Transcript Document
Repair/ Rehabilitation of School Buildings
(Cluster 2)
Estimated Cost by Item of Work
(Materials/ Equipment and Labor Only)
May 12, 2014
Date Prepared
Camp Aquino Elem. School
Demolition/ Restoration Tinsmithry Works 10,000.00
25,260.30
Window Ceiling Works (Interior Only) Project Billboard 152,352.00
141,479.00
5,000
TOTAL 334,091.30
Lourdes Elem. School
Demolition Roof Framing Works Tinsmithry Works Project Billboard 5,000.00
146,299.40
103,642.50
5,000
TOTAL
259,941.90
Cut-Cut II Elem. School
Demolition Roof Framing Works Tinsmithry Works Window Project Billboard 5,000.00
113,890.40
65,158.60
70,932.00
5,000.00
TOTAL 259,981.00
Mapalacsiao Elem. School
Demolition/ Restoration Excavation Concrete Works Form Works Masonry Works Roof Framing Works Tinsmithry Works Project Billboard 8,000.00
1,200.00
74,224.80
12,597.00
61,326.20
57,769.40
40,365.00
5,000.00
TOTAL 260,482.40
Atioc-Dela Paz Elem. School
Demolition/ Restoration Windows Ceiling Works Tile Works Electrical Works Project Billboard 10,000.00
13,018.00
90,433.20
106,301.00
35,925.50
5,000.00
TOTAL 260,677.70
C.A.T. Elem. School
Demolition Roof Framing Works Tinsmithry Works Project Billboard
TOTAL
5,000.00
143,468.00
106,454.40
5,000.00
259,922.40
Buenavista Elem. School
Carpentry Works Tinsmithry Works Painting Works 178,594.00
9,906.00
66,384.00
Project Billboard 5,000.00
TOTAL 259,884.00
San Carlos Elem. School
Tinsmithry Works Ceiling Works 111,835.10
75,506.60
21,827.00
Miscellaneous (Steel Post/ Wood Beam) Painting Works Project Billboard 45,816.00
5,000.00
TOTAL 259,984.70
Paraiso Elem. School
Demolition/ Restoration of Roof Embankment Masonry Works 7,000.00
1,560.00
101,267.40
Roofing & Roof Framing Works Doors & Windows 74,724.00
52,670.00
Painting Works Form Works Project Billboard 12,645.00
5,019.30
5,000.00
TOTAL 259,885.70
Total Material Cost Total Labor Cost Direct Cost Mark-Ups VAT ENG’G SUPERVISION
COST OF PROJECT
1,844,767.00 570,084.10 2,414,851.10 480,603.45 289,545.45 65,000.00
3,250,000.00
School
Camp Aquino Elem. School Lourdes Elem. School Cut-Cut II Elem. School Mapalacsiao Elem. School Atioc-Dela Paz Elem. School C.A.T. Elem. School Buenavista Elem. School San Carlos Elem. School Paraiso Elem. School
TOTAL
Total Amount
334,091.30
259,941.90
259,981.00 260,482.40 260,677.70 259,922.40 259,884.00 259,984.70 259,885.70
2,414,851.10
Repair/ Rehabilitation of School Buildings
(Cluster 1)
Estimated Cost by Item of Work
(Materials/ Equipment and Labor Only)
August 4, 2014
Date Prepared
Sapang Maragul Elem. School
Demolition Concrete/Masonry Works/ Plastering Doors & Windows Ceiling Works Painting Works Form works Project Billboard 7,000.00
23,823.80
121,440.00
111,813.00
25,200.00
2,808.00
5,000.00
TOTAL 297,084.80
Paradise Elem. School
Demolition/ Restoration 20,000.00
Masonry Works 2,412.80
Ceiling Works 291,155.80
Windows Painting Works Roofing works Project Billboard 90,965.00
33,957.00
1,913.60
5,000.00
TOTAL 445,404.20
Suizo Resettlement Elem. School
Excavation 400.00
Concrete Works Masonry Works 7,433.40
17,258.80
Roof Framing Works 136,791.20
Tinsmithry Works 93,520.70
Project Billboard 5,000.00
TOTAL
260,404.10
Suizo Bliss Elem. School
Demolition Anay Treatment Masonry Works Doors & Windows Ceiling Works Tinsmithry Electrical Works Painting Works Project Billboard 10,000.00
11,648.00
9,872.20
24,748.00
103,922.00
66,894.10
9,171.50
18,684.00
5,000.00
TOTAL 259,939.80
Bacuit Elem. School
Demolition 10,000.00
Roof Framing Works 99,013.20
