Purpose of Dashboard
Download
Report
Transcript Purpose of Dashboard
Construction Schedule Best
Practices
®
Overview
• Benefits of a Good Construction Schedule
• Baseline Schedule Development
• Schedule Updating and Maintenance
• Managing Project Changes
• USACE – Specific Schedule Requirements
• Conclusion
1
Benefits of a Construction
Schedule
®
Requires thinking the project through prior to starting the work
Provides a structured approach to executing the project
Provides a means of communicating Scope and planned work
sequence to stakeholders
Identification of problems before they arise
Identification of long-lead procurement/fabrication items
Assessment of resource requirements
Forecasting of cash flow requirements
Serves as primary documentation for modeling delay impacts
2
Baseline Schedule
Development
®
Key Considerations
• Scheduling Software
• Project WBS (Work Breakdown Structure)
• Contract Milestones
• Submittal Requirements
• Activity Coding Requirements
• Project Stakeholders
• Cost & Resources Loading Requirements
• Updating & Reporting Requirements
• Testing & Startup Requirements
• Project Closeout Requirements
3
Baseline Schedule
Development (Cont.)
®
Key Elements
• Milestones
• Design Phase
• Pre-Construction
Submittals/Review
• Construction
Submittals/Review
• Procurement Activities
• Fabrication & Delivery
Activities
• Site Work & Utilities
• Interior Finishes
• Foundations & Structural
• Interior MEP Finishes
• Exterior Finishes
• Testing & Turnover
• Interior MEP Rough-ins
• Project Close-out
4
Baseline Schedule
Development (Cont.)
®
Key Configuration/Control
• CPM with “Retained Logic”
• No open ended activities
(Pred/Succ)
• Activity Durations <20 days
• Activity Calendars
(Work Days vs.
Calendar Days, Weather Days)
• Total Float based on “Longest
Path”
• Limited use of Constraints
• Supports contract required
completion date
5
Schedule Updating /
Maintenance
®
Key Considerations
• Contract Requirements
• Backup to Pay Requests
• Submittal Updates
• Procurement Updates
• Subcontractor Updates
• Impacts / Delays
• Contract Changes
• Reporting Requirements
6
Schedule Updating /
Maintenance
®
Key Elements
• Schedule Update “Data Date”
• Update to reflect actual period
progress / status
» Actual Start Dates
» Actual Finish Dates
» % Complete (Physical)
» Remaining Duration
• Activity Relationship Changes
• Activities Added / Deleted
• Update Narrative Report
7
Schedule Updating /
Maintenance
®
Key Configuration/Control
• Schedule “Data Date”
• Correct “Out of Sequence” Progress
• No open ended activities (Pred/Succ)
• Total Float based on “Longest Path”
• Incorporates all known Impacts and
Delays
• Incorporates Contract Changes
• Updated/Revised Critical Path
• Includes Update Narrative Report
8
Managing Project Changes
®
Key Elements
• Add Changes to the schedule as they
occur.
• Change activities need to be tied to
activities that are or will be
impacted.
• Changes and projected impacts need
to be discussed in the Update
Narrative report.
• Change Notification needs to be
made early and in accordance with
Contract requirements.
• Impact analysis should be performed
as early as possible.
9
USACE Requirements
®
USACE – Project Schedule Requirements
Unified Facility Guide Specification
• UFGS – 01 32 01.00 10, Project Schedule
Contract Specification Section
• 01 32 01.00 ??, Project Schedule
USACE Regulation
• ER 1-1-11, Progress, Schedules, and Network Analysis Systems
10
USACE Requirements
®
3.1 - General Requirements
Contractors proposed sequencing of the project work scope.
Forward planning and project monitoring tool.
Includes dates on which the Contractor contemplates starting
and completing all scheduled activities.
Represents entire project including design, procurement,
construction, and turnover.
Includes participation by contractor management, designers,
subcontractors, suppliers.
