Transcript Key Findings - The Wall Street Journal
Dow Jones Infrastructure Summit 2009
Determining Market
Opportunity
for Public-Private
Partnerships
Harvey M. Bernstein, F.ASCE, LEED AP
Vice President
Industry Analytics, Alliances & Strategic Initiatives
McGraw-Hill Construction
New York, NY
Agenda
Defining
PPP
Transportation
The
Infrastructure Funding Gap
Credit Crisis and PPP
Current
PPP Market & Future Opportunities
PPP Adoption
Overall
and Success Factors
Key Takeaways
2 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Survey of State & Local
Transportation Officials
Survey
conducted between
January 20 and March 6, 2009
Study
PPP Definition: Design, Build, Finance, O&M
PPP Experienced Officials as defined by the
survey meet any of the following criteria:
– Have issued an RFP or pursued an unsolicited proposal
in the last ten years
– Are currently in the process of issuing an RFP or pursuing an
unsolicited proposal
– Have any plans to initiate a PPP in the next three years
3 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Experience Leads to Positive
Opinion of PPPs!
Overall Opinion of
Transportation PPPs
76%
54%
46%
15%
None gave
PPPs an
unfavorable
rating
Experience with
PPP
Favorable
9%
No Experience
with PPP
Indifferent
Unfavorable
4 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Defining PPP
5 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Two Main Types of PPPs
Tolled Concessions or
Monetizations
Availability Concessions
Private Sector …
– Same financing for new
asset as tolled
concessions
– Provides financing for new
asset
(for design, construction,
operation, maintenance)
payment for existing asset
– No upfront payment for
existing assets – financing
all upgrades, operations &
maintenance
Revenue directly to private sector
for the length of concession
– Private sector paid by public
sector based on performance
– Provides a large, up-front
Private Sector …
Longer concession terms
Shorter concession terms
6 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Typical PPP Risk Redistribution:
Major Benefit to the Public Sector
Financing
Acquisition
O&M
Insurance
Legislative
Public
Sector
Risks
Permitting
Planning
Private
Sector
Risks
Revenue
Risk
Design
Construction
7 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Termination
(Some)
More Education Required on
Ability to Shift Construction Risk
Risk
redistribution
is one of the
primary benefits to
the public sector
But
…ability to shift
risk ranked as a
relatively low factor
Factor Impacting Increase of PPP
Ability to
shift
construction
risk
39%
6%
PPP Experienced
PPP Non-Experienced
Education is
required!!
8 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
U.S. Transportation
Infrastructure PPP Market
Very Few PPPs to date
– Every State has its own PPP
contract and requirement
– Political environment not
favorable
Market Opportunity is immense
– More brownfield potential than any
other emerging PPP market
– Well publicized infrastructure
investment needs
“
From a demand
standpoint, there isn’t
a bigger marketplace on
the planet, regardless
of growth in Asia or
elsewhere.
”
— Manju Chandrasekhar
Vice President
Halcrow Consulting Business Group
9 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Lessons Learned for the U.S.
Market
Steps for U.S. to help PPP market
to mature
Create
Center of Knowledge and Expertise
on Federal or State Level
– Build a staff of PPP specialists, such as:
• UK – Federal Level
• Canada – Provincial Level
Develop
Overarching Government Mandate
10 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Dynamic Tolling HOT Lane
Capital Beltway (I-495), Virginia
VA
case study
11 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Transportation Infrastructure
Funding Gap
12 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Revenue Shortfall:
Stimulus Won’t Be Enough
ASCE 2008 Report Card for America’s Infrastructure: DNeeded Annually
for Highway Capital
Improvements
$186 Billion
Annual Spent
Highway Capital
Improvements
$70.3 Billion
Stimulus
only adds
$27.5 billion
one time to
highway
construction
13 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Major Revenue Sources for
Transportation Infrastructure
Gas
/ Diesel Taxes
Other
Taxes
Tolls
Proposed:
Vehicle Miles
Traveled (VMT) fee
Rare:
Monetization of
Existing Transportation
Assets
Multiple methods can be used in
combination
14 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
All Officials Believe Gas & Diesel Taxes
are Effective Funding Mechanisms
Experienced
Officials Believe
VMT Fees are
effective
65%
VMT Fees
39%
50%
52%
Gas & Diesel Taxes
46%
39%
Distance-Based Tolls
35%
27%
Sales Taxes, Fees
In February 2009, the National
Surface Transportation
Infrastructure Financing
Commission recommended
gradually replacing fuel tax
funding with Vehicle Miles
Traveled (VMT) fees by 2020.
