Water Services Training Group 14th Annual Conference New Decade – New Challenges 9th September 2010 New Decade - New Challenges Annual Conference September 2010 WSIP 2010-2012 Implementation Maria Graham Principal Officer Water Services Investment Section, DoEHLG New Decade - New Challenges Annual Conference September 2010 Key features of WSIP 2010-2012 Scale of Programme €1 billion underway €1.8 billion contracts to commence (340 contracts) 190 schemes in planning Presented in River Basin District format Focus on contracts in medium term Integration of water conservation - €321m contracts to commence Annual Review Framing the priorities for 2010-2012 Setting programme priorities Water conservation Environmental objectives ECJ judgments Environmental & public health compliance Economic objectives – works to support sustainable development of hubs and gateways & strategically located areas & employment creation in line with Smart Economy report Assessment process Assessment by Water Services Authorities of projects not substantially advanced in 2007-2009 period against these priorities. Subsequent evaluation by Department. Key inputs… Assessment of Need River Basin Management Plans: priorities EPA – Drinking water, Urban Waste Water Reports Work on RAL and waste water priorities for first cycle Forfas Reports – WSIP 2010-2012 NSS/ Developing areas Enterprise needs of Gateways and Hubs Freshwater Pearl Mussels Plans Shellfish Pollution Reduction Plans Schemes/contracts excluded Did not rate sufficiently highly as contract/scheme… Did not feature highly on public health/ environmental grounds Involved plans for water supply capacity increases not justified by immediate economic need or progress on water conservation; Involved plans for increased waste water treatment capacity not reflected in waste water treatment priorities in first cycle of river basin management plans or other environmental priorities; Scope of proposal impacting on affordability; WSIP 2010-2012 Value of Contracts to commence 2010-2012 by investment type Water conservation 17% Water 44% Waste Water 56% Water Supply (RAL) 15% Water Supply other 12% Water conservation Water Supply (RAL) Water Supply other Waste Water €1.8 billion of contracts to commence Waste Water Infrastructure - €1 billion Water Supply Infrastructure - €800m Infrastructure Investment priorities 2010-2016 Published by Dept of Finance in July 2010 Water Services - Almost €3.5 billion in Exchequer resources over the period 2010-2016 Report acknowledges progress made – but focuses on future issues – satisfying demand in critical centres for industrial & commercial development to aid recovery; tackling high levels of unaccounted for water and achieving full compliance with directives. New Decade - New Challenges Annual Conference September 2010 Infrastructure Investment priorities 2010-2016 Water Services Investment - Exchequer Capital 4,000 3,500 3,000 €m 2,500 2,000 1,500 1,000 500 0 2003-09 2010-16 (projected) “The new funding level will amount to a very substantial sum in real terms, given reduced tender prices..” Infrastructure Investment Priorities 2010-2016 (D/Finance- July 2010) New Decade - New Challenges Annual Conference September 2010 Infrastructure Investment priorities– Anticipated outcomes by 2016 Make “major in-roads” in addressing deficiencies in water infrastructure particularly in hubs & gateways; 100% compliance with Urban Waste Water Directive – (from 2009 base of 92%); 100% compliance with drinking water standards; Average level of unaccounted for water to be reduced from 43% to 33% New Decade - New Challenges Annual Conference September 2010 Local authority financing (1) Measures to address changed financial climate Alignment of WSIP 2010-2012 with available resources EPA Remedial Action List (RAL) – water pricing deferred to later contracts to facilitate early delivery Mechanism for dealing with sunk costs on discontinued schemes (Circular L4/10) Additional resources being devoted to final accounts in 2010 Borrowing Approved allocations of €144m in 2010 Allocations sufficient to cover demands for completed works & works in progress New Decade - New Challenges Annual Conference September 2010 Local authority financing (2) Achieving a sustainable funding mix RAL – generally 100% funding Water conservation – generally 90% funding Other contracts/schemes – need to ensure appropriate project scope and avail of beneficial market conditions Continue to work with CCMA on issues arising. New Decade - New Challenges Annual Conference September 2010 Implications of move to contracts focus Contract = substantial advance, treatment plant Civil, Treatment plant M&E, Treatment Plant DBO, Network Civil, Network M&E, Pumping contracts (Circular L6/09 para. 6) Approved Budgets Application of Water Pricing Planning of Projects Programme/Project Management Annual Review Approved Budgets Planning stage:– budget covers cost to approval of PR and share of water pricing to be recouped from subsequent contracts; Construction/Procurement:- budget details