WP2.2 CoDR PAF introduction

Download Report

Transcript WP2.2 CoDR PAF introduction

AAs in PEP
Jan Geralt Bij de Vaate
PEP
• Project Execution Plan for the pre construction
phase of the SKA
•
•
•
•
Consortium to be formed
AA-low ready for construction
AA-mid part of the Advanced Instrumentation Program (AIP)
2012-2016
Allocation of Requirements from System
to Element level
System Level (SPDO/SPO)
System
RR
1
Element Level (WPCs)
2
Pre-Stage 1
Element
SRR
• 1st allocation is science requirements, operations requirements
(Instrument Requirements Review).
• Later allocations are extensibility requirements and non-functional
requirements.
Assembling Element Level RFPs for Stage 1 Work
Assemble Work Package Consortia
Define Top-level WBS
Pre-Stage 1
Planning Element 1 CoDR-SRR Work
Planning Element 2 CoDR-SRR Work
SoW
RFP
Planning Element N CoDR-SRR Work
Develop Stage 1 Legal, Bid Policy, T&C Contract Templates
Nov/11
Apr/12
Bid
review
Stage 1
Element
MoAs
Jun/12
AA SoW writing team
AA SoW
• Draft WBS created
• SoW writing started
• Full draft by mid Jan.
AA Consortium
AA Consortium
board
WP Mgt
System
Engineering
AA-low
AA-mid
receptor
AA Consortium
WP Mgt
System
Engineering
AA-mid
receptor
AA-low
System Design
Front-end
array
Signal
processing
Verification
systems
Infrastructure
pre Consortium
•
•
•
•
•
•
•
•
INAF
Oxford University
Manchester University
Cambridge University
Obs Paris (Nancay) / Univ. of Bordeaux
ICRAR
Raman Research Institute
ASTRON
– Aperture Array Design and Construction Consortium: AADC2..?
Consortium
Stage 1 ?
Work package
Consortium
Participating
Org
Participating
Org
Industry
Industry
Stage 2 ?
-IP issues
-Funding/budgets
Work package
Consortium
Industry
Participating
Orgs
Pre Consortium
• Telecons and meeting in Perth (Aug/Sept 2011)
• This Friday focus on AA-mid
• Meeting in Manchester during/after the SPO gathering
– Second half of 30th Jan- 3rd Feb week
• Letter of Intend proposal drafted
• Composing the bid on AA work package April/May 2012
• Start 1st July 2012
General AAVS Schedule
AA-low
Small array demonstrators
AAVS0
2011
Technology demonstrator
AAVS1
2013
SKA1 full pre-production prototype array
AAVS2
2015
SKA1 manufacturing data package
AA-mid
2016
Individual tile demonstrators
AAVS0
2011
Single array performance demonstrator
AAVS1
2013
Multi-array interferometer performance demonstrator AAVS2
2016
SKA2 capable costed design
2016
AA-low Demonstrators
Array Scale
Site
Purpose & Comments
AAVS0
AA-low 16 elements
2011/2
Local
Prove electromagnetic performance in small
array. Multiple arrays
AAVS1
256
AA-low
elements
2013/4
Selected SKA
site strongly
preferred.
Single station showing beam performance and
the limits of analogue power requirements
Selected SKA
site.
Multiple stations, similar to AAVS1, to show
imaging performance. Final proving for SKA2.
Small numbers of beams for processing reasons.
NOT a science instrument
,000’s of
AAVS2
elements in
AA-low
single or
2015/6
multiple arrays
AAVS2 science capable
AA-mid Demonstrators
Array Scale
Site
Purpose & Comments
AAVS0
AA-mid ~1m2 tile
2011/2
Test chambers/
EMBRACE
For ORA: prove concept and LNA interface
For Vivaldi: refine array and manufacturing
techniques
AAVS1
AA-mid 256 clusters
2013/4
Selected SKA
site strongly
preferred.
Single station showing beam performance and
the limits of analogue power requirements
Selected SKA
site.
Multiple stations, similar to AAVS1, to show
imaging performance. Final proving for SKA2.
Small numbers of beams for processing reasons.
NOT a science instrument
AAVS2
Single or array
AA-mid
of stations
2015/6
AAVS2 science capable
Milestone/Event
Event
list…..
Jan 2010 AAVP start
Date
Remarks
April 2011 AA CoDR
Aperture Array system, AA-low and AA-mid, Concept design
review
Nov. 2011 AA dCoDR
Aperture Array delta concept design review of the AA-mid
Q1 2012 AAVS0 completion and test
Testing of the various small array test systems
April 2012 AAVP final report for PrepSKA
Consolidated findings from the PrepSKA work
Q2 2012 SKA site selection
Q2 2012 AAVS1 PRR
Production readiness for a small AAVS system
Q3 2012 Start AAVS1 construction
Build AAVS1 on SKA site
Q1 2013 AA- SRR
SKA2 System Requirements Review for the AA-mid
Q1 2013 Start AAVS1 commissioning
Start test and evaluation process
Q2 2013 AAVS2 PDR
Q3 2013 AAVS2 CDR
..
Covers both AA-low and AA-mid
AAVS Funding
• Self funded by the AA consortium
• Material AAVS1: 1M€
• Material AAVS2: 5M€
– PEP numbers..
Notes
• A site decision delay impacts AAVS1/2
• SKA site needs to be ‘happy’ to host AA Verification Systems
• Significant step needed from pathfinders to SKA1
– Tight schedule
• Connect to deliverables of STaN, Computing and Software?
• Interference with pre-cursors?
• Need to tackle outstanding issues with existing team up to
1st July 2012
– AAVS0 design, build and evaluation, AA-station specification/design