Public Health Transition

Download Report

Transcript Public Health Transition

Public Health Transition
Update to Health Overview and Scrutiny
Dr Andrew O’Shaughnessy
Consultant in Public Health
NHS Airedale, Bradford and Leeds
July 2012
Background
• July 2010 - Liberating the NHS
• November 2010 – Healthy Lives, Healthy People
• Transition of the current Public Health function
within Primary Care Trusts to transfer to Local
Authorities by April 2013
• Additional consultation papers on the Funding
and Commissioning of Public Health, and a
Public Health Outcomes Framework
Progress
• High level Transition Plan July 2011
• Approval by Health Scrutiny, GP
Commissioning Executive and Health and
WellBeing Board
• Detailed Project Initiation Document
November 2011
• Formal Programme Plan Jan 2012 – 6
iterations to July 2012
• Regular updates to Health Scrutiny
• Now handing Programme over to LA as
receiving organisation
Stakeholders
• Stakeholder map completed
• Stakeholder Engagement Plan
• CCGs; SHWBB; Elected Members; BMDC
Mgmt. Teams; Cluster; VCS; PHE, NHSCB; HPA
• Communications PID signed off by Health
Scrutiny
• Stakeholder events completed with LA staff and
CCGs
Public Health Transition Board
Membership
• Strategic Director of Childrens Services (Chair)
• Joint Director of Public Health
• LA Change Lead
• CCG representatives
• Project Lead – Transition Design and Implementation
• Project Lead – Workstream Direction
• Representative BMDC HR
• Representative BMDC Finance
• Representative BMDC Childrens
• Representative BMDC Legal
• Representative BMDC ICT
• Representative BMDC Env. Health
Governance
Report directly to :
• SHWBB
• LA Corporate Management Team
• NHSABL Board
• GPCE
• CCG Boards
• Health Overview and Scrutiny
Report indirectly to:
• Public Health England
• NHS Commissioning Board
• NHS North Yorkshire and York
• NHS North of England
Governance Structures
Remaining Milestones
Summer 2012
Department of Health publishes awaited guidance and strategies
August 2012
Consultation process to begin
October 2012
IT Workstream complete
October 2012
Access to named documentation for HR at BMDC
March 2013
Finance Workstream completed
March 2013
Estates Workstream complete
April 2012
All Health Area workstreams complete
April 2013
PCTs abolished, transfer formally complete