Transcript Main Title

ERP Project Status Report
for CFC
Apr 2014
Ganda ERP Project |
Current ERP Project Progress and Achievements
•
CG ERP Jan-2014 accounting period have been generate 1st ERP Financial Report on 07th-Mar2014. Feb-2014 accounting period month-end activities have been completed, Now is processing
Mar-2014 accounting period month-end activities.
•
SAG ERP Jan-2014 accounting period month-end closing process was complete, now is doing
cost value check and fine tune for Feb-2014. At the same time Mar-2014 month-end process have
been started.
•
Motive Mulia ERP project have already been kick-off on 11-Mar-2014 and complete operation
process survey and diagnostic process on 14-Mar.
•
The BI implementation process will be started on 17-Mar-2014.
•
The EFGP implementation process will be started on 11-Apr-2014.
•
CFC Core Process Module (list below) customization for 1st Round Operation Simulation Testing
have been delivered and do customization training on mid of Apr-2014
(Purchasing, Inventory, Sales & B2B, Logistic & FG Warehouse, Production, Financial)
•
Key User Examination have been executed for Core Process Modules
(Maintenance, QC, Elec Power, SMS will be May-2014, and HRM will be June-2014 )
•
CFC ERP 1st Round Operation Simulation Testing will be start on 22-Apr-2014.
Ganda ERP Project |
1
Ganda Project Consultant Man Day Usage
Ganda ERP Project |
Ganda Project System Analyst Man Day Usage
Ganda ERP Project |
ERP Project Milestone 2014
Jan
Feb
Mar
Apr
20/3
15/4
May
June
July
Aug
Sep
Oct
Nov
Dec
CG Month-end Closing
1.Check Up
2.Reconciliation & Report
20/2
10/5
05/6
05/7
20/8
15/8
05/8
CFC Cement
1.UAT & Training
2.Basic data preparation
3.Operation Simulation
4.Launch
Phase 2 development
RMC
& Transport
1.
Survey
& Diagnosis
1.Design
& Development
2.
Application
Training
2.Basic
data Training
preparation
3.
Operation
3.UAT
4.
S.O.P. Modeling
4.Training
5.
Gap Analysis &
5.Launch
Customization
6.
HRM
Application
AASTAR
/ WHI
Training
/Gap
1.Basic data preparation
Analysis
2.Training
3.Launch
CFC – Cement
Kick off 1/07/2013 – Go-Live 1/7/2014
(Operation Simulation Testing : 1st Round 15/4 ; 2nd Round 12/5)
RMC – Motive Mulia
Kick off 11/3/2014 – Go-Live 1/10/2014 (All of RMC)
Transport - ANP
Kick off 10/6/2014 – Go-Live 1/11/2014
AASTAR / WHI
K-off 12/05 – Go-Live
01/07
BI
1.Workshop
2.Design &
Development
3.UAT
4.Launch
Business Intelligence
Kick off 18/3/2014 – Go-Live 01/07 2014 (Pilot)
Easy flow (EFGP)
1.Design & Develop
2.UAT
3.Launch
HR
1.Payroll
2.ESS
Easyflow (EFGP) / Online approval
Kick off 14/4/2014 Go-Live 01/07 2014
Payroll
Kick off 05/2/2014 – Go-Live 01/06/2014 (CG)
ESS (Employee Self Service) – Integrated with EFGP
Kick Off 14/4/2014 – Go-Live 01/07/2014
Ganda ERP Project |
The Schedule to Go-Live for CFC
Nov-2013
Dec-2013
Jan-2014
Feb-2014
Apr-2014
Inventory
Sales
Logistic / FG
Warehouse
Production
Maintenance
Finance &
Accounting
May-2014
June-2014
Simulation Testing 50% (12-May)
Simulation Testing 10% (22-Apr)
Purchasing
Mar-2014
G
O
L
I
V
E
Aug-2014
ERP Go Live
ERP Go Live
Human Resouce
Customization
July-2014
Basic Data upload
Test / Simulation
End User Training
Parallel Test Run
Ganda ERP Project |
Progress update
Module / Function
Purchasing
System
Progress Update
Next Plan
1. All of Purchasing procedure have been
trained and processed in CFC ERP
environment. except GR integrated with
LiGu weight-sacle. (There are some
outstanding issues and will be updated
the status next session.)
