Transcript Document
Project Management
Operations -- Prof. Juran
Outline
• Definition of Project Management – Work Breakdown Structure – Project Control Charts – Structuring Projects • Critical Path Scheduling – By Hand – Linear Programming • PERT – By Hand Operations -- Prof. Juran 2
Project Management
• A Project is a series of related jobs usually directed toward some major output and requiring a significant period of time to perform • Project Management is the set of management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project • An extreme case: Smallest possible production volume, greatest possible customization
Project Control Charts: Gantt Chart
Operations -- Prof. Juran 5
A pure project is where a self-contained team works full-time on the project Advantages: • The project manager has full authority over the project • Team members report to one boss • Shortened communication lines • Team pride, motivation, and commitment are high Disadvantages: • Duplication of resources • Organizational goals and policies are ignored • Lack of technology transfer • Team members have no functional area "home"
Functional Projects
President Research and Development Engineering Manufacturing Project A Project B Project C Project D Project E Project F Project G Project H Project I Example: Project “B” is in the functional area of Research and Development.
Functional Projects
Advantages: • A team member can work on several projects • Technical expertise is maintained within the functional area • The functional area is a “home” after the project is completed • Critical mass of specialized knowledge Disadvantages: • Aspects of the project that are not directly related to the functional area get short-changed • Motivation of team members is often weak • Needs of the client are secondary and are responded to slowly
Matrix Project Organization Structure
President Research and Development Engineering Manufacturing Marketing Manager Project A Manager Project B Manager Project C
Matrix Structure
Advantages: • Enhanced communications between functional areas • Pinpointed responsibility • Duplication of resources is minimized • Functional “home” for team members • Policies of the parent organization are followed Disadvantages: • Too many bosses • Depends on project manager’s negotiating skills • Potential for sub-optimization
Work Breakdown Structure
A hierarchy of project tasks, subtasks, and work packages Level Program 1 Project 1 Project 2 2 Task 1.1
Task 1.2
3 Subtask 1.1.1
Subtask 1.1.2
4 Work Package 1.1.1.1
Work Package 1.1.1.2
Network Models
• A project is viewed as a sequence of activities that form a “network” representing a project • The path taking longest time through this network of activities is called the “critical path” • The critical path provides a wide range of scheduling information useful in managing a project • Critical Path Method (CPM) helps to identify the critical path(s) in the project network
Prerequisites for Critical Path Method
A project must have: •well-defined jobs or tasks whose completion marks the end of the project; •independent jobs or tasks; •and tasks that follow a given sequence.
Types of Critical Path Methods
• CPM with a Single Time Estimate – Used when activity times are known with certainty – Used to determine timing estimates for the project, each activity in the project, and slack time for activities • Time-Cost Models – Used when cost trade-off information is a major consideration in planning – Used to determine the least cost in reducing total project time • CPM with Three Activity Time Estimates – Used when activity times are uncertain – Used to obtain the same information as the Single Time Estimate model and probability information
CPM with Single Time Estimate
1. Activity Identification 2. Activity Sequencing and Network Construction 3. Determine the critical path – From the critical path all of the project and activity timing information can be obtained
House-Building Example
Activity Description
Activity A Build foundation Activity B Build walls and ceilings Activity C Build roof Activity D Do electrical wiring Activity E Put in windows Activity F Put on siding Activity G Paint house
Predecessors
— A B B B E C, F
Duration (days)
5 8 10 5 4 6 3 Operations -- Prof. Juran 16
Managerial Problems
•Find the minimum number of days needed to build the house.
•Find the “critical path”.
•Find the least expensive way to finish the house in a certain amount of time.
•Study the possible effects of randomness in the activity times.
Operations -- Prof. Juran 17
0 Start A 5
Activity-on-Arc Network
1 3 F 6 4 E 4 G 3 B 8 C 10 5 End D 5 2
Operations -- Prof. Juran 18
0 Start A 5
Method 1: “By Hand”
1 3 F 6 4 E 4 G 3 B 8 C 10 D 5 2 5 End
Operations -- Prof. Juran 19
Procedure
• Draw network • Forward pass to find earliest times • Backward pass to find latest times • Analysis: Critical Path, Slack Times • Extensions (really hard!): – Crashing – PERT Operations -- Prof. Juran 20
CPM Jargon
Every network of this type has at least one critical path, consisting of a set of
critical activities.
In this example, there are two critical paths: A-B-C-G and A-B-E-F-G.
1 0 Star t A 5 B 8
Operations -- Prof. Juran
2 3 F 6 E 4 C 10 D 5 4 G 3 5 End
21
Conclusions
The project will take 26 days to complete.
The only activity that is not critical is the electrical wiring (Activity D).
