The Legacies of Trudeau (NEP) and Mulroney (NAFTA)
Download
Report
Transcript The Legacies of Trudeau (NEP) and Mulroney (NAFTA)
Sustainable Energy Policy
1
Sustainable Energy Policy
2
Strategic – BC Hydro Long Term Planning
Project level
Environmental Assessment
▪ Federal
▪ Provincial
Integration
Sustainable Energy Policy
3
Sustainable Energy Policy
4
Integrated electricity planning - the long-term
planning of electricity generation, transmission, and
demand-side resources to reliably meet forecast
requirements.
2000s - long-term acquisition plan (LTAP) every 4 yrs
Needs to be reviewed and approved by BCUC
2010 Clean Energy Act – IRP replaces LTAP
Same problem for analysis and decision-making
but different consultation, review, and approval
Sustainable Energy Policy
5
Planning context, objectives
Gross (pre-DSM) demand forecasts
Resources (supply and DSM) – ID and
measurement
Develop resource portfolios
Evaluate and select resource portfolios
Develop action plan
Consult
Get approval
Sustainable Energy Policy
6
Application submitted to BCUC June 2008
Evidentiary update December 08
Formal hearings in BCUC
BCUC decision rejecting plan July 2009
Greenpolicyprof summary
Sustainable Energy Policy
7
1.
2.
3.
4.
did not adequately addressed
self‐sufficiency
DSM plan not adequately supported by
analysis
Rejected plan to reduce its reliance on
Burrard Thermal
Rejected special target for Clean Power Call
Sustainable Energy Policy
8
Mostly, critical of the lack of evidence or
analysis underlying BC Hydro’s plan
not a challenge to government policy, but as
a criticism of BC Hydro for not providing
sufficient evidence that it was complying with
government policy
Exception: refusal to endorse BC Hydro’s
desire to reduce reliance on Burrard Thermal
Sustainable Energy Policy
9
Critics of private power projects, including the
BC New Democratic Party, declared victory,
claiming the decision is a rejection of the BC
government’s plan to rely on private power for
future electricity supply.
Climate activists blasted BCUC “a serious blow
to the clean energy transition and climate
leadership in British Columbia.”
First Nations denounced the Commission for
creating roadblocks to their ability to use green
power projects to promote economic
development.
Sustainable Energy Policy
10
April 2009 Throne Speech : BC government
clarified that the BCUC “will receive specific
direction”
October 2009: Special direction #2: ordered
BCUC to rely on no more than 900 MW
capacity and 0 GW/yr firm energy
May 2010: Clean Energy Act passed.
New IRP process
Removed from BCUC scrutiny
Sustainable Energy Policy
11
Sustainable Energy Policy
12
What are the consequences of removing BC
Hydro planning from BCUC review?
Sustainable Energy Policy
13
http://www.bchydro.com/etc/medialib/intern
et/documents/planning_regulatory/iep_ltap/2
011q2/bc_hydro_irp__webinar.Par.0001.File.BC-Hydro-IRPWebinar-Presentation-April-2011.pdf
Sustainable Energy Policy
14
Timing delayed by rate review
Old: by 2016 enough B.C.-based energy to meet
customer demand even in critical water conditions;
and by 2020, an extra 3,000 gigawatt hour per year
of insurance energy
New: by 2016, enough B.C.-based energy to meet
customer demand in an average water year
The Province will also propose changes to the Clean
Energy Act to eliminate the insurance requirement
Sustainable Energy Policy
15
Sustainable Energy Policy
16
Approved plan calls for new independent
power projects
What happens now?
Sustainable Energy Policy
17
Sustainable Energy Policy
18
49.9 MW – Ledcor –
Innergex
Extensive review by
Squamish-Lillooet
Regional District (SLRD)
SLRD rejected
BC government passed
Bill 30 to “bring
certainty” to approval
process – 2006
Project approved –
commercial operation
began Dec 09
Sustainable Energy Policy
19
Should local or regional governments have
the right to veto power projects?