1. Recheck all the basic data for
CFC-TKP & CFC-HPGP.
2. Key User Examination have been done,
Key user can process the system
procedure well and smoothly by
themselves.
3. Deliver GR (Good Receiving)
integrated functions with LiGu
with current confirmed spec on
May-2014.
3. Ready to execute 1st Round operation
Simulation Testing
Q : Does Item 3 LiGu Integration
spec will be impacted by new
LiGu database structure ?
2. Outstanding Issues should be
solved or have work around
solution.
Basic Data
User Skill
 Already Confirmed current
integration spec is using new
DB structure data. (24-Apr)
Ganda ERP Project |
6
Progress update
Module / Function
Inventory
System
Basic Data
User Skill
Progress Update
1. All of Inventory procedure have been
trained and processed in CFC ERP
environment.
2. Key User Examination have been done,
Key user can process the system
procedure well and smoothly by
themselves.
Next Plan
1. Recheck all the basic data for
CFC-TKP & CFC-HPGP.
(Item’s CoA attribute should be
maintained)
 CFC MIS done already before
23-Apr !
3. Ready to execute 1st Round operation
Simulation Testing
Ganda ERP Project |
7
Progress update
Module / Function
Sales & B2B
System
Basic Data
User Skill
Progress Update
Next Plan
1. B2B interface should have Vietnamese
( MIS will continue to replace Simplify
Chinese to Vietnamese )
1. Recheck all the basic data for
CFC-TKP & CFC-HPGP.
(especial for CFC-HPGP)
2. All of Sales & B2B procedure have been
trained and processed in CFC ERP
environment. (There are some
outstanding issues and will be updated
the status next session.)
2. Outstanding Issues should be
solved or have work around
solution.
3. Key User Examination have been done,
although TPK user can process the
system procedure by themselves,
but suggest to do continue practice to
enhance the process speed. (not familiar)
(Due to HPGP join the training from
Logistic (L/N,…), so Sales & B2B still
can not process)
3. Sales Customization Report
(6pcs) Spec will be provide on
30-Apr and need to be confirmed
.
4. Develop Training Schedule for
External user for new B2B
interface (Agents, Carriers,..)
4. Ready to execute 1st Round operation
Simulation Testing
Ganda ERP Project |
8
Progress update
Module / Function
Logistic & FG Warehouse
System
Basic Data
User Skill
Progress Update
1. All of Logistic and F/G Warehouse
procedure have been trained and
processed in CFC ERP environment.
(There are some outstanding issues and
will be updated the status next session.)
2. Key User Examination have been done,
although TPK user can process the
system procedure by themselves,
but suggest to do continue practice to
enhance the process speed. (not familiar)
(Due to HPGP join the training from
Logistic (L/N,…), the learning effect are no
good for HPGP, they still need more
practice to familiar new system and
process)
Next Plan
1. Recheck all the basic data for
CFC-TKP & CFC-HPGP.
(especial for CFC-HPGP)
2. Outstanding Issues should be
solved or have work around
solution.
3. Logistic & Warehouse
Customization Report (4pcs +
2pcs) will be provide on 25-Apr
(4pcs) and 30-Apr (2pcs), and need
to be confirmed.
3. Ready to execute 1st Round operation
Simulation Testing
Ganda ERP Project |
9
Progress update
Module / Function
Production
System
Basic Data
User Skill
Progress Update
1. All of Production procedure have been
trained and processed in CFC ERP
environment. (There are some
outstanding issues and will be updated
the status next session.)
2. Key User Examination have been done,
Both TPK & HPGP user can process the
system procedure well and smoothly by
themselves.
3. Ready to execute 1st Round operation
Simulation Testing
Next Plan
1. Recheck all the basic data for
CFC-TKP & CFC-HPGP.
2. Outstanding Issues should be
solved or have work around
solution.
3. Packing and Production
Customization Reports
(7pcs+6pcs) Spec will be provide
on 24-Apr (7pcs) and 30-Apr
(6pcs), and need to be confirmed
.
