C O N S T RU C T I O N P RO J E C T U P DA T E
FOREST AND
L I N D E N AV E N U E S C H O O L S
J U LY 2 3 , 2 0 1 2
GLEN RIDGE PUBLIC SCHOOLS
INTRODUCTION
After nearly a year of study and discussion, the Board of Education has decided to
launch major capital improvement projects at Forest Avenue School and Linden
Avenue School. These projects are designed to provide our educators with the
additional space and flexibility necessary to meet the evolving educational needs of
our youngest students. Through prudent management of the district’s resources,
we have a one-time opportunity to make these improvements without incurring
debt.
We could not undertake this initiative without the help and support of the
community. We look forward to working and communicating with staff, parents and
neighbors as we move forward.
STATEMENT OF NEED - CAPACITY
Functional
Current
Overage
FOREST AVENUE SCHOOL
201 students
259 students
58 students
Functional
Current
Overage
LINDEN AVENUE SCHOOL
210 students
278 students
68 students
STATEMENT OF NEED - ENERGY CONSERVATION
ENERGY AUDIT RESULTS
WINGS MOST ENERGY INEFFICIENT SPACES IN THE DISTRICT
HVAC WINGS
STATEMENT OF NEED - USE OF SPACE
FOREST AVENUE SCHOOL
•
•
•
•
•
All Classrooms Used All Day
Self-contained Special Education Classroom
Resource Room Special Education Program
Shared-Use Room: Resource Center/Reading Instruction
Shared-Use Room: Morning Pre-K/Afternoon Art
LINDEN AVENUE SCHOOL
•
•
•
•
All Classrooms Used All Day
Self-contained Special Education Classroom
Resource Room Special Education Program
Shared-Use Room: Morning Art/Afternoon Counseling, Meetings, OT/PT
ADDRESSING THE NEEDS
FOREST AVENUE SCHOOL
•
•
•
•
•
Classroom
Small Group Instructional Room
HVAC Wing
Playground
Basketball Court Eliminated
LINDEN AVENUE SCHOOL
•
•
•
•
Classroom
Small Group Instructional Room
HVAC Wing
Playground
COST
Forest $729,000
Linden $789,000
TOTAL $1,379,000
TASKS COMPLETED
•
•
•
•
•
Educational Specifications
Architectural Drawings
Soil Testing
Arborist Evaluation
State Application
TASKS IMMINENT
• Confer with Mayor and Borough Manager
• Borough Committees’ Approvals (Planning Board, Historic
Preservation Commission)
• State Approval
• Bids
• Neighbor Meetings
• Ongoing Communication
CONSTRUCTION TIMETABLE
Schematic Design Process: 3 Months - April 7, 2012
• Initiate Contract w/ Architect (DRG to draft and
forward).
• Secure quote for Survey of properties.
• Secure quote for Site / Civil Engineering Services.
• Secure quote for Soils Engineering and Analysis
CONSTRUCTION TIMETABLE (cont’d)
NJDOE:
• District to provide an Educational Specification to support additions.
Include mission statement, purpose, proposed occupancy, room
amenities, etc.
• District to review proposed plan layouts provided by architect. Provide
written comment for architect to make revisions.
• Architect to develop final floor plans and elevations for state and local
review.
• Amend the currently approved LRFP via Board of Education Resolution.
• Adopt the final “Educational Specifications” and “Drawings” via Board of
Education Resolution.
• Approve DRG to expedite application and all supporting materials to the
NJDOE for Schematic Approval.
CONSTRUCTION TIMETABLE (cont’d)
Local Planning Requirements:
• Appear before Glen Ridge Planning Board for courtesy review as required
by the NJDOE.
• Appear before Glen Ridge Historic Preservation Commission.
Construction Documents Process: 2 Months - July 25, 2012 (REVISED)
• Collect site survey / soils information.
• Develop drawings and specifications.
• Consult with attorney on front end requirements.
• Send completed documents to DCA Trenton for review.
• Tony Brun has approved for final educational adequacy and forward to
NJDCA to initiate Local Review.
• Local reviewer has agreed to meet next week to finalize the plans.
CONSTRUCTION TIMETABLE (cont’d)
DCA Trenton Review: 3 Months (varies) - Oct 1, 2012
• DCA issues code review.
• Architect responds
• Preparing for bid
Advertise - Bid Period 1 ½ Months - November 15, 2012
Construction 5-6 Months (varies) - May 15, 2013
• Long lead items
• Windows - 16 weeks from order
• Unit Ventilators - 10 weeks from order