Transcript Document

Client: City of Pittsburgh, Brighton Heights Community
Objectives: Develop a pedestrian/bicycle bridge reconnecting Brighton
Pier Design: 14’x4’ with 2’ radius rounded edges. #6 reinforcement bars and #4 tie bars
placed 4” from pier edges. There will be four total piers. The two piers on the West side of
the bridge will be 20’ high while the piers on the East side will be 10’ and 5’ high.
Heights to Riverview park.
Location: Brighton Heights, Pittsburgh, Pennsylvania. Will connect Davis Avenue to
Riverview Park spanning 396’ over Woods Run Avenue at approximately 80’ high.
Recommended soil testing:
•
•
•
•
•
•
Scope of Work:
Structural Design
Geotechnical preliminary designs and recommendations
Project management plan
Cost estimate
Project Schedule
Bridge History: Originally
constructed in 1898, the Davis
Avenue Bridge would be
rehabilitated in 1986 before
Aerial view of the site showing the proposed
being closed to traffic in 2001 and
bridge site.
eventually demolished in 2009.
•
•
•
•
•
AutoCAD profile view of proposed bridge design.
AutoCAD cross sectional view of design.
AutoCAD plan view of pier design
Estimate: Carried out a detailed estimate for each part of the project.
Top- Detailed estimate of steel superstructure
Bottom- Detailed superstructure of pier and abutment work
Overview: Steel arch bridge consisting primarily of double angles. The two sides of
the arch will be connected creating an 11’ width between them.
Loading guidelines: ASHTO LRFD 2012 Bridge Design Specifications 6th edition
along with ASHTO LRFD Guide Specifications for Pedestrian
Bridges (2009)
Truss member design: Using a STAAD model of the bridge, load cases were
entered and axial forces were found in each member. Girders and
wind columns were treated as beam columns.
Bracing design: Again using the STAAD model wind loading was applied to the
bridge. Axial loads were found and members were selected. All diagonal members
were treated as pure axial loaded members while all other members were treated as
beam columns.
Transverse bottom cord design: Designed in order to provide adequate
stability and force transfer between the two arches and into the foundation.
Connections: Typical connections were designed for bolt strength, block shear,
hole bearing, and slip. Eight connections commonly used in the bridge design were
created.
Floor beams: Floor beams were designed to carry the moment from the
combined live, dead, and snow load.
Atterberg limits
Triaxial testing
Unconfined compression
Consolidation
Direct Shear
Hydraulic Conductivity
Background: Supplied by Composite Advantage in Dayton, Ohio, the fiberglass
decking provides the necessary structural stability while provided numerous benefits
over a concrete decking.
Benefits:
• Light Weight- Weighing anywhere between 5 to 10 psf, the fiberglass deck weighs
only 10 to 20 percent of an equivalent concrete deck.
• Durability- The wearing surface can protect against corrosion for over 50 years
with minimal maintenance.
• Accelerated construction- The prefabricated panels can be placed using lightweight
machinery at a much quicker rate than that of a concrete deck.
Our Design: The Brighton Heights
Pedestrian Bridge will utilize a 4” deep
fiberglass decking. There will be 12 panels
8’x32’ and the final panel will be 8’x12’. The
deck will include a wearing surface along with
prefabricated curbs. Connections will be
bolted to the bottom and clip onto the floor
beams spaced every 8 feet. The use of
fiberglass will enable the decking to be placed
in a matter of days, speeding up construction
time, decreasing the labor cost, and allowing
Woods Run Avenue to reopen quickly.
Top- Picture of Composite Advantage fiberglass deck
Bottom- Diagram of typical deck to floor beam connection
Below- Full project schedule
Members of Allegheny Bridge Consultants would like to thank the following people who aided in our design
.
process: Dr. John Oyler, Mr. Patrick Miner, Dr. Kent Harries, Professor Joseph Beck, Dr. Dan Budny, Dr. Karl
Lewis, Andrew Loff and associates at Composite Advantage, community members of the Brighton Heights
Community Forum