No Slide Title
Download
Report
Transcript No Slide Title
4th ST Workshop
Chamonix, 30 January - 2 February 2001
Control System Implementation and Follow-up
within the CV Contracts for the LHC
Y. Body, H. Jena, M. C. Morodo
ST-CV
Summary
CV control systems: an introduction
Implementation within industrial contracts
Detailed design and approval procedures
On-site installation and acceptance procedures
Conclusions
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
CV Control Systems
The requirements for the LHC era:
To integrate our existing heterogeneous
environment --->
Openness
To cope with the geographical dispersion of our
processes --->
Networking
To provide the operation and maintenance teams
with well-adapted tools --->
Powerful local
supervision
The strategy:
A fully industrial standard control system architecture is taken as a reference
Industrial approach
Development and implementation of the particular solutions in collaboration
with the industry ---> Contracts
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Industrial Approach
Trouble Diagnosis
Post-mortem analysis
Web-access
Layer 4: Data handling and web supervision
Layer 3: TCR remote supervision
Process control and
supervision
Standardization of
interfaces
Flexibility
Process-customized
solutions
Reference Data Base
(for TCR data remote configuration)
Technical Data Server
Windows NT Workstations
SCADA: Wizcon
Layer 2: Local supervision
Reliability
Process regulation
Layer 1: Acquisition and regulation
4th ST Workshop
Availability
Ethernet TCP/IP
CERN technical data
monitoring
Data coherence
Archiving station
PLC: Schneider / Siemens
Profibus DP
Data archiving and
web-based
supervisory tools
Maintainability
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Project and Contract Phases
The Feasibility and Specification stages:
Feasibility study
Engineering Design Review
Market Survey
Technical Specification
Call for Tenders
Contract Negotiation
Contract is signed
The Detailed Design, Implementation and Validation stages:
Development
Implementation
Testing and validation
Provisional acceptance
Operational system
Refining and adjustments
Guarantee period
Final acceptance
Contract disengagement
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Collaboration with the Industry
Partnership CERN-Industry: the win-win relation
CERN project resources
Technical
Specification
Contract
follow-up
Contract
External Contractor project resources
The basis: Having a firm understanding of our own needs
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Collaboration with the Industry
Partnership CERN-Industry: the win-win relation
Planning and
resources
allocation
Technical
Specification
Technical
CERN project resources
CERN
CERN privileged
responsibilities
spokesperson
solution
Requirements
to be fulfilled
Contract
follow-up
External
External
Contractor
Contractor
privileged
External Contractor responsibilities
project resources
spokesperson
CERNContractor
Contract
collaboration
strategy
Work and
resources
organization
The basis: Having a firm understanding of our own needs
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Contract Follow-up
The Contract follow-up assures the Conformity with the Requirements
Technical aspects
Emphasis in validation tests and
acceptance procedures
Project Documentation
Work procedures
State- of-the-art of control engineering
Safety issues, all over design and
implementation
Operational tools
International Standards
Flexible and well adapted to the CV
processes operation, user-friendly
Complete, clear, concise
In-house knowledge basis
Future system maintainability and
evolution
IEC 1131-3 PLC programming method
IEC 61506 Industrial-process control doc
IEC 61508 Functional safety
--> Building control systems to be operational for 10-15 years!!!
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Detailed Design and Approval Process
Specification
Contractor’s
Critical points :
Proposal
Meetings
Discussions
Search for
Feasibility
Availability
Costs
Time
yes
Approval
Implementation
common
solutions
no
CERN’s
Proposal
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Detailed Design and Approval Process:
Example
Specification
Implementation
Handling
Availability
Costs
Control
system with
redundant
architecture
4th ST Workshop
Siemens S7
S7- 400 H
Further improvement
Schneider
TSX 57
Premium
Backup
Y. Body, H. Jena, M.C. Morodo
Schneider
Premium
with
redundant
Power
supply and
network
CERN ST-CV
Design and Implementation Phases:
Document Handling
CERN
Contractor
Process description
Functional Analysis
Modifications - Approval
Electrical schemas and Layouts
Modifications - Approval
Factory Tests Document
Factory Tests
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Document Handling: Contract Roles
Contractor
A
Wiring diagram
Project Leader
UIAOxxx
ghg
hjhjh
Subcontractor
1
A
Project Leader
Wiring diagram
UIAOxxx
ghg
CERN
A
Works
Responsible
Wiring diagram
Project Leader
UIAOxxx
ghg
hjhjh
Control
A
Approval Team
Wiring diagram
UIAOxxx
hjhjh
ghg
ST-CV
hjhjh
Subcontractor 2
Project Leader
Non-ST
Groups
4th ST Workshop
ST Groups
Y. Body, H. Jena, M.C. Morodo
Client
CERN ST-CV
Control cubicle wiring diagram
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Control cubicle wiring diagram
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Control cubicle wiring diagram
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Document Handling: Contract Roles
Contractor
A
Wiring diagram
Project Leader
UIAOxxx
ghg
hjhjh
Subcontractor
1
A
Project Leader
Wiring diagram
UIAOxxx
ghg
CERN
A
Works
Responsible
Wiring diagram
Project Leader
UIAOxxx
ghg
hjhjh
Control
A
Approval Team
Wiring diagram
UIAOxxx
hjhjh
ghg
ST-CV
hjhjh
Subcontractor 2
Project Leader
Non-ST
Groups
4th ST Workshop
ST Groups
Y. Body, H. Jena, M.C. Morodo
Client
CERN ST-CV
Control cubicle wiring diagram
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Control cubicle wiring diagram
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Factory Tests
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
On-site Installation and Acceptance
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV
Conclusions
Working within large-scale industrial Contracts demands of us:
Making the Contractor fully understand our own needs
Best fit the contributions of every participant
Work procedures follow-up (emphasis to safety and quality)
Accurate validation and acceptance procedures
And last but not the least, always consider that...
Efforts investment in Project Documentation is worthwhile
Thank you
4th ST Workshop
Y. Body, H. Jena, M.C. Morodo
CERN ST-CV