Transcript Slide 1
Pavement Type Selection – Updated Guidance on Use of Alternate Bidding
Virginia Concrete Conference Richmond, VA March 6, 2014
1
Session Outline
• Background on FHWA Policy & Guidance on Alternate Bidding for Pavement Type Selection 2 • State Usage 3 • FHWA Technical Advisory 2
Background on FHWA Policy & Guidance Information
Federal Register Oct 8, 1981 PTS Policy If designs equivalent then alternate bidding permitted Federal Register Nov 9, 1981 Clarification Discourages use of price adjustment clauses w/ AB 23 CFR, Part 626 Non-Regulatory Supplement April 8, 1999 FHWA does not encourage use of AB for PTS due to issue of equivalent pavement designs 3
Background on FHWA Policy & Guidance Information
FHWA Memo Nov 13, 2008 Clarifies & consolidates FHWA policy AB is not encouraged Use of commodity price adjustments should not be used SEP 14 approval needed if using price adjustments NCHRP Report 703 – Guide for Pavement Type Selection March 2011 4
PTS Method #1
Identify feasible alternatives Perform LCCA Consider subjective factors: constructability, adjoining pavement, competition, traffic control, budget, etc.
YES Cost within specified % of lowest estimate NO Eliminate alternative Make Decision 8 states
PTS Method #2 (MI)
Identify feasible alternatives 1 rigid, 1 flexible Perform LCCA YES Alternate with lowest LCC Make selection decision NO Eliminate alternative
Identify feasible alternatives
PTS Method #3
Perform LCCA Submit to selection committee. Committee evaluates engineering and economic factors Committee recommends a decision
PTS Method #4
Identify feasible alternatives Prepare LCC Adjustment factor Alternate Bids to determine pavement type 10-25 states Both rigid and flexible alternatives are feasible YES Perform LCCA NO Eliminate alternative
Overview of Pavement Type Selection
Components of Agency Processes – Selection of alternatives – Structural design – Economic Analysis – Primary/Secondary Factors Contractor-based processes – – – – Alternate Bidding Design Build Long Term Warranty Other ( PPP, Value Engineering, BV Contracting, Contract Maintenance)
State Usage
State has advertised at least 1 alternate bid job State has not utilized alternate bidding State did not reply to survey 10
Technical Advisory
Use of Alternate Bidding for Pavement Type Selection, T 5040.39 December 20, 2012 Elimination of SEP 14 approval for price adjustments, November 8, 2012 11
Question 1 Purpose of TA
Guidance on use of AB for PTS on Federal-aid projects on NHS 12
Question 2 Does TA Supersede other Guidance
TA Supersedes: – Federal Register FHWA PTS Policy Statement 11/9/81 – 23 CFR 626 NR Supplement issued 4/8/99 – HIPT Memorandum issued 11/13/08 13
Question 3 Background on AB for PTS
Risk associated w/ material costs and performance 23 CFR 626 NR Guidance did not encourage use of AB Limited use due to: – lack of national guidance, – consistent approach to AB and – open competitive bidding environment 14
Question 4 Scope/Applicability of TA
Recommended practice for use on FA projects on NHS 15
Question 5 FHWA Position
Suitable approach when, – Engineering/economic analysis shows no clear choice between different pavement designs 16
Question 6 When is AB Appropriate
Equivalent Designs – Similar level of service over same performance period (use of ME Design software) – Similar life-cycle costs • Performance period should include min one major rehab • NPV < 10% of alternative 17
Question 6 When is AB Appropriate
Discount Rate – Guidance available in LCCA in Pavement Design – Interim Tech Bulletin Sept 1981 – Recommend use of NPV for future costs – Recommend use of Real Discount Rate consistent w/ OMB Circular A-94 18
Question 6 When is AB Appropriate
Consideration of Uncertainty – Determine total LCC for each alternative – Consider use of RealCost software 19
Question 6 When is AB Appropriate
Maintenance and Rehab Strategy – Should reflect realistic pavement management practices – Should utilize realistic timing and extent of M&R activities – Provide similar level of service over performance period – NCHRP Report 703 Section 3.5 has reasonable approach
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_70 3.pdf
20
Question 6 When is AB Appropriate
Non-Economic Factors – Agency may consider, • Constructability • Continuity of adjacent pavements • Availability of local materials • Experience 21
Question 6 When is AB Appropriate
Appropriate Application – Only use when AB will likely influence determination of lowest bid – Projects w/ substantial quantities of different pavement items not suited for AB 22
Question 6 When is AB Appropriate
Work Zone User Delay Costs – Not suited when user delay costs for initial construction and M&R exceed 20% 23
Question 7 Administration of AB
LCCA Bid Adjustment – – Should be used for all AB projects Compute NPV of all unique costs over performance period – Establish process w/ industry input – – Include LCCA bid adjustment in project specs Should not include non-agency costs • • User delay costs Vehicle operating costs • Environmental costs. Etc 24
Question 7 Administration of AB
Commodity Price Adjustment – Not desirable • Difficult to administer equal treatment • May result in in different levels of material cost risk 25
Question 7 Administration of AB
Quality Price Adjustments – If used, • Provide similar incentives/disincentives for all alternate pavement types 26
Question 7 Administration of AB
Material Quantities – Pay items based on weight/mass may result in cost overruns – Recommend agency establish process to monitor costs to prevent any systematic bias 27
Question 7 Administration of AB
Approvals – Title 23 U.S.C. 112 FA construction contracts awarded based on lowest responsive bid – SEP 14 Innovative Contracting • Evaluated use of alternate pavement type bidding using LCCA bid adjustments – Approval of LCCA bid adjustments no longer required per Nov 8, 2012 memo 28
Question 7 Administration of AB
Change Orders – Should not allow post-award change order for pavement type 29
Question 8 Program Effectiveness
Monitor number of bidders and unit cost of projects Solicit input from respective pavement industry groups 30
Question 9 Reference Materials
NCHRP Report 703 dated November 2011, Guide for Pavement Type Selection
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_703.
31
Questions
Gary Crawford Pavement Design and Analysis Team Tele: (202) 366-1286 E-mail: [email protected]
32