Presentation of Phase 0 - University of Delaware
Download
Report
Transcript Presentation of Phase 0 - University of Delaware
Presentation of Phase 3
Monday 12/11/2006
Nick DePompeo, Brian Hufe, Mike
Sacra, Ben Stuchlik
Southco
Over the past 60 years, Southco has
grown through innovation, strategic
acquisitions and overseas investments into
a global leader in Engineered Access
Hardware.
DZUS quarter-turn fasteners provide quick,
effortless access/fastening for military and
aerospace applications.
Project Scope Definition
To accurately design and manufacture
an interface between an MTS machine
and required fasteners to produce an
efficient and safe testing process for
all required tests.
Current Process
Utilizes 3 machines
Utilizes compressed air
Requires skilled, trained operator
Tensile, shear and torsional tests are performed
Tensile/Shear
Fastener Testing
Torque
Fastener Testing
Tensile/Shear
Receptacle Testing
Why Change?
Three required machines to run tests
Extensive Testing time
Repetitive Testing Process
Testing process may be inaccurate
Southco has an MTS machine available
Customer Wants
Decrease skill requirement of testing
procedure
Decrease testing time
Maintain testing safety standards
Develop an interface with available
MTS Machine
Increase repeatability and accuracy
Metrics
Number of machines
Testing time
Accuracy
Repeatability
Durability
Benchmark-Target Value Comparison
Benchmark Values
Target Values
1) 3 Machines
1) 1 Machine (MTS
Machine)
2) Approximately 8-9 hours
2) Less than 4 hours per lot
3) Unknown
3) 10% more accurate
than what is being tested
4) Unknown
4) 10% more repeatable than
current process
5) N/A
5) Operational for a minimum
of 10 years
Selected Concept:
Single
interface
for all tests
Reduced
setup time
between
tests
Easily
allows for
“nesting”
feature
Key Pieces
1)
2)
3)
4)
Top U Piece
Bottom U Piece
Nesting
Rotator Pieces
1
4
2
3
Assembly Model
Nesting
Nesting allows for adaptation. New
fasteners may be tested through the
use of new nesting pieces.
Locking/Unlocking Fastener
Shear to Tensile Test Re-Positioning
Design Schematic
Testing Procedure
1)
2)
3)
4)
Attach interface to MTS machine
Load TestWorks and initialize test
Calibrate machine
Performed 3 trials of testing for 3fastener lots using required testing
order
5) Record data and analyze results
Testing Results
Interface works as intended.
Testing time reduced to target value.
Test Validation- Ease of Use
Current System:
Requires three Machines
New System:
Requires 1 Machine
Test Validation- Testing Time
Current testing time take approximately 8 hours per lot
Testing Time has been reduced by approximately 4 hours
Test Validation- Accuracy
Load Cell is much
more accurate than
the current
compressed air
system which can
have leaks.
The new system is
calibrated every
time a new testing
shift begins.
Test Validation- Repeatability
Testing showed a
high degree of
repeatability.
Testing time had a low
std. deviation
Value to Southco
Decreased testing time
More lots can be tested in a given time.
Set testing procedure
Detailed step-by-step procedure
Minimizes operator skill requirements
Takes up less space
Project Costs
Implementation Plan
Southco will be provided with the
interface and necessary
hardware/software.
Southco will be provided with a
detailed operations manual, including
engineering drawings.
Southco will be provided with a firsthand training session for operators.
Financial Payback
Skilled operator salary: $30/hr
Current Test Time:
8.5 hr
Tests per day:
1 test
=
$255.00 per test
Skilled operator salary: $30/hr
New Test Time:
4.5 hr
Tests per day:
1 test
=
$135.00 per test
Estimated Savings = $120.00 per test
At a total cost of $2410.85, it would take
Southco approximately 20 days of testing to
completely pay off the new testing system.
Questions?