2014 Campus Construction

2015 Campus Construction Projects Summer Impacts May 1, 2015

Table of Contents

• • • • • Overview Map of Projects Project Details By Campus Quadrant Electrical Infrastructure Project Impacts Parking & Transportation Update Miscellaneous Disruptions

NW NE 3 7 1 2 1 27 23 22 21 26 1 10 11 4 5 12 6 8 9 14 20 13 18 15 17 28 24 16 1 25 19

Construction Projects

1. Electrical Duct Bank 2. Hwy 93 Sanitary Sewer 3. Campus Beach 4. Kingsmore Stadium 5. Little John Renovation 6. West Campus Energy Plant 7. West Campus Satellite Parking 29 8. WEZ Ph III / Suites Renovation 9. Memorial Stadium Suites 10. Printer Site Demolition 11. Advanced Technology Center 12. Centennial Blvd Storm Drain 13. Core Campus 14. Riggs Soccer Field 15. Douthit Hills SW SE 16. Cherry/McMillian Signal 17. Parkway Drive Paving 18. Hardin/Brackett ADA Sidewalk 19. East Campus Satellite Parking Lot 20. Central Energy Facility Boilers 21. Cooper Library North Pavers 22. Watt Innovation Center 23. Freeman Hall Expansion 24. Byrnes Brick Repair 25. Lightsey Bridge Renovations 26. Brooks Center Roof 27. Flour Daniel Roof 28. Hendrix Center Patio 29. Waste Water Treatment N

Northwest Campus

McFadden Jervey 3 7 12 10,11 6 5 2 4

Construction Projects

2. Hwy 93 Sanitary Sewer* 3. Campus Beach* 4. Kingsmore Stadium 5. Little John Renovation 6. West Campus Energy Plant 7. West Campus Satellite Parking 8. WEZ Ph III 9. Memorial Stadium Suites 10. Printer Site Demolition 11. Advanced Technology Center* 12. Centennial Blvd Storm Drain * Projects Starting after Summer ‘15 NW 8,9 N

Northeast Campus

1 14 1 15 20 13

Construction Projects

13. Core Campus 14. Riggs Soccer Field 15. Douthit Hills 16. Parkway Drive Paving 18 16 18. Hardin/Brackett ADA Sidewalk 19. East Campus Satellite Parking Lot 20. Central Energy Facility Boilers* 1. Electrical Duct Banks * Projects Starting after Summer ‘15 19 NE N

1 27 23 22 21 26

Southeast Campus

24 28 16 25 1

Construction Projects

21. Cooper Library North Pavers 22. Watt Innovation Center 23. Freeman Hall Expansion 24. Byrnes Brick Repair 25. Lightsey Bridge Renovations 26. Brooks Center Roof 27. Flour Daniel Roof 28. Hendrix Center Patio 1. Electrical Duct Banks 16. Cherry/McMillian Signal * Projects Starting after Summer ‘15 SE N

Southwest Campus

Construction Projects

29. Waste Water Treatment Upgrades 29 * Projects Starting after Summer ‘15 SW N

Electrical Infrastructure Projects

Scope of Work: Replace electrical infrastructure that has reached the end of its useful life.

• • Many short (hours) and long (days) power outages will be required.

Periodic Parking & Roadway Disruptions will also be encountered.

1. Electrical Duct Bank

Electrical Duct Bank

1. Electrical Duct Bank

D E Electrical Duct Bank Installations Central Campus C Schedule: A. Early Summer B. Early Summer C. Mid Summer D. Late Summer E. Summer/Fall/Available Opportunity N B A

Electrical Outages

• • All campus buildings will be affected briefly by power outages.

A tentative schedule for outages is included here although these are subject to change.

Tentative Electrical Outages

• • • • • • • • • • • 5/8 – 5/10: Freeman Hall 5/16 – 5/17: Sikes and Alumni Center 5/30 – 5/31: McAdams North, Daniel Hall, East Campus Chiller Facility 6/13 – 6/14: P&A Part 1 6/20 – 6/21: P&A Part 2 7/3 – 7/6: Cooper Library 7/18 – 7/19: Barre Hall, McAdams South, Lehotsky Hall, Jervey/McFadden 8/1 – 8/2: Lee II, Lowry 8/8 – 8/9: Sirrine, Riggs, Rhodes 8/28 – 8/30: Brackett 9/19 – 9/20: Hardin, Olin, Trustee House, Fernow (Fernow Possibly Summer) •

Early Summer Outages still to be

determined: Earle Hall, Fluor Daniel, Harris A. Smith, STI, Athletics Facilities in the Bottoms •

Possible outages late in the summer:

Shoeboxes, Stadium Suites

Parking & Transportation Update

• • • 45 additional employee spaces are being designated on Daniel Dr. on May 4, 2015 East & West Employee Shuttles will cease operation Monday, May 4 until further notice 2 ADA spaces will be closed May 11 – Aug. 16 in E-15 (East Library) parking lot

Parking & Transportation Update

• • ROAD CLOSURES Avenue of Champions, between Centennial Blvd & Perimeter Rd, will be closed to all traffic and parking May 11 – Aug 19, 2015 Parkway Drive will be closed to all traffic and parking May 11 – June 1, 2015 Any single day road or parking lot closures will be announced on Parking and Transportation’s website

clemson.edu/parking

• • • • • •

Miscellaneous Disruptions

Campus Steam Outage: May 17 th to May 21 st Long Hall/Campbell Museum Concrete Walks Miscellaneous Summer Road & Crosswalk Restriping Landscape Improvements Projects – Parking Lot Islands C-07, C-09, E-05 Window Seal/Caulk – Earl Hall (June – August) – Strode Tower (June – September) – P&A Building (July – January ‘16) Other Planned Small Roof Projects – Jordan Greenhouse – Rhodes Hall (late summer) – Student Union Repair – Tillman Flat Roof – Hunter Hall & Auditorium (late summer)