PDO, PROJECT MONITORING INDICATORS AND IMPLEMENTATION SUPPORT
Download
Report
Transcript PDO, PROJECT MONITORING INDICATORS AND IMPLEMENTATION SUPPORT
Karnataka Watershed Development Project – II
Implementation Support Mission
and Partner Summit
October 6-11, 2013
Preparation – January 2011 to June 2012
(18 months)
Negotiations – July 2012
(19 months)
Board Approval - September 2012
(21 months)
What does this mean?
Project took far longer than
average for Board approval
and effectiveness
Project disbursements are
already behind estimates in
PAD at Board approval
Senior management is
following implementation
progress carefully
Loan Signing – February 2013
(26 months)
Effectiveness – May 2013
(29 months)
Implementation Support
(From May 2013 to 2018)
The Project
Development
Objective (PDO) is to:
Demonstrate more
effective watershed
management through
greater integration of
programs related to
rainfed agriculture,
innovative and science
based approaches, and
strengthened institutions
and capacities.
Importance?
At closure, Bank will gauge
project success against the
PDO using higher level and
several intermediate level
indicators
We need to ensure good
M&E system is in place to
deliver information on
these indicators on a
regular basis
Indicator One: New science based approaches
and tools adopted into wider watershed
operations (innovation)
Indicator Two: Improved M&E capability in WDD
(strengthened institutions)
Indicator Three: Incremental change in
agric/horticulture productivity in project areas
for selected crops (watershed management)
Indicator Four: Percentage of micro-watersheds
with improved convergence and integration
(integration)
Mandatory Bank process to
review progress and support
implementation
Minimum of every six
months, more with problem
projects
Client prepares status
report ahead of mission
During mission:
Progress reviewed overall +
progress in each component
FM and procurement
Disbursements and projections
Key issues and actions agreed on
Share ideas for improvement
Wrap up with client
Importance?
Team must process an aide
memoire, management
letter (for client) and ISR
(for Bank) two weeks after
mission
Bank management carefully
review the internal ISRs
Expect candor and well
defined actions
Expect ratings to reflect
disbursement patterns
Project Size:
Assistance:
Disbursements:
$85.7 million
$60.0 million
Karnataka
held in high regard for watershed
management
Build on work to date with implementation
Focus on procurement and getting the key
partners on board - CRITICAL
Start moving with M&E as per Results
Framework in PAD
Remember that projects bring flexibility in
addressing PDO and implementation issues
Communication is key – Bank is there to
provide support and ideas