MARKET SYSTEM RELEASE UPDATE
Modifications Committee Meeting
31 January 2012
SEM R1.10.0 – Oct. 2011
•
•
Scope for SEM R1.10.0 was as follows:
Change Request
Description
SEM_PC_CR172
MIUN Calculation
Release was deployed successfully on Friday October 21st, 2011 in conjunction
with the deployment of the new Auction Management Platform (AMP).
SEM R1.11.0 – Dec. 2011
•
Scope for SEM R1.11.0 was as follows:
Change Request
Description
SEM_PC_CR282
RUN_TYPE on SFTP D+1 MIUN Files
SEM_PC_CR283
Import of IUNs from MI
•
Release was deployed successfully on December 15th, 2011.
•
Change Requests were raised during testing with AMP.
•
Changes were delivered by MIUN Calculation solution vendor and not CMS
vendors (ABB / Navita).
•
Changes did not impact on interfaces between the CMS and Participant
systems.
SEM R2.0.0 – Intra-Day Trading - Scope
•
Scope for SEM R2.0.0 is as follows:
Change Request
Mod Ref Description
SEM_PC_CR222
18_10
SEM_PC_CR244
Intra-Day Trading
SO Security (Option 1)
SEM_PC_CR256
43_10
Variable Price Taker Generator Units and Firm Access
SEM_PC_CR284
18_10
Data to be Utilised when MSP Software Cancellation
Run occurs
SEM_PC_CR287
Inclusion of Breach Amount in the Credit Risk Report
•
SEM_PC_CR284 added to scope on Dec 2nd 2011. Change to the vendor design
to ensure alignment of IDT solution with High Level Design Summary agreed at
the Modifications Committee.
•
SEM_PC_CR287 added to scope on Dec 12th, 2011. Minor change included to
align with the T&SC and to ensure Participants could effectively manage Credit
Cover under IDT.
SEM R2.0.0 – Intra-Day Trading – Project schedule
•
•
Major activities and associated schedule for the project are as follows:
Activity
Schedule
Status
Detailed Requirements
Dec 1st , 2010 – Apr 30th, 2011
Complete
Vendor Detailed Design
May 1st, 2011 – Jul 29th, 2011
Complete
Design Deliverables Issued to Participants
(MPUD etc.)
Aug 29th, 2011
Complete
Participant Engagement Plan published
Sep 9th 2011
Complete
Participant Systems Design Workshops
Sep 28th, Oct 5th 2011
Complete
Vendor Implementation
Jun 20th, 2011 – Nov 11th, 2011
Complete
Factory Testing
Nov14th, 2011 - Dec 23rd, 2011
Complete
System Integration Testing
Jan 3rd, 2012 - Apr 27th, 2012
In Progress
Market Trial
Apr 30th, 2012 – Jul 6th, 2012
Deployment
Jul 20th, 2012*
The project is on schedule across all workstreams.
* subject to successful completion of testing
SEM R2.0.0 – Intra-Day Trading – Technical Workstream
•
Major activities and associated schedule for the Technical Workstream:
Activity
Schedule
Status
Technical Infrastructure Design
Apr-May 2011
Complete
Hardware Procurement
Jun-Jul 2011
Complete
Hardware Installation (EirGrid & SONI)
Aug-Sep 2011
Complete
Data Network Commissioning
Oct 2011
Complete
Non-Production Test Environments Build
Nov 2011- Feb 2012
In-Progress
Data Centre Capacity Uplift (SONI)
Feb-Mar 2012
In-Progress
Production Environments Build (Eirgrid & SONI)
Jan 2011-Feb 2012
In-Progress
Infrastructure Technical Testing
Feb-Mar 2012
High Availability & Disaster Recovery Testing
Mar-Apr 2012
Operational Acceptance Testing
May-Jun 2012
Go-Live Migration Rehearsals
May-Jul 2012
Go-Live
Jul 20, 2012
SEM R2.1.0 – Oct. 2012
•
The Modification Proposals approved for inclusion in scope for SEM R2.1.0 are
as follows:
Mod Ref
CR Ref
Description
Mod_40_10
SEM_PC_CR254
Differentiation between Dwell Times and Dwell Trigger
Points While Ramping Up and Ramping Down
Mod_42_10
SEM_PC_CR255
Changes to the Single Ramp-Up Rate and the Single
Ramp-Down Rate calculation.
Mod_01_11
SEM_PC_CR258
UI Payments for Generator Units.
Mod_06_11
SEM_PC_CR259
Increasing maximum daily submission number and
automating cancellation of Settlement Reallocation
Agreements.
Mod_10_11
SEM_PC_CR274
Interconnector Under Test.
Mod_12_11
SEM_PC_CR275
Interconnector Unit Loss Adjustment when Exporting
Mod_21_11
SEM_PC_CR280
UI Payments for Generator Units Constrained On
SEM R2.1.0 – Oct. 2012
•
The release cut-off date for the October 2012 release to the Central Market
Systems was Friday, November 18th, 2011.
•
Two meetings of the Change Control Forum (CCF) were held to determine the
non-T&SC release scope, i.e. Changes routed through the SEM Design
Service (SDS).
•
A SEM R2.1.0 release scope proposal paper has been issued to the RAs
outlining the complete release scope.
•
Once approval has been received from the RAs the release scope will be
published to the industry.
SEM R2.2.0 – Apr. 2013
•
The release cut-off date for the April 2013 release to the Central Market
Systems is : Friday, June 22nd, 2012
•
All approved Modifications Proposals will be allocated to this release (subject