Ganda ERP Project | 10
Progress update
Module / Function
Equipment Maintenance
System
Progress Update
Next Plan
1. Maintenance Customization Module have
been develop and deliver to CFC.
1. Equipment Maintenance basic
data preparation and upload into
ERP DB.
2. Maintenance Module Basic Data
preparation had been explained on 19Mar-204 by Mr. Nick.
2. Maintenance Module Training will
be hold on May-2014.
Basic Data
3. Due to priority consideration (for 1st
Round Simulation Test), we postpone the
Maintenance Module from Apr-2014 to
May-2014.
Ganda ERP Project | 11
Progress update
Module / Function
Finance & Accounting
System
Basic Data
Progress Update
Next Plan
1. Dual Currency have conclusion and
already release to programming.
1. Recheck all the basic data for
CFC-TKP & CFC-HPGP.
2. All of Financial & Accounting
procedure can be process well in
CFC ERP environment, except for
Invoicing for shipment about 100%
Deposit Order.
1. To revise program for Invoicing
for shipment about 100%
Deposit Order on May-2014.
User Skill
3. Key User Examination have been
done, but the result are no good,
AP & AR user still can not process
the new procedure by themselves,
still need more and more practice.
4. Ready to execute 1st Round
operation Simulation Testing
2. Deliver Dual Currency Solution
and do customization training
on May-2014 (2nd Round Testing)
3. FIN Customization for
Vietnamese Description input
(186) & Dual currency (250).
Total costs about 416
programming hours !
Ganda ERP Project | 12
Progress update
Module / Function
Cost Accounting
System
Basic Data
Progress Update
1. Dual Currency Solution for Cost
Accounting have been confirm and
now developing customization spec.
2. Because of this additional level
process need to auto generate related
transaction from system. That will
cause additional customization
charge (88 hours).
Next Plan
1. Deliver Dual Currency Solution
for Cost Accounting and do
customization training on May2014 (2nd Round Testing)
2. Additional customization
charge for Cost Accounting
88 programming hours should
be confirmed.
Ganda ERP Project | 13
Progress update
Module / Function
Q.C Reports
System
Progress Update
1. All of QC Spec have been confirmed on
Mar-2014.
Next action Plan
1. QC Module will be hold on May-2014.
2. Current QC customization module now is
under programming and expect to deliver
to CFC on 12-May-2014.
Basic Data
Module / Function
Electric Power
System
Progress Update
1. All of Electric Power Spec have been
confirmed on Feb-2014.
Next action Plan
1. Electric Power Module will be
hold on May-2014.
2. Current Electric Power customization
module now is under programming and
expect to deliver to CFC on 12-May-2014.
Basic Data
Ganda ERP Project | 14
Progress update
Module / Function
SMS
System
Basic Data
Module / Function
Customization Reports
System
Basic Data
Progress Update
Next action Plan
1. SMS Customization Spec have
already delivered to CFC on Mar-2014.
1. Doing CFC SMS Modem Compatibility
Testing on May-2014.
2. SMS Platform and SMS Service
Message Program have been develop
(and revised).
2. CFC SMS Customization Technical
Transfer on June-2014.
3. Now is testing SMS Modem
integration function.
Progress Update
1. Have already provide 25
customization Reports Spec to CFC
confirmed on 05-Apr.
2. There are some delay on remaining
customization reports , and Digiwin
should to catch-up the schedule.
( Original Plan (52 RPTs) : 28/3 : 25
RPTs ; 5/4 : 10 RPTs; 11/4 : 8 RPTs ;
18/4 : 5 RPTs ; 25/4 : 4 RPTs )
Next action Plan
1. To catch-up delay schedule and
provide Cust. reports Spec as below:
on 24-Apr :
a. Packing Report
(7pcs)
b. Elec Power Report (4pcs)
c. Logistic Report
(4pcs)
on 30-Apr :
d. Sales Report
(6pcs)
e. Production Report (6pcs)
f. Warehouse Report (2pcs)
Ganda ERP Project | 15
Progress update
Module / Function
HRM & ESS
System
Basic Data
Progress Update
Next action Plan
1. All of HRM confirmation spec have been 1. Provide P/S Bonus Spec to confirm
before 02-May-2014.
provide except P/S Bonus Spec.