Sustainable Energy Policy
20
Environmental Assessment as a policy tool – a
“procedural policy instrument”
Requires analysis and procedure but does not specify
outcome
Sustainable Energy Policy
21
1.
2.
3.
4.
5.
6.
7.
Proposal from proponent
Screening – is EA required and if so what
kind?
Scoping – what issues?
Assessment of the proposal
Report preparation, submission, and review
Decision: recommendation by EA body,
authoritative decision by political body
Monitoring and compliance follow-up
Sustainable Energy Policy
22
Canadian Environmental Assessment Act
Came into force in 1995
Since 1972, governed by cabinet guidelines
applies to anything that requires federal approval
or permit
Procedures managed by Canadian Environmental
Assessment Agency, within Environment Canada
Usually, if federal EA no provincial EA
Sustainable Energy Policy
23
Determine if an environmental assessment is required
Identify responsible authority (RA)
screening – initial assessment
If potentially significant adverse effects or significant public
concern, requires mediation or panel review
4. Conduct the analysis and prepare the environmental
assessment report
5. RA Reviews environmental assessment report
6. Make environmental assessment decision
7. Implement mitigation and follow-up program, as
appropriate
1.
2.
3.
Sustainable Energy Policy
24
(a) where, taking into account the implementation of any
mitigation measures that the responsible authority considers
appropriate,
(i) the project is not likely to cause significant adverse
environmental effects, or
(ii) the project is likely to cause significant adverse
environmental effects that can be justified in the
circumstances
the responsible authority may exercise any power or perform
any duty or function that would permit the project to be
carried out in whole or in part
Sustainable Energy Policy
25
99% of projects approved
Sustainable Energy Policy
26
Gold and copper mine
west of Williams Lake
BC
Proposal would use
Fish Lake as tailings
pond
Federal EA process
Proponent insisted a
BC EA be done
Sustainable Energy Policy
27
PROVINCE
FEDERAL
BC gov approves despite
serious problems identified
by gov agencies in quality
of analysis and magnitude
of impacts
Panel assessment far more
rigorous on data, analysis
Concluded significant
impacts to environment
and First Nations concerns
Cabinet rejects mine
proposal
Update: Taseko has resubmitted a revised proposal that is now under review
Sustainable Energy Policy
28
Vertical Coordination (across jurisdictions)
Horizontal Coordination (across agencies)
Includes issues of “substitution”
Scoping
Cumulative effects
Followup
Strategic assessments
Missing?
Sustainable Energy Policy
29
“effects that are additive or interactive and
result from the recurrence of actions over time.
Cumulative impacts are incremental and result
when undertakings build on or add to the
impacts of previous impacts.”
Consideration required in federal rules,
permitted but not required in BC
What is the best way to deal with cumulative
effects in project level assessments?
Sustainable Energy Policy
30
Sustainability as core
objective
Strengthen public
participation
Meaningfully engage
Aboriginal
governments as
decision makers
Legal framework for
strategic and regional
EA
Sustainable Energy Policy
Require
comprehensive,
regional cumulative
effects assessments
Coordinate multiple
jurisdictions with
highest standards
Transparency
Fair, predictable,
accessible
Rights over efficiency
31
protect and advance the public interest;
promote a fair and competitive market economy;
make decisions based on evidence;
create accessible, understandable, and responsive
regulation;
advance the efficiency and effectiveness of
regulation; and
require timelines, policy coherence, and minimal
duplication.
Sustainable Energy Policy
32
Sustainable Energy Policy
33
IRP + PROJECT SPECIFIC
ASSESSMENT/APPROVALS
risks larger than necessary
local environmental effects
Risks less satisfied public
STRATEGIC ASSESSMENT
Risks delay in renewable
development (and climate
change mitigation)
An important tradeoff that needs to be
considered in process design
Sustainable Energy Policy
34