– Damage is now known to be:
• Roof of reactor 2 damaged but intact
• Reactor 3 roof is blown away
• Walls of reactor 4 building have collapsed
• Steam is emanating from reactors 2,3,4
Fukushima Timeline
• March 28
– Radioactive water found in tunnels that house
electrical wires form the turbines, and within
meters over overflowing which would send this
water into the sea.
• March 29
– Radiation reported to have reached the UK and
US, though not at unsafe levels.
3 minutes after second explosion at
Unit 3
Other accidents-1980s
•
•
•
•
•
•
March 13, 1980 –- Orléans, France - Nuclear materials leak
–
A brief power excursion in Reactor A2 led to a rupture of fuel bundles and a minor release (8 x 1010 Bq) of nuclear
materials at the Saint-Laurent Nuclear Power Plant. The reactor was repaired and continued operation until its
decommissioning in 1992.
March, 1981 - Tsuruga, Japan – Overexposure of workers
–
Overexposure of workers More than 100 workers were exposed to doses of up to 155 millirem per day radiation
during repairs of a nuclear power plant, violating the company's limit of 100 millirems (1 mSv) per day.
September 23, 1983 Buenos Aires, Argentina - Accidental criticality
– An operator error during a fuel plate reconfiguration in an experimental test reactor led to an excursion of 3×1017
fissions at the RA-2 facility. The operator absorbed 2000 rad (20 Gy) of gamma and 1700 rad (17 Gy) of neutron
radiation which killed him two days later. Another 17 people outside of the reactor room absorbed doses ranging
from 35 rad (0.35 Gy) to less than 1 rad (0.01 Gy).
April 26, 1986 — Prypiat, Ukraine (then USSR) - Power excursion, explosion, complete meltdown
– A mishandled reactor safety test led to an uncontrolled power excursion, causing a severe steam explosion, meltdown
and release of radioactive material at the Chernobyl nuclear power plant located approximately 100 kilometers northnorthwest of Kiev.
May 4, 1986 – Hamm-Uentrop, Germany (then West Germany) - Fuel damage
– A spherical fuel pebble became lodged in the pipe used to deliver fuel elements to the reactor at an experimental
300-megawatt THTR-300 HTGR. Attempts by an operator to dislodge the fuel pebble damaged its cladding, releasing
radiation detectable up to two kilometers from the reactor.
November 24, 1989 — Greifswald, Germany (then East Germany) - Fuel damaged
– Operators disabled three of six cooling pumps to test emergency shutoffs. Instead of the expected automatic
shutdown a fourth pump failed causing excessive heating which damaged ten fuel rods. The accident was attributed
to sticky relay contacts.
Other Accidents 1990s
•
April 6, 1993 — Tomsk, Russia – Explosion
–
•
June, 1999 - Ishikawa Prefecture, Japan - Control rod malfunction
–
•
A pressure buildup led to an explosive mechanical failure in a 34 cubic meter stainless steel reaction vessel
buried in a concrete bunker under building 201 of the radiochemical works at the Tomsk-7 Siberian Chemical
Enterprise plutonium reprocessing facility. The vessel contained a mixture of concentrated nitric acid,
uranium (8757 kg), plutonium (449 g) along with a mixture of radioactive and organic waste from a prior
extraction cycle. The explosion dislodged the concrete lid of the bunker and blew a large hole in the roof of
the building, releasing approximately 6 GBq of Pu 239 and 30 TBq of various other radionuclides into the
environment. The contamination plume extended 28 km NE of building 201, 20 km beyond the facility
property. The small village of Georgievka (pop. 200) was at the end of the fallout plume, but no fatalities,
illnesses or injuries were reported. The accident exposed 160 on-site workers and almost two thousand
cleanup workers to total doses of up to 50 mSv (the threshold limit for radiation workers is 100 mSv per 5
years)
Operators attempting to insert one control rod during an inspection neglected procedure and instead
withdrew three causing a 15 minute uncontrolled sustained reaction at the number 1 reactor of Shika
Nuclear Power Plant. The Hokuriku Electric Company who owned the reactor did not report this incident and
falsified records, covering it up until March, 2007.
September 30, 1999 — INES Level 4 - Ibaraki Prefecture, Japan - Accidental criticality
–
Workers put uranyl nitrate solution containing about 16.6 kg of uranium, which exceeded the critical mass,
into a precipitation tank at a uranium reprocessing facility in Tokai-mura northeast of Tokyo, Japan. The tank
was not designed to dissolve this type of solution and was not configured to prevent eventual criticality.