( P/S Bonus will be separate into
P/S bonus parameters P/S Bonus
2. CFC Organization Data already upload
Calculation and P/S Bonus )
into HRM System.
 should provide some scenario
sample together for easy confirm.
3. Basic Salary formula already been
setting
2. HRM Customization Progress, and
4. Waiting CFC Sign-back customization
Spec. (annual leave,…)
 (1) Customization hours need
provide Standard HRM function to
confirmed & review.
(2) Due to Offset Leave logic is quite
complex, those Spec need provide
scenario data to explain current
design.
start to deliver from end of May-2014.
3. Checking HRM Go-Live Strategy :
(1) HRM Go-Live first (01-July) , then
ESS Go-Live Second step.
(2) HRM + ESS Go-Live at same time
(will impact original HRM 01-July
Go-live Schedule, the expect
Parallel testing on Aug-2014, and
go-live on Sep-2014)
 Already Confirmed HRM go-live
first on 01-July-2014; and then
ESS go-live on 01-Sep-2014
(ESS From no need to integrated
with EFGP, but need to discuss
ESS Form validation logic.
Ganda ERP Project | 16
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Purchasing
1. GR weight-scale & belt-scale
Integration will be put on Phase-I
(Plan to deliver on May-2014)
1. Goods Receiving Qty -> LiGu Scale ->
Stock In -> QC Moisture -> Price Qty
 Price Qty OK !
2. PR Priority should can choose Urgent
/Prompt /Ordinary/Overhaul
 Will be provided before 05-May.
3. Please open the application for the new
Vendor basic data.
 will be setting before 02-May.
Inventory
1. Warehouse Voucher Report
customization already Finished !
1. Please open the application for the new Item
master.
 will be setting before 02-May.
2. Please open the maintain Item application.
 will be setting before 02-May.
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Sales
1. Sales Module Report 1 (Finish Goods,10Rpts) 1. Web user creation.
will be delivered before 15-May-2014.
 Can Use axmi250 can create
Web user
2. Sales Module Report 3 (Marketing, 5 Rpts)
Customization Spec will be provide 30-Apr,
2. B2B Toolbar how to change to
and those reports will expect to delivery on
the Vietnamese language
10-June-2014.
 Checking now, will be reply
before 01-May.
3. L/N input truck ID/Ship ID,
providing query function
 We suggest if want to provide
Query, should create internal
CFC truck data first.
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Logistic
& Warehouse
1. Sales Module Report 2 (Logistics, 4 Rpts),
Customization Spec will be provide 25-Apr,
and those reports will expect to delivery on
10-June-2014.
1. L/N document type (LNHP/ LNHN...)
2. The Warehouse Report (2 Rpts) will be
delivery on 20-June-2014.
(Raw material daily report (cimr101) &
Daily report on receiving of material by
belt scale (cimr102)
should be auto come base on
schedule
 this function so far can not
provide.
2. Reference unit (detail part) should
be default “BAG”
Now system according the setting
of item Bag or Bulk in Item master.
if Bulk, default use TON is makesense. We suggest if bulk cement
use TON as unit just the same
with CG now.
3. Delivery date (in detail part) still
could not be changed
 for LN type = X (jetty), can
change date in detail!
the other LN type do not
provide this function.
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Logistic
& Warehouse
(continue)
4. In detail part – commit 2nd line still
need typing (could not select as 1st
line) some items (Product No. ,
Warehouse,)
 So far not yet provide this f
unction. Suggest do this fine
tune on May.
5. L/C – Cxmp220t have 2 remain
minor Issues email at 21-Apr
 Checking now, will be reply
before 01-May.
6. D/N – Cxmt628 have 2 remain
minor Issues email at 21-Apr
 Checking now, will be reply
before 01-May.
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Production
1. Production Daily Report Part 1 (3Rpts)
1. Factor figure should have special
authorized then can changed. & R/C
( RM/Clinker ) radio figure should
have special authorized then can
changed.
 Suggest not do like this way
because now just input one
time each day.
 Mr. Alex will double check with
users is OK or not !
will be delivered on 15-May.