15%
12%
Flat-Rate Tolls
Carbon Tax
8%
3%
15 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
PPP Experienced
PPP Non-Experienced
Perception of Effective Funding
Mechanisms Varies by Region
#1: Gas/Diesel Taxes
- 73% favorable
- Other regions:
average 46%
#1: VMT Fees
#1: Distance Based Tolls
- 60% favorable
- Other regions:
average 33%
- 62% favorable
- Other regions:
average 46%
#1: Gas/Diesel Taxes:
52% (about avg.)
#2: Sales Taxes: 50%
- 50% favorable
- Other Regions:
average 17%
16 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Adding a Toll versus Monetizing Assets
More
active resistance to tolls by those with
experience
– Politically unpopular
– Harder to pay for what used to be free
– Monetization of Assets is preferred by those with
experience over adding a toll
17 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
The Credit Crisis and PPP
18 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
How to Identify a PPP in
Today’s Financial Crisis
Criteria to Identify Projects for PPP
Given Financial Crisis
89%
PPP Experienced
67%
65% 64%
PPP Non-Experienced
58%
52%
19%
Excessive Traffic / Unsafe Conditions
Congestion
from Deteriorating
Infrastructure
Aging / Lifecycle
Tables
15%
Would Not
Recommend PPP
19 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Managed Toll Lane
LBJ Freeway (I-635), Texas
20 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Economic Crisis:
Consideration of PPPs
Consideration of PPPs despite
Financing Costs
Projects Limited to Only Urgent Needs
according to Public Officials
according to Public Officials
22%
10%
58%
42%
32%
Those with
experience:
report 81%
36%
Still being considered
Not limited
Neutral
Neutral
Not being considered
More limited
21 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Financial Crisis: Changing the
Types of PPPs Pursued
Before the Crisis
During the Crisis
Tolled Concessions or
Monetizations
Long concession terms
High ratio of Debt to Equity
(80/20)
Availability Concessions
Shorter concession terms
Lower ratio of Debt to Equity
(60/40)
After the Crisis
Higher Debt/Equity ratios
will return
Asset monetization likely to increase
due to underfunded local/state
government pensions
22 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Current PPP Market &
Future Opportunities
23 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
All Officials Have High Awareness of
Transportation PPP Projects
Awareness of PPPs
Three Most Cited
In Other
Areas/States
Within Own
Area/State
Indiana Toll Road:
Largest PPP in North America
Chicago Skyway: 4th largest
PPP in North America
King Coal Highway:
Featured on US FHWA PPP
site
70%
32%
24 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Planned PPPs in Next 3 Years
Occurring Most in South & West
% Planning a PPP
24%
13%
13%
39%
25 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
As Experience Increases, so
Does Interest in Future PPPs
Interest in PPPs
Officials with
PPP Experience
Officials without
PPP Experience
High Interest
8%
Some Interest
6%
Little Interest
48%
27%
65%
46%
26 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Large
percentage of
ambivalent
officials
suggests
opportunity
Larger Agencies
More Engaged in PPP
Agencies with
2009 budgets over $2 billion
PPP Engagement
by 2009 Budget Size
57%
57% current level of PPP
engagement
43% expected future PPPs
38%
15%
Perceive more challenges to PPP
adoption
71% believe federal funding
availability critical in spurring PPPs
<$500M
27 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
$500M to
$2B
Budget Size
Over $2B
PPP Adoption and
Success Factors
28 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Concern about Private Profits
Largest Obstacle to PPPs
Top Factors Discouraging PPP
– Top Three Factors:
• Unacceptable profits by private entities
• Fair tolling
• Political opposition
– Inexperienced officials believe private
entity may skimp on maintenance to boost
profits—demonstrates lack of
understanding PPP contracts
29 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Top Factors Leading to PPPs:
All Focus on Funding Concerns
Top Factors Having the Biggest Impact in
Increasing Number of PPPs
Inability of
department to fund
large projects
Lack of federal
financing
PPP provides
access to private
financing
77%
61%
65%
36%
62%
36%
PPP Experienced
Desire to accelerate
completion large
projects
62%
36%
30 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
PPP Non-Experienced
Public Transit PPP
Canada Line, Vancouver, Canada
31 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Overall Key Takeaways
32 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.
Overall Key Takeaways
Status
PPPs
Quo not sufficient
are well known, but not well understood
– More education of all stakeholders is required
The
more experience officials have,
the more they value PPPs
The
current economic downturn is not
perceived to be a major obstacle to PPPs
33 McGraw-Hill Construction Confidential. All information presented © McGraw-Hill Construction, 2009. All rights reserved.