at two levels Scheme ( or phase of scheme) level Contract level reflecting both relevant contract & noncontract costs - water pricing will apply at this level (on bottom line basis) WebPCS being adjusted to allow for these changes New Decade - New Challenges Annual Conference September 2010 Project financing – water pricing application to contracts Scheme Stage Planning stage Approved Cost Water pricing WSA share (20%) €2m Approved Grant Cumulative share of costs borne by Dept at end of each stage. €2m (with €0.4m to be recouped over the procurement/ construction phase) 100% (€18m) Apportionment of planning costs across contracts (pro-rata share) Application of 20% to contract cost & pro-rata share of planning costs Contract 1 (including noncontract costs) €2m €0.222m €0.444m €1.556m 89% Contract 2 (including noncontract costs) €7m €.0.778m €1.556m €5.444m 82% Contract 3* (including non-contract costs) €4m €0.444m €0.889m €3.111m 81% Contract 4* (including non-contract costs) €3m €0.333m €0.667m €2.333m 80% Contract 5* (including non-contract costs) €2m €0.222m €0.444m €1.556m 80% Total €20m €16m (80%) Procurement/ Construction stage * Construction post 2012 – illustrative example from Circular L4/10 New Decade - New Challenges Annual Conference September 2010 Planning Preliminary report Critical appraisal tool – determining scale, scope and phasing of project; Need broad vision to guide the incremental approach Set in River Basin Management Plan context – need to look at opportunities for cross boundary synergies/economies of scale, Reduce the need for “design reviews” Aim - to have appropriate contracts ready to go for next investment cycle. New Decade - New Challenges Annual Conference September 2010 Programme/project management Driving the programme Need to use the “project steering group” meetings as “programme steering groups” to drive local programmes; Determine key milestones at project level and monitor any slippage and address; Be guided in implementation by WSIP priorities – quality, compliance and economic recovery; Project management staff New Decade - New Challenges Annual Conference September 2010 Annual Review Review progress at end of each year of operation to allow for re-prioritisation; Review in line with programme priorities but will take account of new issues emerging – Remedial Action List (RAL), licensing/ certification etc RAL – call for proposals in Summer 2010 for small scheme funding. Implementation - Future Trends VFM study Review of WSIP 2007-2009 with outcome to inform implementation of WSIP 2010-2012; Due to be finalised in Autumn; Steering group involving D/Finance and CCMA; Terms of Reference to look at efficiency and effectiveness of overall investment & project delivery; New Decade - New Challenges Annual Conference September 2010 Implementation - Future Trends Project scale Use of small schemes funding to complement overall priorities Bundling and DBO : “continued use of DBO” – Local Government Efficiency Review Group recommendation; Consideration of bundling projects based on common compliance considerations as well as geographical proximity. Clarity on overall strategy and contribution of individual contracts to delivering on outcomes New Decade - New Challenges Annual Conference September 2010 Economies of scale – waste water DBOs Wastewater DBO Contracts - DB Cost per PE 1600.00 1400.00 1382.19 1334.37 Cost per PE, € 1200.00 1000.00 889.61 800.00 28,000, 628.23 660.47 600.00 556.61 3,500, 493.99 3,600, 461.67 3,000, 428.27 400.00 65,000, 470.48 447.61 334.24 200.00 0.00 0 10,000 20,000 30,000 40,000 Population Equivalent, PE New Decade - New Challenges Annual Conference September 2010 50,000 60,000 70,000 Economies of scale –water DBOs Water DBO Contracts - DB Cost per Ml 2,500,000 2; 1,886,230 Cost per Ml, € 2,000,000 1,500,000 15; 1,103,318 1,000,000 8; 1,018,501 31; 793,653 18; 461,062 500,000 87; 309,246 0 0 10 20 30 40 50 60 70 Daily Water Production in Megalitres per day, Ml/d New Decade - New Challenges Annual Conference September 2010 80 90 100 Implementation - Future Trends Performance measurement Greater definition of outcomes expected rather than output only - eg number of schemes/contracts completed Shared services Potential being considered in VFM study drawing from existing examples; Governance issues being considered in context of implementation of River Basin Management Plans Local Government Efficiency Review Group recommended – “enhanced regional office approach should be developed at river basin level for: - infrastructure delivery and implementation of river basin management plans…..” New Decade - New Challenges Annual Conference September 2010 Conclusion Substantial Exchequer resources available over the coming years; Opportunity to make major impact on water services infrastructure; Priorities have been set; Need to demonstrate success in terms of improved compliance, water conservation and security of supply if projected funding level is to be maintained. New Decade - New Challenges Annual Conference September 2010