Operations -- Prof. Juran 22
Time-Cost Models
• Basic Assumption: Relationship between activity completion time and project cost • Time Cost Models: Determine the optimum point in time-cost tradeoffs – Activity direct costs – – Project indirect costs Activity completion times
Crashing Parameters
Activity
Build foundation Walls and ceilings Build roof Electrical wiring Put in windows Put on siding Paint house
Cost per Day to Reduce Duration
$30 $15 $20 $40 $20 $30 $40
Maximum Possible Reduction (Days)
2 3 1 2 2 3 1 What is the least expensive way to finish this project in 20 days? (This is hard!) Operations -- Prof. Juran 24
CPM with Three Activity Time Estimates Activity A B C D E F G Optimistic 3 5 9 3 2 3 2 Most Likely 5 8 10 5 4 6 3 Pessimistic 7 11 11 7 6 9 4 Operations -- Prof. Juran 25
Expected Time Calculations
1 2 3 4 5 6 7 8 A B C D E Activity Optimistic Most Likely Pessimistic Expected A 3 5 7 5 B C D E F G 5 9 3 2 3 2 8 10 5 4 6 3 11 11 7 6 9 4 8 10 5 4 6 3 F G
=(B2+C2*4+D2)/6
Expected Time = Opt.
Time + 4(Most Likely Time) + Pess.
Time 6 Operations -- Prof. Juran 26
Expected Time Calculations
5 6 7 8 1 2 3 4 A B C D E Activity Optimistic Most Likely Pessimistic Expected A B C 3 5 9 5 8 10 7 11 11 5 8 10 D E F G 3 2 3 2 5 4 6 3 7 6 9 4 5 4 6 3 F G
=(B2+C2*4+D2)/6
Note: the expected time of an activity is not necessarily equal to the most likely time (although that is true in this problem).
Operations -- Prof. Juran 27
1 3 F 6 4 A 5 G 3 E 4 0 Start B 8 C 10 5 End D 5 2
The sum of the critical path expected times is the expected duration of the whole project (in this case, 26 days).
Operations -- Prof. Juran 28
What is the probability of finishing this project in less than 25 days?
Operations -- Prof. Juran Z = D - T E cp 2 29
Estimated Activity Variance 2
Pessimisti c
Optimistic
6 2 1 2 3 4 5 6 7 8 A B C D E F Activity Optimistic Most Likely Pessimistic Expected Variance A 3 5 7 5 0.4444
B C 5 9 8 10 11 11 8 10 1.0000
0.1111
D E 3 2 5 4 7 6 5 4 0.4444
0.4444
F G 3 2 6 3 9 4 6 3 1.0000
0.1111
G
=((D2-B2)/6)^2
Operations -- Prof. Juran 30
Activity Optimistic Most Likely Pessimistic Expected Variance Criticial Path 1 Criticial Path 2 A 3 5 7 5 0.444
0.444
0.444
B 5 8 11 8 1.000
1.000
1.000
C D E F G 9 3 2 3 2 10 5 4 6 3 11 7 6 9 4 10 5 4 6 3 0.111
0.444
0.444
1.000
0.111
Expected Variance St Dev 0.444
1.000
0.111
26.000
3.000
1.732
0.111
0.111
26.000
1.667
1.291
2
= 3
Sum the variances along the critical path. (In this case, with two critical paths, we’ll take the one with the larger variance.) Operations -- Prof. Juran 31
Z = D T
E cp 2
= 25 26 3 = - 0.5774
p(Z < -.156) = .438, or 43.8 % (NORMSDIST(-.156) There is a 28.19% probability that this project will be completed in less than 25 days.
Operations -- Prof. Juran 32
CPM Assumptions/Limitations
•Project activities can be identified as entities (there is a clear beginning and ending point for each activity).
•Project activity sequence relationships can be specified and networked. •Project control should focus on the critical path.
•The activity times follow the beta distribution, with the variance of the project assumed to equal the sum of the variances along the critical path.
0 Start A 5
Method 2: Excel Solver
(Linear Programming)
1 3 F 6 4 E 4 G 3 B 8 C 10 D 5 2
Operations -- Prof. Juran
5 End
34
Procedure
• Define Decision Variables • Define Objective Function • Define Constraints • Solver Dialog and Options • Run Solver • “Sensitivity” Analysis: Critical Path, Slack • Extensions: – Crashing (not too bad) – PERT (need simulation, not Solver) Operations -- Prof. Juran 35
LP Formulation
Decision Variables
We are trying to decide when to begin and end each of the activities.
Objective
Minimize the total time to complete the project.
Constraints
Each activity has a fixed duration.
There are precedence relationships among the activities.
We cannot go backwards in time.
Operations -- Prof. Juran 36
Formulation
Decision Variables
Define the nodes to be discrete events. In other words, they occur at one exact point in time. Our decision variables will be these points in time.
Define t i to be the time at which node i occurs, and at which time all activities preceding node i have been completed.