Tinsmithry Ceiling Works (Interior Only) Electrical Works Project Billboard 70,613.40
68,255.20
7,351.50
5,000.00
TOTAL 260,233.30
Samberga Elem. School
Demolition Concrete Works Ceiling Works Electrical Works Painting Works Project Billboard
TOTAL
4,000.00
57,974.80
94,161.60
47,765.90
51,345.00
5,000.00
260,247.30
San Pablo Elem. School
Demolition Roof Framing Works Tinsmithry Ceiling Works (Interior Only) Electrical Works Project Billboard 10,000.00
99,013.20
70,613.40
68,255.20
7,351.50
5,000.00
TOTAL 260,233.30
School
Sapang Maragul E/S Paradise E/S Suizo Resettlement E/S Suizo Bliss E/S Bacuit E/S Samberga E/S San Pablo E/S
TOTAL Total Amount
297,084.80
445,404.20
260,404.10
259,939.80
260,233.30
260,247.30
260,233.30
2,043,546.80
Total Material Cost Total Labor Cost Direct Cost Mark-Ups VAT ENG’G SUPERVISION
COST OF PROJECT
1,543,350.00 500,196.80 2,043,546.80 406,453.20 245,000.00 55,000.00
2,750,000.00
Repair/ Rehabilitation of School Buildings
(Cluster 3)
Estimated Cost by Item of Work
(Materials/ Equipment and Labor Only)
August 6, 2014
Date Prepared
Laoang Elem. School
Demolition/ Excavation/ Restoration Concrete/ Masonry Works 20,000.00
114,821.20
Roof Framing Works Tinsmithry Works Project Billboard 89,845.60
67,223.00
5,000.00
TOTAL 296,889.80
Baras-Baras Elem. School
Demolition Roof Framing Works Tinsmithry Works Ceiling Works Tile Works Painting Works Electrical Works Project Billboard 10,000.00
90,069.20
55,573.70
67,709.20
23,012.60
20,931.00
24,567.40
5,000.00
TOTAL 296,863.10
Ceiling Works Windows
Sinait Elem. School
Electrical Works Roofing Works Project Billboard 148,623.80
132,480.00
44,133.70
3,827.20
5,000.00
TOTAL 334,064.70
Tariji Elem. School
Demolition Roof Framing Works Tinsmithry Works Ceiling Works Project Billboard 5,000.00
112,634.60
69,958.20
67,412.80
5,000.00
TOTAL 260,005.60
Capulong Elem. School
Demolition/ restoration of Roof Roof Framing Works 30,000.00
112,634.60
Ceiling Works Electrical Works Project Billboard 103,508.60
9,171.50
5,000.00
TOTAL 230,314.70
Balibago I Elem. School
Demolition Concrete Works Masonry Works Doors and Window Painting Works Project Billboard 7,000.00
68,684.20
25,214.80
107,640.00
46,666.50
5,000.00
TOTAL 260,205.50
School
Laoang Elem. SchooL Baras-Baras Elem. School Sinait Elem. School Tariji Elem. School Capulong Elem. School Balibago I Elem. School
TOTAL
Total Amount
296,889.80
296,863.10
334,064.70
260,005.60
230,314.70
260,205.50
1,708,343.40
Total Material Cost Total Labor Cost Direct Cost Mark-Ups VAT ENG’G SUPERVISION
COST OF PROJECT 1,282,808,00 425,535.40
1,708,343.40
340,747.51
204,909.09
46,000.00
2,300,000.00
Repair/ Rehabilitation of School Buildings
(Cluster 4)
Estimated Cost by Item of Work
(Materials/ Equipment and Labor Only)
August 7, 2014
Date Prepared
Matatalaib-Bato Elem. School
Demolition/ Restoration Concrete/ Masonry Works & Partition Wall Doors & Window Painting Works Project Billboard 20,000.00
40,266.20
138,828.00
56,073.00
5,000.00
TOTAL 260,167.20
San Juan Bautista Elem. School
Anay Treatment Concrete Works Ceiling Works Form Works Painting Works 4,290.00
99,010.60
121,815.20
10,868.00
19,188.00
Project Billboard 5,000.00
TOTAL 260,171.80
School
Matatalaib-Bato Elem.
School San Juan Bautista Elem. School
TOTAL Total Amount
260,167.20 260,171.80
520,339.00
Total Material Cost Total Labor Cost Direct Cost Mark-Ups VAT ENG’G SUPERVISION
COST OF PROJECT 388,394.00
131,945.00
520,339.00 103,297.36
62,363.64
14,000.00
700,000.00