Transcript Slide 1

Water Distribution Optimization:
Taking SCADA One Step
Forward: A Case Study
Chuck Weber - WaterOne
Simon Bunn – Derceto Inc
1950’s – 1970’s Control room
PLC and RTU provide local control
1970’s : Mixed auto/manual systems
1980’s : SCADA systems appear
1990’s :Historical Databases arrive
1990-2000 Smart Instruments arrive





WaterOne is a quasi-municipal agency that provides water to
more than 400,000 individuals
WaterOne serves residential and commercial accounts in 16
cities in the Johnson County area. WaterOne serves
approximately 135,000 customers.
WaterOne has nearly 3,000 miles of transmission and
distribution mains, equal to the distance from Kansas City to
Seattle.
WaterOne's service area covers more than 270 square miles.
WaterOne’s current treatment capacity is 180 millions gallons
per day.
Modern UCOS Scada System


Single control room for treatment and distribution
Installed in 1991, upgraded 2006
What next after Scada?
Decision Support Systems
What to optimize?
Energy cost minimization is a good target, as it is one of the highest
costs in producing the “next gallon of water.”
"The more than 60,000 water systems and 15,000 wastewater
systems in the United States are among the country’s largest energy
consumers, using about 75 billion kWh/yr nationally – 3 percent of
annual U.S. electricity consumption."
Electric Power Research Institute,
Energy Audit Manual for Water/Wastewater Facilities,
(Palo Alto: 1999), Executive Summary.
Electricity Use by WaterOne
Water Treatment
(Backwash/Transfer
Pumps)
10%
Transmission
Pumps
46%
Intake/Pretreatment
Pumps
26%
Distribution Pumps
14%
Offices
4%
Energy and Demand Charges

Pricing is based on two components, energy use in kWh and
demand in kW
Car Analogy for kWh and kW


kW is like the speed that is measured
by a speedometer
kWh is the distance measured by the
odometer
Electricity Supply tariffs

Kansas City Power & Light (KCPL)



Kansas City Board of Public Utilities (KCBPU)






Flat kWh tariff applies 24 hours day, 365 days year
Flat demand charge, 24 hours a day, 365 days year
Flat kWh tariff applies 24 hours day, 365 days year
Demand charge only applies 10 hours/weekday with monthly peak
and 70% of highest summer peak setting winter charge (effectively
a 12 month ratchet clause)
Almost no incentive at all for shifting electrical load
No options for time-of-use or real-time pricing
Last KCPL tariff structure changes were made10 years ago
Market is unlikely to change or deregulate in the mid term
Solving the energy equations
Numerically impossible to solve, but the
following techniques have been attempted





Localized optimization at each pump station using profiling or
time triggers
Expert Systems using cascading rules
Advanced techniques using Genetic Algorithms
Multi-Objective Polynomial Systems (MOPS)
Dynamic Programming with Stochastic analysis
All still make considerable assumptions and do
not achieve optimality
A 2001 AWWA report said “the market is
waiting for an off-the-shelf solution”
A New Customized-Off-The-Shelf tool


Over the last 4 years, Derceto Aquadapt has implemented energy
cost optimization systems with leading US water utilities
Five key cost reduction techniques were employed






Electrical load shifting in time, to maximize utilisation of low cost kWh
tariff blocks (time-of-use tariffs)
Peak electricity kW demand reduction
Energy efficiency improvements from pumps and pumping plants.
Utilization of lowest production and chemical cost sources of water.
Utilization of shortest path between source and destination
WaterOne benefited primarily from peak demand reduction and
lowest cost source selection
Key Energy Management Modules
Operator Panel
OPC
SCADA Interface
PC on
LAN
Current day / real-time
WaterOne UCOS
SCADA System
Data Cleaner
Primary Database
Aquadapt
Primary Database
(Live Server)
Operations Simulator
Application Manager
PC on LAN
Optimizer
Aquadapt
Back-up
Backup Database
(Historical Server)
Dashboard
PC on
LAN
Project Timeline






Feasibility Study - June 2004 to August 2004
Detailed Design - September 2004 to April 2005
Configuration and Testing - July 2005 to Mar 2006
Delivery, Implementation and Site Testing - April/May 2006
Had to be ready in time for peak summer demand otherwise
majority of savings would be lost for 2006/07
WaterOne created and maintained an audit tool to measure
savings on a monthly basis. This is a sophisticated analysis tool




Uses formulation of kW versus MGD from four previous years
Created non-linear functions to calculate kW at each major point
Allowed for changes in tariff in future years to be incorporated
Maintenance, Enhancement and Support contract started in
June 2006 with latest Aquadapt version 5.5 rolled out in 2008
0
Observed With Derceto
Day
Expected Without Derceto
31-May
30-May
29-May
28-May
27-May
26-May
25-May
24-May
Max Peak-Time kW (May 2006)
23-May
22-May
21-May
20-May
19-May
18-May
17-May
16-May
15-May
14-May
13-May
12-May
11-May
10-May
9-May
8-May
7-May
6-May
5-May
4-May
3-May
2-May
1-May
Sum of kW at WTP and Intakes
Peak Demand Reductions
5 MW Reduction
20000
18000
16000
14000
12000
10000
8000
6000
4000
2000
0
Observed With Derceto
Day
Expected Without Derceto
30-Jun
29-Jun
28-Jun
27-Jun
26-Jun
25-Jun
24-Jun
23-Jun
22-Jun
21-Jun
20-Jun
19-Jun
18-Jun
17-Jun
16-Jun
15-Jun
14-Jun
13-Jun
12-Jun
11-Jun
10-Jun
9-Jun
8-Jun
7-Jun
6-Jun
5-Jun
4-Jun
3-Jun
2-Jun
1-Jun
Sum of kW at WTP and Intakes
Even after a major Pipe-break
Max Peak-Time kW (June 2006)
25000
Woodson Inflow Valve out of Service
20000
Out of Derceto
Control
15000
10000
5000
Results to date – Electricity $ savings









First month of operation May 2006, saved $90,000
First year of operation May 06 to April 07 saved $565,000
First six months of 2007/08 saved $553,000
Total of $1,118,000 saved in 18 months of operation
Reduced greenhouse gas emissions by 4800 tons/year
Other impacts
Has required changes in operation, but no additional hardware
or instrumentation was required
Operators were involved all the way through the process and
had valid concerns which needed to be addressed
Ongoing program of training and product enhancement is
helping culture change and acceptance
Aquadapt is now being used to identify areas where further
savings can be made
Conclusions







The considerable investment in a Scada system is often hard to
justify financially, but it is an essential tool
Utilization of the data and interfaces presented by a Scada
system in areas such as planning and operations optimization
can provide additional financial benefits
Even in an energy market that looked unfriendly to energy
optimization, significant benefits were achieved
Buying advanced software “off-the-shelf” reduces risk
Use robust systems to measure the benefits to avoid doubt
Operators need to be involved from start to finish, they know the
treatment and distribution systems best
This is just one step in the path to operations optimization, keep
an eye on costs and benefits in all areas to best serve your
customers
Questions?