Define t 0 to be zero.
Objective
Minimize t 5 .
Operations -- Prof. Juran 37
Formulation
Constraints
There is really one basic type of constraint. For each activity x, let the time of its starting node be represented by t jx and the time of its ending node be represented by
t
kx . Let the duration of activity x be represented as d x . For every activity x,
t kx
t jx
d x
For every node i,
t i
0 Operations -- Prof. Juran 38
Solution Methodology
A B C D E F G H 1 2 3 4 5 6 13 14 15 16 17 18 7 8 9 10 11 12 t0 t1 t2 t3 t4 t5 0 1 1 1 1 1 1 t0 t1 t2 t3 t4 t5 A -1 1 0 0 0 0 B 0 -1 1 C 0 0 -1 0 0 0 1 0 0 D 0 E 0 F 0 G 0 0 -1 0 -1 0 0 0 0 0 1 -1 0 0 0 1 -1 1 0 0 1 I
=G6
J K
0 Start
L
A 5 1 B 8
M
E 4 =SUMPRODUCT($B$6:$G$6,B12:G12)
1 >= 5 0 >= 8 0 >= 10
2
0 >= 5 0 >= 4 0 >= 6 0 >= 3
3 C 10
N
F 6 D 5
Operations -- Prof. Juran O 39 P
4 G 3 5 End
Solution Methodology
The matrix of zeros, ones, and negative ones (B12:G18) is a means for setting up the constraints. The sumproduct functions in H12:H18 calculate the elapsed time between relevant pairs of nodes, corresponding to the various activities. The duration times of the activities are in J12:J18.
Operations -- Prof. Juran 40
Operations -- Prof. Juran 41
Optimal Solution
A B C D E F G H I J 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 t0 t1 t2 t3 t4 t5 0 26 5 13 17 23 26 t0 t1 t2 t3 t4 t5 A -1 1 B 0 -1 1 C 0 D 0 0 0 -1 0 -1 0 0 0 0 0 0 1 0 0 0 0
5 8 10
>= 5 >= 8 >= 10 1 13 >= 5 E 0 F 0 G 0 0 -1 0 0 0 0 1 -1 0 0 1 -1 0 0 1
4 6 3
>= 4 >= 6 >= 3 K L
1 0 S ta r t A 5 B 8 2
M
E 4 3 C 1 0
N
F 6 D 5
O
4 G 3 5 E n d
P Operations -- Prof. Juran 42
CPM Jargon
Any activity for which
t kx
t jx
d x
is said to have slack time, the amount of time by which that activity could be delayed without affecting the overall completion time of the whole project. In this example, only activity D has any slack time (13 – 5 = 8 units of slack time).
Operations -- Prof. Juran 43
CPM Jargon
Any activity x for which
t kx
t jx
d x
is defined to be a “critical” activity, with zero slack time. Operations -- Prof. Juran 44
Excel Tricks: Conditional Formatting
K A B C D E F G H I J 6 14 15 16 17 18 7 8 9 10 11 12 13 1 2 3 4 5 t0 t1 t2 t3 t4 t5 0 26 5 13 17 23 26 t0 t1 t2 t3 t4 t5 A -1 1 0 B 0 -1 1 0 0 0 0 0 0 C 0 D 0 0 -1 0 -1 0 0 1 0
5 8
>= 5 >= 8 0
10
>= 10 1 13 >= 5 E 0 F 0 G 0 0 -1 0 0 0 0 1 -1 0 0 1 -1 0 0 1
4 6 3
>= 4 >= 6 >= 3
0 S ta r t A 5
L
1 B 8 2
M
E 4 3 C 1 0
N
F 6 D 5
O
4 G 3
P
5 E n d
Operations -- Prof. Juran 45
Critical Activities: Using the Solver Answer Report
Constraints
Cell Name
$H$12 A $H$13 B $H$14 C $H$15 D $H$16 E $H$17 F $H$18 G
Cell Value Formula Status
5 $H$12>=$J$12 Binding 8 $H$13>=$J$13 Binding 10 $H$14>=$J$14 Binding 13 $H$15>=$J$15 Not Binding 4 $H$16>=$J$16 Binding 6 $H$17>=$J$17 Binding 3 $H$18>=$J$18 Binding
Slack
0 0 0 0 0 0 8 Operations -- Prof. Juran 46
House-Building Example, Continued
Suppose that by hiring additional workers, the duration of each activity can be reduced. Use LP to find the strategy that minimizes the cost of completing the project within 20 days.
Operations -- Prof. Juran 47
Crashing Parameters
Activity
Build foundation Walls and ceilings Build roof Electrical wiring Put in windows Put on siding Paint house
Cost per Day to Reduce Duration
$30 $15 $20 $40 $20 $30 $40
Maximum Possible Reduction (Days)
2 3 1 2 2 3 1 Operations -- Prof. Juran 48
Managerial Problem Definition
Find a way to build the house in 20 days.
