Planning for Risk
Download
Report
Transcript Planning for Risk
Planning for Risk and
Change
Geoff Leese Sept 1999 revised Sept
2001, Jan 2003, Jan 2006, Jan 2007,
Jan 2008, Dec 2008
(special thanks to Geoff Leese)
Risk and risk management
Much “risk management” focussed on
Health and Safety risks these days
Topic is much bigger than that
Business
risk
Security risk
Business continuity
Introduction
Is it worth doing?
Cost/benefit
analysis
What might affect it if we go ahead?
Risk
management
Cost-benefit analysis (1)
Cashflow projection
Payback period
Time
taken to “break even”
Return on Investment (Accounting Rate
of Return)
average
annual profit/total investment*100
Cost-benefit analysis (2)
Present value
value
in year t/(1+r)t
“r” is discount rate as decimal value
Discount factor tables are available!
Net Present Value of a project (NPV)
Sum
of discounted values of all cashflows
for that project
Assessment of risk
Risk
Customer cancels contract
Supplier goes bankrupt
Budget exceeded by <= 20%
Budget exceeded by > 20%
Maintenance costs higher
than estimate
Response time targets not
met
Importance
High
Low
Low
Medium
Low
Likelihood
Low
Medium
Medium
Low
Low
Low
High
“Risky” projects less likely to start.
Apply “Risk premium” to discount rates for NPV
Expected Value
Sales
Optimistic
Net Annual
Income (I)
£800,000
Probability
(P)
0.1
Expected
Value (I*P)
£80,000
Most Likely
£650,000
0.6
£390,000
Pessimistic
£100,000
0.3
£30,000
Expected
Income
£500,000
Weighted average of all possible outcomes.
A useful measure for comparing contracts!
Risk Profile Analysis
Sensitivity analysis
Vary
each factor (in turn) by + or - 5%
Recalculate costs/benefits
Indicates sensitivity of project to each
factor
Helps with risk assessment
Monte Carlo Method? (see Cotterill. &
Hughes Chap 7)
Decision trees (1)
Improve or replace machinery?
Market will expand, or not expand?
Expansion
Improve
NPV (£)
-100,000
0.2
0.8 75,000
No expansion
D
Expansion
Replace
0.2
0.8
No expansion
250,000
-50,000
Decision trees (2)
Improve (0.2*-100,000)
+(0.8*75,000)
=£25,600
Replace
(0.2*250,000)
+ (0.8*-50,000)
=£10,000
Therefore choose Improvement!
Project Evaluation
Evaluate on economic,strategic and
technical grounds
Assess all costs & income over lifetime
of project
Discount accordingly
Allow for uncertainty!
Evaluate expected outcomes and choose
strategies
Risk management (1)
Estimation errors
Use
historical data and keep records!
Planning assumptions
State,
and be prepared to revise them!
Eventualities
Identify,
and deal with them!
Risk management (2)
Hazard identification
Risk analysis
Risk prioritisation
Risk reduction
Risk monitoring
Hazard identification
Contract Factors (is it special or different?)
Customer Factors
Staff Factors
Project Methods
Technology Factors
Changeover Factors
Supplier Factors
Environment Factors
Consider for each phase or product!
Risk Analysis (1)
Risk Value = Likelihood * Impact
Impact expressed as monetary values?
Likely
to be difficult or impossible!
Likelihood AND impact expressed
using “arbitrary scale “ (1-10)
Most likely - 10, least likely - 1
Highest impact -10, lowest impact - 1
Risk Analysis (2)
Hazard
Likelihood Impact Risk Value
Sickness affecting critical
path activities
Production takes longer
than expected
Specification takes
longer than estimate
Sickness affecting noncritical activities
Changes to
requirements during
production
Product testing shows
up design deficiencies
5
7
35
5
5
25
3
7
21
7
3
21
2
8
16
1
10
10
Risk Prioritisation
Prioritise by risk value?
Consider
Confidence
in assessment
Compound risks
Number of risks
Cost of action
Risk Reduction Leverage (RRL)
=
(RV(before) - RV(after))/risk reduction cost
Use the same units!
Risk Reduction (1)
Hazard prevention
Likelihood reduction
Risk avoidance
Risk transfer
Contingency planning
Risk Reduction (2)
Personnel shortfalls
get
the best, job matching, early
scheduling, personal development, team
building
Unrealistic estimating
multiple
estimates, use of different
techniques, standardisation of methods,
use of historical data
Risk Monitoring
Assign INDIVIDUALS to monitor risks
Part of “change plan”
Use PERT techniques to assess potential
effects of uncertainties on project
schedule
3 way estimating
Activity standard deviations
Probability & “Z” values” (Cott. & Hughes)
Evaluation and Review
Projects should be reviewed on completion
The risk management plan should be
reviewed at the end of the project .
Risks
were successfully foreseen?
Contingencies were properly planned for?
Lessons to be learnt?
Improvements to be made?
should be built into the risk management plan
Change Control Plan
Vital part of the project plan
Changes are almost inevitable
Example: the client originally asked for
sweetcorn on all sandwiches but now
wants sweetcorn on tuna only. What
changes will need to be made?
Project roles should include a Project
Librarian, responsible for logging
change requests and responses.
Controlling Change
Risk of “scope creep”
One big change? Lots of little ones?
Poorly documented changes make
maintenance and enhancement difficult
May comprise the integrity of the design
May comprise the profitability and
deliverability of the contract
Change Control Plan
Change Request (CRF)
Change Specification
Change Analysis
Costing & feasibility
Change decision (Change Control Board)
Change implementation & documentation
And the downside Perceived as bureaucratic, expensive &
time-consuming
Likely to annoy users and may affect
their relationship with the company.
Will definitely annoy production staff.
Restricts responsiveness to user needs
Emphasises costs and control rather
than user needs
Summary
Project evaluation
should we do it?
How should we do it?
Risk management what
COULD happen if we do?
How will we cope if it does?
Change control
Further Reading
http://www.rmri.co.uk/
Link
to BSI risk management