Request Management - Irrigation Australia
Download
Report
Transcript Request Management - Irrigation Australia
The Murrumbidgee Irrigation Area (MIA)
Infrastructure Modernisation
Key Objectives
Improve delivery system efficiencies
Meet changing customer needs
Reduce asset ownership costs
Generate water savings
Reduce infrastructure
footprint
Lake Wyangan System
Background
Closed system within a catchment of 7,000 ha
Irrigation supplies to around 200 properties
Ageing concrete-lined gravity supply channels
Constrained system
limited to 220 ML/day
Mix of hobby blocks,
horticulture and large area
Social amenity provided
by Lake Wyangan
Lake Wyangan Project Area
Lake Wyangan Project
Objectives
Replace ageing infrastructure that is at risk of failure
Enable delivery of contracted levels of service
Minimise the impact on water levels and water quality and
the overall environmental health of the Lake Wyangan
catchment
Realise the estimated water
savings target for the project
Lake Wyangan Project
Options considered
Upgrade the existing supply system
– Focus on renewal of ageing assets over water savings
Reconfigure the existing system
– Focus on providing a secondary supply system for some areas
to address capacity constraints
Build new assets to alleviate
requirement to upgrade some
capacity constraints
– Focus on creating new asset over
renewal of existing assets
Lake Wyangan Modernisation
Scope
Reline and widen 15.8km of ageing concrete-lined Lake
View Branch Canal (122,000 sq. m of shotcrete lining)
Replace open channels and pipelines at the end of their
working lives with 13.8km of GRP and PVC gravity pipelines
Replace Dethridge wheels with electromagnetic flow
meters compliant with AS4747
Automation of regulators and escape structures
Install remote monitoring of flow
meters
Existing Channel Lining
Assessment of Existing Lining
Percentage of Collapsed and Failed Panels
120%
Failed Panels
Percentage of Panels
100%
Collapsed Panels
80%
60%
40%
20%
0%
1
6
11
16
21
26
31
36
Sector Number
41
46
51
56
61
Lining Design Criteria
Design Criteria
Ranking
Convey the required flow
Construction within winter
shutdown periods
Reduce seepage losses
Prevent erosion / dispersion
of soil behind lining
Durability for 80 years
design life
Cost-effective solution
Fibre reinforced shotcrete
Grouted fabric mat
Shotcrete over sealed liner
Coletanche (geotextile) with
asphalt / bitumen
Shotcrete over a flexible
membrane
Hypalon
HDPE
Technical Risk Reduction
Shotcrete Lining Trials
Earthwork remediation and compaction
Concrete mix and curing
– Unreinforced v. polymer reinforced shotcrete
Shotcrete application
– Shotcrete lining over a geotextile
Panel contraction and expansion
joints
Lining detail at bank top
Shotcrete surface finish
Channel Re-lining
Channel Re-lining
Construction Schedule
Building
relationships
Planning and
design
Construction
Testing/
Commissioning
Timing
Oct 2011– ongoing
Oct 2011 – May 2013
May 2013 –Nov 2014
Nov 2013/Nov 2014
Key steps
Stakeholder
forums
Planning options
Construction:
Acceptance
testing
Individual face-toface meetings
Survey and detailed
design
Outlet designs
– Civil
– Mechanical
– Electrical
– Automation
New system
begins operation
Lake Wyangan Modernisation
Challenges
Forecasting future customer behaviour and intentions
Managing customer expectations
Developing and adopting new design rules
Establishing new business processes
Anticipating changes to operating
practices
Compressed construction window
Delivering a successful project for
MI, customers and the region
Acknowledgement
The Lake Wyangan Modernisation Project
received Australian Government funding
of $50 million through the Private
Irrigation Infrastructure Operators
Program in NSW
Thank You for Your Attention