11
USACE Requirements
®
3.1 - General Requirements (continued)
3.1.1 - Approved Project Schedule
• Must be Cost Loaded
• Must have all required activity coding
• Used to measure work progress
• Forms basis for progress payments
• Aids in evaluating time impacts and extensions
• Approval of Progress Payments may be withheld
without schedule submission
12
USACE Requirements
®
3.2 - Basis for Payment and Cost Loading
Activity cost loading shall be reasonable
Activity cost loading must balance with contract CLIN values
Basis for determining period contract earnings/progress
payments
Lack of approved schedule will impact processing of progress
payments
Retainage may be withheld if changes/revisions have not
been incorporated into the updated schedule
13
USACE Requirements
®
3.3 - Project Schedule Detail Requirements
3.3.1 - Critical Path Method
3.3.2 - Level of Detail Required
3.3.3 - Scheduled Project Completion and Activity Calendars
3.3.4 - Interim Completion Dates
3.3.5 - Default Progress Data – Not Allowed
3.3.6 - Out-of-Sequence Progress – Not Allowed
3.3.7 - Negative Lags and Start to Finish Relationships – Not Allowed
3.3.8 - Calculation Mode – Retained Logic
3.3.9 - Milestones
14
USACE Requirements
®
3.4 - Project Schedule Submissions
3.4.1 - Preliminary Project Schedule Submission
» Submit within 15 calendar days of NTP
» Used for basis of Progress Payments during first 90 days after NTP
3.4.2 - Initial Project Schedule Submission
» Submit within 42 calendar days of NTP
» Used for basis of all remaining Progress Payments
» Once approved, becomes the Baseline Schedule
3.4.3 – Design Package Schedule Submission
» Extracted from the then current Preliminary, Initial, or Updated schedule
3.4.4 - Periodic Schedule Updates
» Required to support estimate upon which progress payments may be made
15
Project Schedule
®
3.4 - Project Schedule Submissions (continued)
3.4.5 - Standard Activity Coding Dictionary
• SDEF (ER 1-1-11, Appendix A)
• Exact structure is mandatory
Activity
Field
Code
Length
Description
1
WRKP
3
Workers per day
2
RESP
4
Responsible Patry (e.g. GC, Subcontractor, USACE)
3
AREA
4
Area of Work
4
MODF
6
Modification or REA number
5
BIDI
6
Bid Item (CLIN)
6
PHAS
2
Phase of Work
7
CATW
1
Category of Work
8
FOW1
10
Feature of Work (used up to 10 charactures in length)
9
FOW2
10
Feature of Work (used up to 20 charactures in length)
10
FOW3
10
Feature of Work (used up to 30 charactures in length)
16
USACE Requirements
®
3.5 - Submission Requirements
3.5.1 - Data CD’s
3.5.2 - Narrative Report
Description of activities on Critical Path
Description of current/anticipated problem areas
Description of delay factors and their impacts
Explanation of corrective actions taken
Communicate Contractors analysis of the schedule and its plans to compensate for any
problems
3.5.3 - Approved Change Verification
3.5.4 - Schedule Report
3.5.5 - Network Diagram
17
USACE Requirements
®
3.6 - Periodic Schedule Update Meeting
3.6.1 - Update Submission following Progress Meeting
3.6.2 - Status of Activities
Start and Finish Dates
Remaining Durations
Activity Percent Complete
Logic Change
Other Change
3.7 – Request For Time Extensions
3.7.1 - Justification of Delay
3.7.2 - Submission Requirements
3.7.3 - Additional Submission Requirements
18
Project Schedule
®
3.8 - Directed Changes
3.9 - Weekly Progress Meetings
3.10 - Ownership of Float
3.11 - Transfer of Schedule Data into RMS/QCS
19
Conclusion
®
The schedule communicates the Scope and Work Plan of the
project
It all starts with the project Baseline schedule
Periodic (monthly) updating is a must
Minimum configuration control must be followed to retain
validity of the schedule
The schedule documents what actually happened through-out the
life cycle of the project
The schedule is the primary tool used for documenting and
modeling time related impacts/delays
20