PDO, PROJECT MONITORING INDICATORS AND IMPLEMENTATION SUPPORT

Download Report

Transcript PDO, PROJECT MONITORING INDICATORS AND IMPLEMENTATION SUPPORT

Karnataka Watershed Development Project – II
Implementation Support Mission
and Partner Summit
October 6-11, 2013
Preparation – January 2011 to June 2012
(18 months)

Negotiations – July 2012
(19 months)

Board Approval - September 2012
(21 months)
What does this mean?

Project took far longer than
average for Board approval
and effectiveness

Project disbursements are
already behind estimates in
PAD at Board approval

Senior management is
following implementation
progress carefully

Loan Signing – February 2013
(26 months)

Effectiveness – May 2013
(29 months)


Implementation Support
(From May 2013 to 2018)

The Project
Development
Objective (PDO) is to:
Demonstrate more
effective watershed
management through
greater integration of
programs related to
rainfed agriculture,
innovative and science
based approaches, and
strengthened institutions
and capacities.
Importance?

At closure, Bank will gauge
project success against the
PDO using higher level and
several intermediate level
indicators

We need to ensure good
M&E system is in place to
deliver information on
these indicators on a
regular basis
Indicator One: New science based approaches
and tools adopted into wider watershed
operations (innovation)
 Indicator Two: Improved M&E capability in WDD
(strengthened institutions)
 Indicator Three: Incremental change in
agric/horticulture productivity in project areas
for selected crops (watershed management)
 Indicator Four: Percentage of micro-watersheds
with improved convergence and integration
(integration)





Mandatory Bank process to
review progress and support
implementation
Minimum of every six
months, more with problem
projects
Client prepares status
report ahead of mission
During mission:






Progress reviewed overall +
progress in each component
FM and procurement
Disbursements and projections
Key issues and actions agreed on
Share ideas for improvement
Wrap up with client
Importance?

Team must process an aide
memoire, management
letter (for client) and ISR
(for Bank) two weeks after
mission

Bank management carefully
review the internal ISRs

Expect candor and well
defined actions

Expect ratings to reflect
disbursement patterns
Project Size:
Assistance:
Disbursements:
$85.7 million
$60.0 million
 Karnataka
held in high regard for watershed
management
 Build on work to date with implementation
 Focus on procurement and getting the key
partners on board - CRITICAL
 Start moving with M&E as per Results
Framework in PAD
 Remember that projects bring flexibility in
addressing PDO and implementation issues
 Communication is key – Bank is there to
provide support and ideas