Transcript Chapter 1
Allocating Resources to the Project Expediting a Project Fast-Tracking a Project Resource Loading Allocating Scare Resources 1 Introduction • Projects Compete With One Another for Resources – resources that are not consumed – resources that are consumed • Goal of Resource Allocation is to Optimise Use of Limited Supply • Requires making trade-offs – time constrained – resource constrained 2 EXPEDITING A PROJECT • The Critical Path Method • Probabilistic Activity Durations • Fast-Tracking a Project 3 The Critical Path Method • Normal Duration Estimates • Normal Costs • Crash Duration Estimates • Crash Costs • Crash Cost Per Day Normal Duration - Crash Duration Crash Cost - Normal Cost 4 Probabilistic Activity Durations • Three time estimates made for both normal resource loading and crash resource loading • Variance of normal activity may be different than variance of crash time 5 Fast-Tracking a Project • Used Primarily in Construction Industry • Building phase started before design and planning phases completed (Scottish Parliament) • Particularly appropriate when large proportion of work is routine 6 Resource Loading • Amount of specific resources that are scheduled for use on specific activities or projects at specific times. • Usually a list or table. 7 Use of Software • Begin with Pert/CPM Schedule • Activities examined period by period and resource by resource • In cases where demand for resource exceeds supply, tasks considered one by one and resources assigned to these tasks based on priority rules 8 Some Priority Rules • As soon as possible • As late as possible • Shortest task duration first • Minimum slack first • Most critical followers • Most successor • Most resources first 9 Resource Loading/Leveling and Uncertainty • What about – Workers getting sick? – Task not ready when worker is ready? – Change orders? 10 Pseudo activities • Used to link several project together • Have duration but do not require any resources • This approach allows a set of projects to be dealt with as though it were a single project – use of MSP’s resource loading and leveling charts and tables 11 Bottle Necks • • • • • Identify the constraint Exploit the constraint Subordinate everything else Elevate the constraint Go back to step 1 12 Goldratt’s Critical Chain What is it? • Tackles the inherent uncertainty in managing projects • Systems approach 13 Goldratt’s Critical Chain • Similar issues that trouble people about working on projects regardless of type of project – – – – unrealistic due dates too many changes resources and data not available unrealistic budget • These issues/problems related to need to make trade-offs • To what extent are these problems caused by human decisions and practices? 14 Observations • Average Completion Times • Implications of Assuming Known Activity Times • Worker Time Estimates • Impact of Inflated Time Estimates • Student Syndrome 15 Common Chain of Events • Underestimate time needed to complete project • Project team members inflate time estimates • Work fills available time • Safety time misused • Misused safety time results in missed deadlines 16 Common Chain of Events concluded • Poor multitasking increases task durations • Uneven demand on resources also results due to poor multitasking • More projects undertaken to ensure all resources fully utilized • More projects further increases poor multi tasking 17 Reversing the Cycle • Reduce number of projects assigned to each individual • Schedule start of new projects based on availability of bottleneck resources • Reduce amount of safety time added to individual tasks and then add some fraction back as project buffer – activity durations set so that there is a high probability the task will not be finished on time 18 The Critical Chain • Longest chain of consecutively dependent events – considers both precedence relationships and resource dependencies • Project Buffer • Feeding Buffer 19 Critical Chain Rules 1. Projects should not be started ASAP 2. Tasks and resources should not be precisely scheduled during planning 3. Adding explicit buffers into projects makes them run faster 20 Buffer Management Taking the appropriate action No action needs to be taken, consumption of the buffer is expected Identify the tasks consuming the buffer, develop a recovery plan Implement recovery plan Use information on task performance for future improvement activities 21 Why not start projects ASAP? All three projects started ASAP • Constant resource shuffling • Priorities not synchronised • All projects are delayed Start dates are staggered • Resources stay focused • Tighter synchronisation • All projects finish faster • More projects can be done 22 Why not schedule precisely? Schedules set in planning • Uncertainties are unavoidable • Wanting to be reliable, people add safeties into estimates • Safeties get wasted in execution Schedules set in Execution • Estimates are used only to plan projects • Task schedules determined in execution, when tasks are closer to being started 23 How safety or contingency time is wasted • Task dependency – Gains are wasted and delays are passed on • Student Syndrome / Cherry Picking – Starting work is delayed • Parkinson’s Law – “Work expands to fill the time available” • Multi Tasking – A resource has to divide its time between two or more tasks 24 Benefits • • • • • • • PROJECTS: coming in on-time completing within budget completing without cutting scope reduced project lead-times Improved efficiency 25 A resource allocation example Looking at the example of Breakfast in Bed there can be seen a number of different tasks to perform, all of which have a resource implication. Activity Effort Duration (person-minutes) (minutes) Butter toast 1 1 Pour orange juice 1 1 Boil egg 0 4 Slice bread 1 1 Fill pan with water 1 1 Bring water to boil 0 3 Toast bread 0 2 Take loaded tray to bedroom 1 1 Fetch tray, plates, cutlery 1 1 Time resource estimates for "Breakfast in Bed" project 26 Often estimates of the time taken are quite inaccurate 27 Plan with Resource Allocation 28 Revised Plan with Resource Allocation 29 Plan with Levelled Resources and Warm Toast 30