2. Production Daily Report Part 4 (Packing,
4Rpts) cust. spec will be provide 25-Apr,
and those reports will expect to delivery on
30-May-2014.
3. The Other Production Reports (including
HPGP, 6 Rpts) ) cust. spec will be provide
30-Apr, and those reports will expect to
delivery on 20-June-2014.
2. Kiln feeding Qty can write back to
the raw mill material issue qty.
 if no any concern, Will
provide this function soon.
3. Down time will not limited one day
1440 min., but when print out the
report will show up the total down
time and operation time.
 Conclusion no need to do this
in last week meeting
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Production
(continue)
4. Insert one column for the currently
storage Qty in the WIP interface
 OK, we will provide this.
5. Production schedule input should
provide the Replicate function..
OK,we will provide this.
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Financial &
Accounting
1. Dual Currency Customization Spec
have been confirmed.
1. FIN Customization for Vietnamese
Description input (186) & Dual currency
(250). Total costs about 416 programming
hours !
2. Dual Currency Customization will be
delivery on 12-May-2014.
3. Dual memo for Accounting transaction
customization will be delivered from
12-May-2014 to 20-May-2014.
4. Tax Declaration customization will be
expected to delivered on June-2014.
Cost Accounting
1. Dual Currency Cost Accounting Spec
will be provide on 05-May, and will be
expected to delivered on 30-May-2014.
1. Additional customization charge for Cost
Accounting 88 programming hours
should be confirmed.
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Maintain
1. Customization Module have been
developed, Waiting Training.
(May-2014)
None
Electric Power
1. Customization Program will be delivered and
trained on May-2014. (12-May)
None
QC Report
1. Customization Program will be delivered and
trained on May-2014. (12-May)
None
SMS Module
1. Customization Module have been
developed, Waiting Integration Test.
(May-2014)
None
Customization
Reports
(50 reports)
1. Customization Report will be delivered from
May-2014 to June-2014.
 Need to re-prioritize the customization
reports to ensure all of A class reports will
be provided before 31-May-2014.
 All of other reports CFC wish can received
before 06-June-2014. (Digiwin will check it)
None
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Human
Resource
1. HRM system upgrade will be complete
on mid-of-May (1 week delay)
1. P/S Bonus Spec will be provide on 02-May.
 HRM module
now is high-risk
module due to
customization
schedule.
2. HRM Operational function
customization will be delivered from
19-May-2014 to 16-June-2014,
except Shift Table Upload (will be
delivered on Aug-2014)
3. HRM Customization Report will be
delivered from 16-June-2014 to 18July-2014.
2. Signed back the customization documents
for Annual Leave related customization.
-Digiwin need provide some supporting
data for spec confirme.
3. Currently procedure in HRM Training
Module will be revised into another way after
September, so we have to make sure do we
need to customize it before change the
procedure, or we want to move the training
modules on Sep-2014.
4. Do we need to launch ESS+ Easyflow on
first of the july? If yes, we need to
reschedule the implementing plan of HRM.
--> Already confirmed HRM Go-Live First !
5. ESS can't handle the function to upload shift
table, so it will be change to Easy Flow
upload the shift table. But we got some issue
have to confirm, that's customizaion period
and go live period.
 Digiwin have to find-out alternate way for
01-July-2014 go-live work-around solution
Ganda ERP Project |
Current Status of Customization and Issues
Module
Customization
Outstanding Issue
Human
Resource
(Continue)
6. After requirements meetings, we found that
remain 37 reports need to customize, so if
those report are necessary please help us to
confirm and signed back the confirmation
documents.
 Digiwin will provide HRM standard
Similar report format for CFC evaluation.
 Digiwin will provide HRM Self-Define
Report Document to CFC (Mr. Alex) for
assessment if there is any report can be
developing by CFC self;
Ganda ERP Project |
Major Activities of CFC on May-2014
• Maintenance, QC, Elec. Power, SMS customization Training and Testing
• Dual Currency Solution Training and Testing
• 2nd Round Operation Simulation Testing (50% transaction Volume)
• ERP Go-Live and Opening Plan Developing
• Production Environment Preparation
• End User Training
Ganda ERP Project | 27
THANK YOU