Three workers were exposed to (neutron) radiation doses in excess of allowable limits. Two of these workers
died. 116 other workers received lesser doses of 1 mSv or greater though not in excess of the allowable
limit..
Other accidents -2000s
•
April 10, 2003 - Paks, Hungary - Fuel damaged
–
•
April 19, 2005 — Sellafield, England, United Kingdom - Nuclear material leak
–
•
Partially spent fuel rods undergoing cleaning in a tank of heavy water ruptured and spilled
fuel pellets at Paks Nuclear Power Plant. It is suspected that inadequate cooling of the rods
during the cleaning process combined with a sudden influx of cold water thermally shocked
fuel rods causing them to split. Boric acid was added to the tank to prevent the loose fuel
pellets from achieving criticality. Ammonia and hydrazine were also added to absorb iodine131.
Twenty metric tons of uranium and 160 kilograms of plutonium dissolved in 83,000 literes of
nitric acid leaked over several months from a cracked pipe into a stainless steel sump chamber
at the Thorp nuclear fuel reprocessing plant. The partially processed spent fuel was drained
into holding tanks outside the plant.
November 2005 — Braidwood, Illinois, United States - Nuclear material leak
– Tritium contamination of groundwater was discovered at Exelon's Braidwood station.
Groundwater off site remains within safe drinking standards though the NRC is requiring the
plant to correct any problems related to the release.
•
March 6, 2006 — Erwin, Tennessee, United States - Nuclear material leak
– Thirty-five liters of a highly enriched uranium solution leaked during transfer into a lab at
Nuclear Fuel Services Erwin Plant. The incident caused a seven-month shutdown and a
required public hearing on the licensing of the plant.
Fusion
• Powers the sun
• In fusion, we combine
two atoms and release
energy
• Easiest to do this with H
or its isotopes
– We already talked about
the proton-proton chain in
the sun
• D-T reaction-takes
deuterium and tritium
and creates He
Fusion
• In order for these reactions to occur, one
needs the deuterium and tritium at high
temperatures
• For the DT reaction, T = 40 x 106 K
• For DD reaction, T = 100 x 106 K
• DT is good for bombs, not so good for long
term power, and tritium has a half life of 12
years
Thermonuclear devices
• Also called H bombs, these are
fusion bombs
• Require fission to compress
and heat the fusion fuel.
• The fusion releases enormous
amounts of high speed
neutrons which are then
often used to induce fission in
matter that it is normally
difficult to induce fission in
(such as depleted Uranium,
Uranium composed mostly of
238U).
• This adds to the radioactive
fallout of the bomb
Fusion reactors
• Main problem is maintaining
the fusion material at high
enough T so that fusion
produces the bulk of the
energy (break even)
• Confined plasma via a
magnetic field so it does not
contact the container walls
(which would cool it and
quench the reaction)
• Not nearly as hazardous as
fission reactors, most studies
show severe failures to be
contained within the plants
themselves.
Barriers to fusion power
• Scientific feasibility of the reactions
• Economics
• Damage to reactor components due to large
flux of high energy neutrons
• Availability of materials to build the reactors
• Maybe in 50 years -but we have been saying
that for 50 years!
Planes, trains and automobiles
• 27% of the total national energy budget goes
into transportation
• Of this 27%, 35% is used by automobiles
• Autos are among the least energy efficient
modes of transportation (Bicycles are number
1)
• Rely on the internal combustion engine
What does it take to move a car?
• Four force terms need to be considered:
• Force needed to accelerate the vehicle
– Fa = ma
• Force needed to climb any hills
– Fh=msg, where s is the slope of the hill
• Force needed to overcome internal energy losses (tire flexure,
wheel bearings, friction with the road surface, etc)
– Fr = Crmv, where Cr is a constant term
• Force needed to overcome aerodynamic drag on the vehicle,
depends upon speed.
– Fad = CD Af v2 /370 where CD is the aerodynamic drag coefficient, Af is
the frontal area of the vehicle.
• So the total force required is the sum of these 4 terms:
– FT = Fa + Fh + Fr + Fad
Energy required
• The energy required will be equal to the work
done by the force over a given distance or
– E = W = Fd or
– E = Pt, where P is the power output and t is the
time the vehicle is operated or
– E = Fvt
• So to minimize energy, you need to minimize
the forces.
Making current cars more efficient
• Minimize the force required:
– ma+msg+ Crmv+CD Af v2 /370
•
•
•
•
•
•
Make m small
Make Cr small
Make CD small
Make Af small
Make v small
Or any combination of reducing these values