Operations -- Prof. Juran 49
Formulation
Decision Variables
Now the problem is not only when to schedule the activities, but also which activities to accelerate. (In CPM jargon, accelerating an activity at an additional cost is called “crashing”.)
Objective
Minimize the total cost of crashing.
Operations -- Prof. Juran 50
Formulation
Constraints
The project must be finished in 20 days.
Each activity has a maximum amount of crash time.
Each activity has a “basic” duration. (These durations were considered to have been fixed in Part a; now they can be reduced.) There are precedence relationships among the activities.
We cannot go backwards in time.
Operations -- Prof. Juran 51
Formulation
Decision Variables
Define the number of days that activity x is crashed to be R x . For each activity there is a maximum number of crash days
R
max, x Define the crash cost per day for activity x to be C x
Objective
Minimize Z =
x
7 1
R x C x
Operations -- Prof. Juran 52
Formulation
Constraints
For every activity x, For every activity x, For every node i,
t kx
t jx
d x
R x R x
R
max,
x t i
0 Operations -- Prof. Juran 53
Solution Methodology
A B C D E F G H I J K L 7 8 9 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 t0 t1 t2 t3 t4 0 5 13 17 23 26
=SUMPRODUCT($B$6:$G$6,B12:G12)
t0 t1 t2 t3 t4 A -1 1 F 0 G 0 0 0 0 B 0 -1 1 C 0 0 -1 D 0 E 0 0 -1 0 -1 0 0 0 0 0 0 1 -1 0 0 0 1 0 0 1 -1 30 t5 20 <- t5 0 0 0 1 0 0 1
=SUMPRODUCT(M12:M18,O12:O18)
5 >= 8 >= 10 >= 13 >= 4 >= 6 >= 3 >= Max Completion Time Improved Duration 4 8 10 5 4 6 3
=L12-M12 0 Start A 5 1 B 8 2 E 4
Basic Duration 5 8 10 5 4 6 3
3 C 10
M
F 6 D 5 4
N
G 3 5 End
O Crash Time Max Crash Cost/Time 1 0 0 0 0 0 0 2 3 1 2 2 3 1 $ 30 $ 15 $ 20 $ 40 $ 20 $ $ 30 40 Operations -- Prof. Juran 54
Solution Methodology
G3 now contains a formula to calculate the total crash cost. The new decision variables (how long to crash each activity x, represented by R x ) are in M12:M18.
G8 contains the required completion time, and we will constrain the value in G6 to be less than or equal to G8.
The range J12:J18 calculates the revised duration of each activity, taking into account how much time is saved by crashing. Operations -- Prof. Juran 55
Operations -- Prof. Juran 56
Optimal Solution
A B C D E F G H I J K 7 8 9 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 t0 t1 t2 t3 t4 0 3 t0 t1 t2 t3 t4 A -1 1 0 B 0 -1 1 C 0 0 -1 D 0 E 0 F 0 G 0 0 -1 0 -1 0 0 0 0 0 0 0 0 1 -1 0 0 0 1 0 0 1 -1 145 t5 8 11 17 20 20 <--
=SUMPRODUCT($B$6:$G$6,B12:G12)
t5 0 0 0 1 0 0 1 3 5 9
=SUMPRODUCT(M12:M18,O12:O18)
>= >= >= 12 >= 3 6 3 >= >= >= Max Completion Time Improved Duration 5 3 6 3 3 5 9
0 S ta r t =L12-M12 A 5 1 B 8 2
L
E 4
Basic Duration 5 8 10 5 4 6 3
3 C 1 0
M
F 6 D 5 4
N
G 3 5 E n d
O Crash Time Max Crash Cost/Time 2 3 1 0 1 0 0 2 3 1 2 2 3 1 $ $ $ $ $ $ $ 30 15 20 40 20 30 40 Operations -- Prof. Juran 57
Crashing Solution
Basic Duration Crash Time Improved Duration Cost/Time A 5 2 3 $30 B C D 8 10 5 3 1 0 5 9 5 $15 $20 $40 E F G 4 6 3 1 0 0 3 6 3 $20 $30 $40 Cost $60 $45 $20 $- $20 $- $- $145 Operations -- Prof. Juran 58
Crashing Solution
It is feasible to complete the project in 20 days, at a cost of $145.
1 3 F 6 4 0 Star t A 3 B 5 E 3 C 9 G 3 5 End D 5 2
Operations -- Prof. Juran 59
Summary
• Definition of Project Management – Work Breakdown Structure – Project Control Charts – Structuring Projects • Critical Path Scheduling – By Hand – Linear Programming • PERT – By Hand Operations -- Prof. Juran 60